HomeMy WebLinkAbout80A - JOINT - SA PEEBLER AGMTREQUEST FOR
COUNCIL /
SUCCESSOR
AGENCY ACTION
CITY COUNCIL MEETING DATE:
MAY 19, 2015
TITLE:
SECOND AMENDMENT AND EXTENSION OF
SETTLEMENT AGREEMENT AND MUTUAL
AND GENERAL RELEASE WITH GERALD
PEEBLER FOR THE CONSTRUCTION OF
PUBLIC IMPROVEMENTS WITHIN THE
SOUTH MAIN CORRIDOR
{ST77?W
C.
CITY MANAGER
RECOMMENDED ACTION
CITY COUNCIL ACTION
CLERK OF COUNCIL USE ONLY:
UT-J-7561wk
❑ As Recommended
❑ As Amended
❑ Ordinance on 1 ®t Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Authorize the City Manager and the Clerk of the Council to execute the second amendment and
extension of the settlement agreement and mutual and general release with Gerald Peebler to
extend the deadline for Peebler /UCI to submit the list of proposed public improvements to
December 31, 2015, and the deadline for the City to review and approve the list will be extended
to March 31, 2016, subject to non - substantitive changes approved by the City Manager and City
Attorney.
SUCCESSOR AGENCY ACTION
Authorize the City Manager and the Clerk of the Council to execute the second amendment and
extension of the settlement agreement and mutual and general release with Gerald Peebler to
extend the deadline for Peebler /UCI to submit the list of proposed public improvements to
December 31, 2015, and the deadline for the City to review and approve the list will be extended
to March 31, 2016, subject to non - substantitive changes approved by the City Manager and City
Attorney.
DISCUSSION
On November 18, 2014, the City Council authorized a Settlement Agreement and Mutual and
General Release with Gerald Peebler. The Settlement Agreement, dated November 14, 2014,
stipulated the establishment and deposit of $4.7 million into the "Peebler Fund" for the
80A -1
Second Amendment and Extension —
Settiement Agreement
May 19, 2015
Page 2
construction of public improvements within the South Main Corridor area, $250,000 for design
services to be provided by Gensler and Associates, and other provisions.
One of those provisions specified that within six months of the date of the original settlement
agreement, Peebler /University of California, Irvine School of Law, Community and Economic
Development Clinic ( "UCI ") is required to submit a list of proposed public improvements to the
City for review and approval, and that the City will be required to approve the list of
publicimprovements for development within nine months of the date of the agreement. These
deadlines are currently May 14, 2015 and August 14, 2015, respectively.
To date, Peebler /UCI has not executed the agreement with Gensler and Associates for design
services and is not ready to submit the list of proposed public improvements by the May 14, 2016
deadline. Therefore, Peebler /UCI has requested an extension of the deadlines. In order to
provide Gensler sufficient time to provide the design services in order for the list of proposed
public improvements to be developed, It Is recommended that Peebler /UCI's request be granted,
Therefore, the Second Amendment and Extension of Settlement Agreement and Mutual and
General Release (Exhibit 1) will extend the deadline for Peebler /UCI to submit the list of proposed
public improvements to December 31, 2015, and the deadline for the City to review and approve
the list will be extended to March 31, 2016.
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's effort to meet Goal #6 Community Facilities &
Infrastructure, Objective #1 (Establish and maintain a Community Investment Plan for all City
assets).
