HomeMy WebLinkAbout25C - AGMT - GENERAL PLAN UPDATEREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
DECEMBER 15, 2015
TITLE:
AMEND AN AGREEMENT FOR PLANNING
AND ENVIRONMENTAL SERVICES WITH IBI
GROUP FOR THE SANTA ANA GENERAL
PLAN CIRCULATION ELEMENT UPDATE
{STRATEGIC PLAN NOS. 3, 2A; 5, 68}
lL
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
❑ As Recommended
❑ As Amended
❑ Ordinance on 18' Reading
❑ Ordinance on 2nd Reading
❑ Implementing Resolution
❑ Set Public Hearing For
CONTINUED TO
FILE NUMBER
Authorize the City Manager and Clerk of the Council to execute the attached amendment to the
agreement with IBI Group for planning and environmental services to prepare the General Plan
Circulation Element update, for a period no longer than eighteen months for an additional
amount of $80,245 not to exceed a total contracted amount of $613,245, subject to non -
substantive changes approved by the City Manager and City Attorney.
DISCUSSION
Assembly Bill 1358 (AB 1358), the 2008 California Complete Streets Act, requires that cities
prepare a comprehensive update to their General Plan Circulation Element to incorporate the
concepts of "Complete Street" design if it is determined that a substantial change has been, or
will be, made to the Element. A Complete Street is one that supports the development of a
balanced, multimodal transportation network that serves all users, whether they are driving,
walking, bicycling or taking transit.
In 2011, the City Council approved an agreement with IBI consulting team for $500,000 to assist
in the preparation of the General Plan Circulation Element update. The IBI Group's team of
subconsultants includes Alta Planning, PlaceWorks (formerly The Planning Center), and
Cornerstone Communications. While an amendment to the contract for $33,000 was approved
in October of 2014 to complete the project, the Circulation Element Update was placed on hold
soon thereafter to produce a Safe Mobility Santa Ana Plan (SMSA). Targeted to be completed in
December 2015, the Safe Mobility Santa Ana Plan is anticipated to identify additional street
reclassifications for potential "road diets" within the Circulation Element Update, and that will
require further traffic impact analysis. This traffic analysis is also needed to support an
amendment to Orange County Transportation Authority's (OCTA) Master Plan of Arterial
Highways. The proposed contract amendment (Exhibit 1), not to exceed $80,245, will allow for
completion of these technical studies, an updated traffic model, the incorporation of recent
community feedback into the policy framework, and enhancements to promote a user friendly
Circulation Element document.
25C -1
Amend an Agreement with IBI Group
December 15, 2015
Page 2
ENVIRONMENTAL IMPACT
The awarding of a contract for preparation of an environmental impact report and General Plan
update is statutorily exempt from CEQA.
STRATEGIC PLAN ALIGNMENT
Approval of this item supports the City's effort to meet Goal #3 - Economic Development,
Objective #2 (Create new opportunities for business /job growth and encourage private
development through new General Plan and Zoning Ordinance policies), Strategy A (Complete a
comprehensive update of the City's General Plan including the development of policies and
implementation measures that directly relate to equitable economic development); and Goal #5
Community Health, Livability, Engagement & Sustainability, Objective #6 (Focus projects and
programs on improving the health and wellness of all residents), Strategy B (Incorporate the
improvement of walking and biking lanes as well as the development of a citywide bike master
plan into the Circulation Element of the City's General Plan).
FISCAL IMPACT
Funds in the amount of $80,245 are available for this amendment in the Council Special Projects
Fund, Planning & Building — Contract Services (Account No. 05016018- 62300).
assan HaglAni, ArCP
Executive Director
Planning and Building Agency
F ed Mo savipour
Executive Director
Public Works Agency
MM:rb
MACirculatiamContrachRFCA Amend Contract12.15.15REVdoc
Exhibit: 1. Amended Agreement
APPROVED AS TO FUNDS AND ACCOUNTS:
knom > ���
Francisco Gutierrez
Executive Director
Finance & Management Services Agency
25C -2
SECOND AMENDMENT TO PROCESSIONAL
SERVICES AGREEMENT WITH IBI GROUP
THIS SECOND AMENDMENT TO AGREEMENT, made and entered into this 15 °i day
of December, 2015, by and between IBI GROUP, a California general partnership
( "Consultant "), and the City of Santa Ana, a charter city and municipal corporation organized
and existing under the Constitution and laws of the State of California ( "City ").
