23B - PROJ - WARNER WATER AND SEWER IMPROV
1 III M11111111111111 0 1011 A • ►_ CITY COUNCIL MEETING DATE: MAY 17, 2016 TITLE: AWARD CONTRACT TO KANA PIPELINE, INC. FOR WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS (PROJECT 16 -6461) {STRATEGIC PLAN NO. 6, 1C} CITY MARTMR ' x!_11 11 ..:: 1, ! ■ CLERK OF COUNCIL USE ONLY: APPROVED ❑ As Recommended ❑ As Amended ❑ Ordinance on 1" Reading ❑ Ordinance on 2ntl Reading ❑ implementing Resolution ❑ Set Public Hearing For CONTINUED TO FILE NUMBER Authorize the City Manager and Clerk of the Council to award and execute a construction contract to Kane Pipeline, Inc., the lowest responsible bidder, in accordance with the bid in the amount of $3,457,000, for the term beginning upon execution of the contract and ending upon project completion, for the construction of the Warner Industrial Community Water and sewer Improvements Project, subject to nonsubstantive changes approved by the City Manager and City Attorney. 2. Approve the Project Cost Analysis for a total estimated project delivery cost of $4,494,100, which includes the contract base amount, administration, inspection, testing, and a $516,550 contingency. DISCUSSION The existing 6 -inch diameter cast iron water main located within the Warner Industrial Community (Exhibit 1) was installed in the 1950's and has begun to experience a number of significant breaks and leaks. Staff monitors the condition of water main pipelines by assessing critical factors such as history of breaks, size, location, and system redundancy to determine the replacement priorities, Based on an analysis of these factors, both the water main and sewer within this Industrial community have been identified for replacement, The Improvements Include the construction of a new 6" P,V.C, water main, fire hydrants, water services and appurtenances. Additionally, the sewer main system Is undersized and will be replaced with a new 10" vitrified clay pipe (VCP). Once this project is completed, water service quality and reliability will Improve significantly. The water main breaks and the possibility of a loss of service will be substantially reduced. In addition, the upgraded sewer main system will provide larger flow capacity to prevent overflow issues. 23B -1 Contract Award to Kane Pipeline, Inc. for Warner Industrial Community Water and Sewer Improvements May 17, 2016 Page 2 A Notice Inviting Bids was advertised on March 28 and April 4, 2016, and bids were opened on April 19, 2016. The following is a summary of the bid Invitations mailed and received, and the bid results: Contractor Participation Data Santa Ana contractors receiving notices 16 Contractors re guesting bidding documents 37 Bids received 12 Bids received from Santa Ana contractors 0 RANK BIDDER'S NAME LOCATION BASE BID 1 Kane Pipeline, Inc. Placentia $314571000,00 2 Mike Prllch and Sons Inc. Baldwin Park $3,475,095.00 3 Sully-Miller Contracting Company Brea -$31a371851.00 4 Dominguez General Engineering Inc. Pomona $3 645 080.00 5 6 Gwinco Construction & En ineerin Inc. _ Ramona Inc. Ontario Arcadia $31760,073.00 -$3,803,860.00 7 Colich & Son L.P. Gardena $3,951,785.00 8 TBU Inc. — Beaumont $4,048,655.00 9 Excel Paving Companv Long Beach $4,104,865.00 10 MNR Construction, Inc. Baldwin Park $4,144,215.00 11 Blois Construction, Inc. Oxnard $4,416,772 12 Lonerock, Inc. Irvine $4,988,965.00 _A A total of twelve bids were received and all twelve were considered responsive. Kane Pipeline, Inc., submitted the lowest responsive bid in the amount of $3,457,000, which Is significantly lower than the Engineer's Estimate of $5,100,000. Based on a staff analysis of the bids received (Exhibit 2), staff recommends award of a construction contract to Kane Pipeline, Inc. (Exhibit 3). STRATEGIC PLAN A . I� GNMENT Approval of this item supports the City's efforts to meet Goal 06 Community Facilities & Infrastructure, Objective 01 (establish