FISCAL IMPACT
There is no fiscal impact associated with this action,
Kelly Reenders
Executive Director
Community Development Agency
kr /sg /sb
Exhibit; 1. Second Amendment and Extension of Settlement Agreement and Mutual and
General Release
80A -2
SECOND AMENDMENT AND EXTENSION OF
SETTLEMENT AGREEMENT AND
MUTUAL AND GENERAL RELEASE
This Second Amendment and Extension of Settlement Agreement and Mutual and
General Release ( "Amendment ") is entered into this 19' day of May, 2015, by and between
Gerald Peebler ( "Pechter "), the City of Santa Ana, a charter city and municipal corporation
( "City ") and the Successor Agency to the Former Redevelopment Agency of the City of Santa
Ana ( "Successor Agency"). Peebler, City and Successor Agency are collectively referred to
herein as the "Parties,"
RECITALS:
A. The Parties entered into the Settlement Agreement and Mutual and General Release
( "said Agreement ") dated November 14, 2014 whereby the City agreed to establish and
deposit Four Million Seven Hundred Thousand Dollars ($4,700,000) into a separate fund
(the " Peebler Fund ") which was to be used solely for the following purposes:
a. Construction of public improvements (the "Public Improvements ") as proposed to
be developed by Gensler and Associates in the South Main Corridor (as defined
below) and as approved by the City, as more fully set forth in said Agreement,
b. Administrative and related costs incurred by the City arising from and related to
the implementation of said Agreement, in an amount not to exceed Twenty
Percent (20 %) of the cost of the Public Improvements; and
c. Peebler's litigation costs in the amount of Six Thousand Four Hundred Nineteen
Dollars and Thirty -three Cents ($6,419.33) to be paid to the University of
California, Irvine School of Law, Community and Economic Development Clinic
( "UCI" ).
B. In addition to the Peebler Fund, City agreed to allocate an additional Two Hundred Fifty
Thousand Dollars ($250,000) ( "Design FunW') to pay for the services of Gensler and
Associates ( "Gensler ") to develop a plan for the Public Improvements in the South Main
Corridor. As used in said Agreement, "South Main Corridor" means (i) South Main
Street between Warner Avenue and First Street; and (ii) First Street between Parton
Street and Standard Avenue, "Public Improvements" was defined to mean public
facilities, streets, drains, sewers, parks, sidewalks, streetscapes, landscaping and lighting
located on public property or in public rights -of -way.
C. Per said Agreement, UCI was to contract with Gensler to prepare the Public Improvement
projects for the South Main Corridor, and submit claims to the City for reimbursement,
along with supporting documentation, for payment to Gensler. The Parties agreed that in
no event shall the City be obligated to pay more than Two Hundred Fifty Thousand
Dollars ($250,000) for the costs of the design work for the South Main Corridor Public
Improvements.
;ir
D. Said Agreement was amended on January 30, 2015 to clarify that certain litigation costs
($998,75) awarded by the trial court in Peebler v. Department of Finance, Sacramento
County case mumbo 34- 2012 - 80001172 -CU -MW -GDS were to be paid to UCI from the
Peebler Fund by the City /Successor Agency,
E. Said Agreement contained cert,, n timeframes and deadlines that must be amended and
extended by this Second Amendment.
NOW, THEREFORE, for and in consideration of the mutual agreements set forth herein and
for other good and valuable consideration, the receipt and sufficiency of which is hereby
acknowledged, the Parties agree as follows;
The second paragraph of Section 3 of said Agreement shall be amended and extended to
allow for an additional seven (7) months for UCI and /or Design Finn to submit a list of
proposed Public Improvements to City for review and approval on or before December
31, 2015, so that a list of City - approved Public Improvements can be developed within
ten (10) months of the date of this Amendment or by March 31, 2016,
2. Except as hereinabove modified, the terms and conditions of said Agreement remain unchanged
and in full force and effect.
{Signatures on Following Page)
• I M
IN WITNESS WHEREOF, the parties hereto have executed this Second Amendment to said
Agreement the date and year first above written.
ATTEST:
Maria Huizar
Clerk of the Council
APPROVED AS TO FORM:
Sonia Carvalho, City Attorney
Lisa Store](, Assistant City Attorney
RECOMMENDED FOR APPROVAL:
Kelly Reenders, Executive Director
Community Development Agency
CITY OF SANTA ANA
David Cavazos
City Manager
SUCCESSOR AGENCY TO THE FORMER
COMMUNITY REDEVELOPMENT AGENCY
OF THE CITY OF SANTA ANA
David Cavazos
City Manager
SCOTT PEEBLER, as successor in interest to
Gerald Peebler
APPROVED AS TO FORM:
Carrie Hempel, University of California
Irvine School of Law
• 11.
FORM
FO.,