RECITALS
A. City and Consultant entered into Agreement #A- 2011 -198, dated September 13,
2011, for a consultant having special skill and knowledge in the field of circulation
element updates and related services ( "said Agreement ").
B. On October 21, 2014, the Scope of Services and the Compensation clauses of said
Agreement were amended.
C. In accordance with the terms and conditions of said Agreement, the Parties desire to add
additional funds, revise the Scope of Services, and extend the Term of said Agreement.
NOW THEREFORE, in consideration of the mutual and respective promises, and subject to the
terms and conditions of said Agreement, except as herein modified, the parties agree as follows:
Section 1, SCOPE OF SERVICES, shall be amended to include those services necessary
to complete the circulation element, including but not limited to performing new data
collection of traffic counts along with the collection of bicycle and pedestrian volumes at
intersections, meeting attendance and editing the draft Circulation Element to incorporate
new policies and text associated with the preparation of the Santa Ana Safe Mobility
Plan, as set forth in more detail in Consultant's Amendment Proposal No. 4 — Circulation
Element Update dated September 2, 2015, attached hereto as Exhibit A and incorporated
herein by this reference.
2. Section 3, COMPENSATION, the relevant portion of said section shall be amended to
increase the compensation by $80,245.00, such that the total sum to be expended under
this Agreement shall not exceed $613,245.00 during the extended Term of this
Agreement.
3. Section 4, TERM, shall be amended to extend the Tern through June 30, 2017.
4. Except as hereinabove modified, all terns and conditions of said Agreement shall remain
in full force and effect.
25C -3
IN WITNESS WHEREOF, the parties hereto have executed this Second Amendment to
Agreement the date and year first above written.
ATTEST:
MARIA D. HUIZAR
Clerk of the Council
APPROVED AS TO FORM:
SONIA R. CARVALHO
City Attorney
By: *StorCk-.Lj-
Assistant Lis City Attorney
RECOMMENDED FOR APPROVAL:
Ilassan Haghani, Executive Director
Planning & Building Agency
CITY OF SANTA ANA
DAVID C:AVAZOS
City Manager
Consultant
CBI GROUP
DAVID CHOW, P.E. AICP
Director
25C -4
EXHIBIT A
SCOPE OF SERVICES
(Attached)
3
25C -5
September 2, 2015
Melanie McCann
City of Santa Ana
20 Civic Center Plaza, Ross Annex M -20
Santa Ana, CA 92702
AMENDMENT PROPOSAL NO.4 - CIRCULATION ELEMENT UPDATE
This letter proposal details IBI Group's request for an amendment under our contract with the City
of Santa Ana for the Circulation Element Update project. Work efforts associated with this request
involve additional work will be incurred by IBI Group and Placeworks at the request of the City of
Santa Ana. The work efforts detailed in this amendment request were not included in our original
scope of services for this contract. The tasks listed below correspond to the tasks assigned in the
original scope of services for this contract. The proposed budget for completing this work is
attached to this letter.
Task ? — Project Management and Meetings
Amendment No. 1 included an augment to this task to reflect the ongoing management of the
contract up to a 39 -month effort. The current work effort as of August 2015 stands at 47- months,
which exceeds the extension provided under Amendment No, 1. Additionally, the city desires for
IBI Group and Placeworks to coordinate with the city and consultant selected as part of the Santa
Ana Safe Mobility Plan.
Based on these two components, IBI Group has budgeted for attendance by IBI staff and
Placeworks staff at up to three meetings for the Santa Ana Safe Mobility Plan and two hours per
month for IBI Group senior staff (project manager or deputy project manager) for ongoing
coordination with the city for a duration of 12 months from August 2015. This coordination effort
would carry the contract through the Safe Mobility Plan preparation and preparation of the draft
Circulation Element and environmental impact report (EIR).
Task 2 — Data Collection
As part of the original contract, IBI Group completed a data collection effort focused on the
inventory of the existing street network and collection of traffic, bicycle, and pedestrian counts. As
part of this effort, traffic counts were collected in June 2012 at 32 intersections and along 18
roadway segments that were approved by the City's Public Works Department. The count
locations were selected based on proposed street reclassifications identified by IBI Group and the
City of Santa Ana in 2012.
