OVERALL GOALS
Provide sustainable and reliable water and
•
sewer service meeting or exceeding federal
and state standards.
Deliver clean and safe drinking water to all
•
residents.
Protect and care for the City’s infrastructure.
•
Bring value to the City through new
•
technology and automation.
Take action now to bring financial stability to
•
maintain a high sustainable Level of Service.
Begin and make bi-annual rate studies
•
2
KEY TAKE-AWAY POINTS
Meet all these goals for just an additional
•
$1.58 per month (5¢/day).
More than 20 years since last comprehensive
•
rate study.
Acting now saves money:
•
Avoid additional costs of road closures,
•
impacted businesses, sinkholes, etc.
Avoid regulatory fines and mandated
•
activities
3
PURPOSE OF THE WATER AND SEWER
RATE STUDIES
•Develop a long-term financial plan that projects
operating revenue, expense and capital financing
costs to meet the City’s future needs.
•Propose a capital program that incorporates a risk
evaluation of the City’s assets
•Increase revenue stability for the utilities to support
capital system investments
4
WATER & SEWER UTILITIES
BACKGROUND
Large capital Significant
Provide Heavily
intensive fixed costs
services to regulated by
programs
the 11Federal &
th
largest CA State
Purchased
More than
cityagencies
water costs
$86M
planned
Operate
capital
USEPA,
Increasing
complex water
projects
State WRB,
MWD &
and sewer
over next 5
CA DPH
OCWD costs
systems
years
5
QUICK FACTS -WATER
•500 miles of mains
•Average age: 50 years
•Life expectancy: 40 to 60 years
•Main replacement cost: $943M
•Age pipes breaking: 35 to 45 years
•10 reservoirs, 7 pumping stations, and 19 active wells
•Current replacement rate is
0.5% of system per year
•Industry standard is minimum
of 1% of system per year
•Imported water costs have
increased more than 25% since
last rate adjustment in 2011
6
QUICK FACTS -SEWER
•390 miles of mains
•20 miles of OCSD mains maintained by City
•Average age: 50 years
•Life expectancy: 40 to 60 years
•Main replacement cost: $405M
•Current replacement rate is 0.1% of system per
year
•Industry standard is minimum of 1% of system
per year
•8,000 manholes
•2 lift stations
7
COST BREAKDOWN –FY 15 BUDGET
Approximately 80% of costs are fixed
Sewer Budget
Water Budget
17%
36%
38%
46%
45%
18%
O&M
O&M
Laterals & FOG Programs
Purchased Water
Capital
Capital
8
WATER SYSTEM –DISTRIBUTION BY
INSTALL DECADE
70%
Over 70% of the system installed pre-1980s
9
SEWER SYSTEM –DISTRIBUTION BY
INSTALL DECADE
85%
Over 85% of the system installed pre-1980s
10
WATER SYSTEM PRIORITIZATION
Colored Zones
Total of $119.2 million
13 miles (5% of system) –significant probability of
failure in 5 years
11
PRIORITY WATER MAINS
Older Part
Of City
12
SEWER SYSTEM PRIORITIZATION
Colored Zones
Total of $88 million
44 miles (12% of system totaling $46M) –high likelihood of failure in
5 years
13
PRIORITY SEWER MAINS
Older Part
Of City
14
PROPOSED WATER CIP
2.8% annual increases provides:
•
CIP of $67.8M over 5 years
–
Elimination of main replacement backlog
–
3 miles per year replacement
–
Rehab of Well 32 (currently offline) will increase local supply
–
Requires debt financing of $24M and cash financing of
•
$35M (from revenue adjustments
)
In $000’s
ProjectFY 14/15FY 15/16FY 16/17FY 17/18FY 18/19
AMI3,278.23,376.53,477.83,582.2
Well 32 Rehab
5,177.3
R&R -Annual
5,352.55,057.25,208.8
Inspections
314.81,300.6
R&R -Critical
10,462.23,299.44,505.54,640.78,738.8
Total
$10,462.2$12,244.9$13,059.3$14,476.3$17,529.8
AMI = Advanced Metering Infrastructure R&R = Rehabilitation and Replacement
15
PROPOSED SEWER CIP
8.8% annual revenue provides:
•