and maintain a Community Investment Plan for all City assets), Strategy C (invest resources to extend the service life of existing Infrastructure to protect the City's investment and support a high quality of life standard), 23B -2 Contract Award to Kana Pipeline, Inc. for Warner Industrial Community Water and Sewer Improvements May 17, 2016 Page 3 ENVIRONMENTAL IMPACT In accordance with the California Environmental Quality Act, the recommended actions are exempt from further review. Categorical Exemption Environmental Review No. ER #2016 -25 will be filed for this project. In addition, a Certification of Categorical Exemption and Statutory Worksheet have been prepared in accordance with the National Environmental Policy Act. FISCAL IMPACT As indicated in the Cost Analysis (Exhibit 4), the estimated total delivery cost of this project is $4,494,100, which includes construction, contract administration, inspection, testing, surveying, and contingencies. Funding is available in the Water Capital Project Fund (Account No. 06617647 - 66301) and Sewer Connection Projects Fund (Account No. 05517660- 66220). FISCAL YEAR ACCOUNT NO. Amount 2016 -17 06617647 -66301 $2,651,365 2016 -17 05517660 -66220 $1,842,715 TOTAL: $4,494,100 U re Mou avi ' ur Executive irector Public Works Agency FM /EWG/TC /MO Exhibits: 1. Location Map 2. Bid 3. Construction Contract 4. Cost Analysis APPROVED AS TO FUNDS AND ACCOUNTS: Francisco Gutierrez Executive Director Finance & Management Services Agency 23B -3 23B -4 SANTA ANA City Council ■ - ���j ■ Agenda gate Nwl.r AWI May ... 2016 EXHIBIT 1 23B -5 PWEW CITY OF SANTA ANA Exhibit 2 PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS RID PROPOSAL TO: CITY COUNCIL OF THE CITY OF SANTA ANA FROM: REQUIREMENT: The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump sums) set forth in the following schedule: WATER MAIN IMPROVEMENTS Item Bid Item Unit City Unit Price Amount 1.* Mobilization —Water L5 1 $ 7 $) Main Improvements_ 2 8" DR14 AWWA C900 LF 9,120 $ )o > p $9>76co'7 P.V.C. Water Main - - -i- Construct 1" Water 00 o 3. Service and Connect to EA 35 Existing Meter Construct 2" Water 0 4. Service and Connect to EA 60 Existing Meter Construct 3" Water' 20 00 5- Service and Connect to EA 2 $ 5,760 $ t, � Existing Meter 6. 8" Resilient Wedge Gate EA 11 q "— Valve Fire Hydrant Assembly 7. (includes gate valve and EA 18 $ _ lateral pipe) Construct 6" Fire Service as ck 8. and Connect to Existing EA 30 Piping Construct 8" Fire Service 00 00 9. and Connect to Existing EA 9 $ { -- __ �— Piping P -1 OF P -17 23B -7 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS P -2 OF P -17 r Furnish and Install Traffic �,>o ' 10. Rated Meter Box and EA 81 $ _ Cover 11 Construct Water Pipe EA 11 $ 'L?�zv $S ClE+t� ` Casing CCTV Inspection of 12. Existing Sewer Main (to> LI= 2,800 $ } $ be left in place) Adjacent to New Water Main CCTV Inspection of 13' Existing Sewer Laterals (to EA 34 $ 'ZI $ be left in place) Adjacent to New Water Main 14. Replace Damaged Traffic _ EA 2 Loop Detectors 15. Signing and Striping LS 1 $0 $ gyp `'° 16.— Traffic Control LS 1 $ a+ � '' $ 5, �5 17. As -Built LS 1 $17,500 $17,500 18 Prepare SWPPP LS 1 $ Q $,0 °c' 1g ** Combination Air Valves EA 10 $? +� Ile $ (As Needed) 20. ** Vertical Offset (As EA 10 $ 8J; 00 _ Needed) 21. ** _ ___ Imported Backfill Material pNeeded) CY 200 $ �� i} (As 22. ** Potholing (As Needed) EA 10 $ t5goe P -2 OF P -17 r CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS SEWER MAIN IMPROVEMENTS Item Bid Item Unit qty Unit Price Amount 23.