As part of the additional traffic analysis work completed by IBI Group under Amendment No. 1,
the City of Santa Ana conducted and provided traffic counts at 8 intersections and along 6 roadway
segments in 2014, above and beyond those counts previously identified and collected in 2012.
101 Group is a group of firms providing professional services
25C -6
IBI Group
7`j, `(
18401 Von Karman Avenue -Suite 110
11..LKJ1
Irvine CA 92612 USA
CRpUP
tot 9498335688
fax 9498335611
September 2, 2015
Melanie McCann
City of Santa Ana
20 Civic Center Plaza, Ross Annex M -20
Santa Ana, CA 92702
AMENDMENT PROPOSAL NO.4 - CIRCULATION ELEMENT UPDATE
This letter proposal details IBI Group's request for an amendment under our contract with the City
of Santa Ana for the Circulation Element Update project. Work efforts associated with this request
involve additional work will be incurred by IBI Group and Placeworks at the request of the City of
Santa Ana. The work efforts detailed in this amendment request were not included in our original
scope of services for this contract. The tasks listed below correspond to the tasks assigned in the
original scope of services for this contract. The proposed budget for completing this work is
attached to this letter.
Task ? — Project Management and Meetings
Amendment No. 1 included an augment to this task to reflect the ongoing management of the
contract up to a 39 -month effort. The current work effort as of August 2015 stands at 47- months,
which exceeds the extension provided under Amendment No, 1. Additionally, the city desires for
IBI Group and Placeworks to coordinate with the city and consultant selected as part of the Santa
Ana Safe Mobility Plan.
Based on these two components, IBI Group has budgeted for attendance by IBI staff and
Placeworks staff at up to three meetings for the Santa Ana Safe Mobility Plan and two hours per
month for IBI Group senior staff (project manager or deputy project manager) for ongoing
coordination with the city for a duration of 12 months from August 2015. This coordination effort
would carry the contract through the Safe Mobility Plan preparation and preparation of the draft
Circulation Element and environmental impact report (EIR).
Task 2 — Data Collection
As part of the original contract, IBI Group completed a data collection effort focused on the
inventory of the existing street network and collection of traffic, bicycle, and pedestrian counts. As
part of this effort, traffic counts were collected in June 2012 at 32 intersections and along 18
roadway segments that were approved by the City's Public Works Department. The count
locations were selected based on proposed street reclassifications identified by IBI Group and the
City of Santa Ana in 2012.
As part of the additional traffic analysis work completed by IBI Group under Amendment No. 1,
the City of Santa Ana conducted and provided traffic counts at 8 intersections and along 6 roadway
segments in 2014, above and beyond those counts previously identified and collected in 2012.
101 Group is a group of firms providing professional services
25C -6
181 Group
City of Santa Ana - September 2, 2015
Under this amendment request No. 4, given the time period of over three years that will have pass
between the traffic counts and release of the draft environmental impact report (EIR), is it
appropriate to obtain updated traffic counts at all the previously counted locations from the original
contract and under Amendment No. It o ensure that the traffic analysis utilizes the most up to date
information and data available. Therefore, the data collection effort would consist of new AM and
PM peak period traffic counts at all 40 intersections and 24 -daily traffic volumes at all 24 roadway
locations. The AM and PM intersection counts will also include collection of bicycle and pedestrian
volumes at the intersections. These counts are associated with additional roadway
reclassifications identified by the City of Santa Ana for analysis and advancement of the OCTA
MPAH Amendment process.
Amendment request No. 4 also includes new AM and PM peak hour counts at up to 36
intersections to account for the MPAH reclassification. The additional counts will also include
collection of bicycle and pedestrian volumes at intersections.
Task 4: Evaluation of Master Streets and Highways Plan
This new amendment involves work efforts that will be completed by IBI Group to _analyze up to
36 additional intersections in the traffic analysis beyond those contained in the original contract
and the previous two amendments. IBI Group will also coordinate with OCTA to provide inputs
for a single new OCTAM model run to develop updated Year 2035 traffic forecasts that include
the additional modifications to the MPAH roadway network identified by the city.
IBI Group will post- process the updated model forecasts obtained from OCTA, incorporate the up
to 36 additional intersections into the traffic impact analysis, and update our July 2014 draft traffic
study, including the analysis of 40 previously analyzed intersections and 36 roadway segments
using the new forecasted traffic volumes provided by OCTA.
This task also assumed time for attendance at up to two additional meetings with OCTA staff to
discuss the new proposed street reclassifications.