CIP of $18.4M over 5 years
–
Elimination of main replacement backlog
–
Target 5 miles replacement/year after FY 18/19
–
Requires debt financing of $13.5M and cash financing of
•
$4.3M
Reserves at 90 days of O&M and $1M emergency fund
•
In $000’s
ProjectFY 14/15FY 15/16FY 16/17FY 17/18FY 18/19
CriticalR&R
1,230.8 2,674.8 3,393.2 1,154.0 2,805.9
Master Plan
300.0 0.0 0.0 0.0 0.0
Inspections
0.0 0.0 0.0 1,241.4 663.0
Non-Collection
System Projects
0.0 0.0 84.7 327.3 399.3
Total
$1,530.8 $2,674.8 $3,477.9 $2,722.7 $3,868.2
R&R = Rehabilitation and Replacement
16
BENEFITS OF ACTING NOW
Maintain level Take advantage
of service of low interest
provided to rates to finance
ratepayersactivities
Avoid increased
costs of
Establish long-
deferring
term financial
activities and
and service
opportunity
viability
costs
17
COST OF DEFERRING CIP
•
American Society of Civil Engineers Reports
“Failure to Act” series examines economic impacts if capital
•
investment is delayed
Road closures, sinkholes
•
Loss of jobs, health & safety issues
•
Costs are in addition to asset replacement and regulatory
•
fines
•
Mandated projects via consent decrees
Annual Water Impacts
Annual Sewer Impacts
HouseholdsBusinessesLocal EconomyHouseholdsBusinessesLocal Economy
$366K $917K$4.46M $129K $324K$1.58M
toToTotoToTo
$1.31M$3.29M$16.00M$1.08M$2.70M$13.12M
18
WATER CASH FLOW
NO ADJUSTMENTS
•
FY 14/15 revenues include refinancing proceeds
19
WATER CASH FLOW
PROPOSED
2.8%
2.8%2.8%2.8%2.8%
•FY 14/15 revenues include refinancing proceeds
20
SEWER CASH FLOW
NO ADJUSTMENTS
21
SEWER CASH FLOW
PROPOSED
8.8%
8.8%
8.8%
8.8%
8.8%
22
TYPICAL MONTHLY BILLS –MARCH 2015
Combined Single Family Residential Bill Increase = $1.58/month (3.1%)
Water
ProposedRates
% Total Meter Usage Current Bill
Customer
AccountsSize(HCF)($/month)
$/monthIncrease ($)
SingleFamily76.7%5/8”15$44.41$45.40$0.99
Commercial9.6%2”50$171.51$199.94$28.43
Industrial0.18%6”500$1,707.61$1,899.11$191.50
Sewer
ProposedRates
% Total Usage Current Bill
Customer
Accounts(HCF)($/month)
$/monthIncrease ($)
SingleFamily80.9%15$5.18$5.760.59
Commercial7.6%50$17.25$16.41($0.84)
Food Services2.5%50$17.25$33.81$16.56
Industrial0.19%500$172.50$153.30($19.20)
23
TYPICAL SINGLE FAMILY RESIDENTIAL
COMBINED MONTHLY BILLS
24
WHAT ELSE CAN YOU GET FOR 5¢ A DAY?
½ a gallon of
regular unleaded
gasoline
1/3 of a
Less than ½ a
3/4 of a Coke
Grand Latte
gallon of milk
25
COMPARISON TO OTHER CITIES –WATER
26
COMPARISON TO OTHER CITIES –SEWER
27
COMPARISON TO OTHER CITIES –
COMBINED
28
NEXT STEPS
Present to Council and direct staff to proceed with
report recommendations (December 2, 2014)
Written (Prop 218) Notice of rate adjustments to be
mailed to parcel owners
Citywide town hall meeting on proposed rate
adjustments
City Council to hold a public hearing to consider all
written protests against the proposed charge.
(February 17, 2015)
If a majority of parcel owners do not object, the new
rate adjustment will become effective. (March 1,
2015)
29
City of Santa Ana
THANK YOU
PROP 218 NOTICES
•
Must include:
The amount of the charge
The basis of the charge
The basis upon which the amount of the
proposed charge was calculated
The reason for the charge
The date, time, and location of a public
hearing, which is to be held not less than 45
days after the notice is mailed
31
PLANNED OUTREACH
Written (Prop 218) Notice of rate adjustments to
be mailed to parcel owners
Upload presentation and reports to City website
Presentation to Com-Link on proposed rate
adjustments
Issue a Press Release
Informational inserts to be included along with
bills
Presentations at neighborhood association
meetings
32