* Mobilization —Sewer LS 1 $ T� $ 77`1, i Main Improvements 24 Construct 15" VCP Sewer LF 465 $ Main 25. Construct 12" PVC Sewer LF _ 545 $ $ 70 Main 2& _ Construct 10" PVC Sewer _ LF 3,285 _ _ F Main _ 27. Conti Construct 8" PVC Sewer LF 1,020 $ 2 "° $ J4" 640 Main 28 Construct HDPE, Double LS 1 $ � �� $ 55,0a> -C Barrel, Sewer Siphon 29 _ Construct 42" RCP Storm LS Drain 30 Construct 6" Laterals and EA 61 L Cleanouts 31. Construct 48" Concrete EA 24 $� °~ 5 _ 0 0 Manhole 32. Bypass Pumping Existing LS 1 0-) $ (% ®r }y 00 $ Sewer Flow 33. CCTV Inspection of New LF 5,315 $ Sewer Main 34 CCTV Inspection of New EA 61 $? $ Sewer Lateral _ Construct Sewer Flow (90 00 35. Level Monitoring and EA 2 $;3Ck7 $r�� "� Alarming Device _ 36 _ Replace Damaged Traffic EA 2 $ (25' $� 3 Loop Detectors _ 37. Signing and Striping L5 1 _ $ 566 38. Traffic Control LS 1 $2t7 39. As -Built LS 1 $17,500 $17,500 40. PrepareSWPPP LS 1 YO $ �.a�yan`° $_ :� ooca^ P -3 OF P -17 23B -9 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS 41. ** Imported Backfill Material (As Needed) CY 200 $'° $�} 42 ** Additional Potholing (As EA 10 $J` �— Needed) _/! TOTAL BID $ �I 71 000 The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add - alternate bid items (if any). Each mobilization item is limited to a maximum of 2.5% of the Total Bid. ** The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25 %" limit as stated in Section 3 -2 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES jBidder signature must be shown on same page as total bid amount shown on table) The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within one hundred seventy -five (17 5) working days after the commencement date stated in the Notice to Proceed. 25 –Working days for exploratory potholing and data gathering 150–Working days for project construction The bidder also proposes to commence construction of the Work within thirty (30) days after issuance of a Notice to Proceed, and to continue in a diligent and workman -like manner without interruption, and to complete the construction thereof within the time specified above. The liquidated damages amount in lieu of the amount specified in Subsection 6 -9 of the Standard Specifications, shall be $2,000 per calendar day. Name of Firm Signature of BID[ Title `– 'f_`ocl) G1 4 ( (if an individual, so state) P -4 OF P -17 23B -10 CITY OF SANTA ANA PROPOSAL PROJECT N0, 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS BIDDER'S STATEMENT BIDDER understands and agrees that this Bid Proposal, Contract Documents and subsequent Construction Contract Agreement shall constitute the entire agreement between BIDDER and the AGENCY only after it has been accepted by the City Council, endorsed by the Clerk of the Council with her signature and official seal noting hereon the action of approval of the Council, signed by the Public Works Agency Executive Director or his /her duly authorized agent, and signed by the City Attorney, denoting his approval of the form of this document, and its execution, and when it or an exact copy of it has been either delivered to BIDDER or deposited with the United States Postal Service properly addressed to the BIDDER with the correct postage affixed thereto. BIDDER further agrees that upon delivery (as defined above) of the accepted agreement he /she will furnish AGENCY all required bonds and certificate of liability insurance within ten (10) business days or the funds, check, draft, or BIDDERS bond substituted in lieu thereof accompanying this proposal shall become the property of the AGENCY and shall be considered as payment of damages due to the delay and other causes suffered by AGENCY because of the failure to Furnish the necessary bonds and because it is distinctly agreed that the proof of damages actually suffered is difficult to ascertain; otherwise said funds, check, drafts, or BIDDER'S bond substituted in lieu thereof shall be returned to the undersigned. BIDDER understands that a bid is required for the entire work, the estimated quantities set forth In the bid schedule are solely for the purpose of comparing bids, and that final compensation under the contract will be based upon the actual quantities of work satisfactorily completed. The BIDDER also certifies that