Task 9: Prepare Updated Circulation Element
This task will involve further updates and edits to the draft circulation element to incorporate new
policies and text associated with the preparation of the Santa Ana Safe Mobility Plan ( SASMP).
Specific edits are anticipated to be additions to the policy framework and incorporation of a
summary of the Santa Ana Safe Mobility Plan in the circulation element appendix. These edits to
the draft circulation element will be In addition to those Identified in Amendment No, 2.
As part of this task, Placeworks will also prepare up to two new maps in the Circulation Element
policy framework to reflect the Santa Ana Safe Mobility Plan components. This will include
importing linework, changing the base maps, amending colors and shades, and amending
symbols in accordance with City direction. This effort assumes that line work completed by the
Santa Ana Safe Mobility Plan consultant is in GIS and then transferred to Illustrator for
enhancement. Graphics supporting the Appendix are not included in this scope of work.
This task also assumes up to 10 hours for IBI Group and 12 hours for Placeworks for additional
coordination and meetings with City staff to discuss the SASMP and other city initiatives that may
influence the finalization of policies in the Circulation Element.
Given prior efforts on the circulation element, this scope of work assumes one final edit to be
completed by the project team, with only minor changes thereafter. This assumes that City staff
will review the document and provide direction prior to commence of work, with only final minor
25C -7
181 Group
City of Santa Ana — September 2. 2015
edits thereafter. The final document production will include photos and graphics that are readily
available, but do not require drafting or amendment. Following completion, we will provide a high
quality PDF for distribution.
A detailed cost summary sheet is attached to this scope of work. Should you have any questions
regarding this proposal, please do not hesitate to contact Bill Delo at (949) 833 -5588. We look
forward to the opportunity to continue to work with and assist the city on this project.
Sincerely,
IBI Group
David Chow, P.E., AICP
Regional Director, USA West
25C -8
Santa Ana General Plan Caunattlmr Mani Update � Soul Abora of No
let G., TP.am
Mandrour, by Task
o-ni
yam, r
TOTAL FEE by STAFF
In i In
11
$1.200 $20.800 57,580 $14.950
181 Gronp
IBI TOW Labor HOOre
Plaueworks
UM Total Labor Fee
$44 b20
Task 2- Update All 2012 counts
$12,500
Task 2- HOderssiflralion Counts
58,625
. un
Nara
b Pen „a br 11.1e I
J.
i'
via,
seeJr
Y
Total
use
HOUrs
a c”.
110alp :
0AI,.u.11 cnman
macaw
ntl— ! a i
Pees
5Mf).Qf)
$200.00:
5135001 $85,00 57500
519500
$175.00 $175.00
5135.00
TASK 1: Pro set Management antl Mealln a
anon prger._managen an
2r1
81
39
__$6.600
nleeun s
�
TASK 2: Uflbe Collection
YehlGalsr, bad antltlka roans
2'
41
6
$9,15
TASK 4: EValmdOn of Master Plan of Sheets S HIV
Goal OGTAkI Year 2035 Forecast
10.
8 20
I
38
$A 900
OCTA Merril
A
A� 5
24
$3,060
MtannaW,a aall$treat LOS An.111n,
21
20, 100: —� _ -
-��
I - - -� --
104
$16,000
U dates to Traffic Study
16 ":
16. 48 ":
80
$9.400
TASK B: Pr are CEOA Documenatilon
Sr."Ru" al SladY
Grab FIR --
t
-
- - -- d
8
$I:T66
Final SIR
i
0
90
TASK U: Fie are U doted Circulation Element
Droll Clarolation EIe rani
- -_
16
50__.56.210
Final Circulation Elomeat
__. _..
10
T_
I2:'
2'!.
SA.100
yam, r
TOTAL FEE by STAFF
In i In
11
$1.200 $20.800 57,580 $14.950
50
IBI TOW Labor HOOre
340
UM Total Labor Fee
$44 b20
Task 2- Update All 2012 counts
$12,500
Task 2- HOderssiflralion Counts
58,625
Cori 5
90
181 Teal BwlgeC $65,735
$0 SI0,S50 51,400 $2,160 ran
558.030
86
$14,410
5100
$14.510
151 Total BUdise 565,735
Pascevmrks Total Budge¢ S14,510
Alta Total Budget: $0
Cornerstone Total Budget s0
Total Proposed Budget: $80,245
25C -9
25C -10