the bid is a balanced bid. In accordance with Section 7028.15 of the California Business and Professions Code, the undersigned certifies under penalty of perjury that the foregoing is true and correct. Name of Firm Signature of BIC Title i t4- v -(if an individual, so state) (If a firm or co- partnership, state the firm name and give the names of all individual co- partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) cif' 1'44'C10} ! P -5 OF P -17 23B -11 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS CONTRACTOR'S LICENSING and REGISTRATION STATEMENT The undersigned contractor, or corporate officer, declares under penalty of perjury that he /she and all his /her subcontractors are registered with the State of California Department of Industrial Relations (DIR), and that the following is true and correct. Contractor's Name: Kwi. , Business Address: t�-. MIC C L zip la twF- 1UT- Pt t PT0S -, (,A. Utz ip Business E -Mail br-, tF0 K- j,7rave 6o --1 Address: t` l V->A UI.-P �i--il-+..l= %2L:', - CC) b"1 Telephone: 01to el'�)t - �± State Contractor's License No. and Class: 4 (S l 4 �_7 A License Expiration Date: - -'1 State Dept. of Industrial Relations (DIR) Registration No.: i Q C>CJ 0 Q 2--Z--t> State Dept. of Industrial Relations (DIR) Registration Expiration Date: ja to 2la Signed: N\ 1 1.-0Gv- Title: PV.GSw'>- or- P -6 OF P -17 23B -12 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS PREVAILING WAGE COMPLIANCE AND MONITORING STATEMENT Contractor is aware of the requirements of California Labor Code Section 1720, et seq., as well as California Code of Regulations, Title 8, Section 16,000, et seq., ( "Prevailing Wage Laws "), which require the payment of prevailing wage rates and the performance of other requirements on "public works" and "maintenance" projects. Since the services are being performed as part of an applicable "public works" or "maintenance" project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. City shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Agreement. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the services available to interested parties upon request, and shall post copies at the Contractor's principal place of business and at the project site. Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. The undersigned certifies that the foregoing is true and correct. Name of Firm Signature of BIE Title 1 sjW� (if an individual, so state) P -7 OF P- t 7 23B -13 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS OWNERSHIP AFFIDAVIT STATE Or- CALIFORNIA ) COUNTY OF ORANGE ISS: CITY OF SANTA ANA j being duly sworn, deposes and says: INDIVIDUAL That he /she is the party making the foregoing proposal: El PARTNERSHIP That he/ she is a member of the co-partnership firm designated as: and who has been and is duly vested with the authority to make and execute instruments for the co- partnership by: who constitute the other members of the co- partnership. CORPORATION That he is of: a corporation which is making the foregoing proposal: JOINT VENTURE That he is of: one of the parties making the foregoing proposal as a joint venture, and the he /she has been and is duly vested with the authority to execute instruments for an on behalf of the parties making said bid who are: that such a bid is genuine and not collusive or sham, and has not in any manner sought by collusion to secure any advantage against the City of Santa Ana or any person interested in the proposed contract, for himself or any qt er person. Signature of Bidder Subscribed and sworn to before me this I r( day of 20 '���'7�r: � =,tee;: v;rc3�,c:�1•. Signature of officer Administering Oath (Notary Public) P -8 OF P -17 x o'R64Uiti:GlEFtt 23B -14 California All - Purpose Acknowledgement State of California County of Orange On 41 A (2Gl (, before me,_ Ferns Salvador- Tabadero Notary Public Date Name & Title ot'6lticer personally appeared _ I t4 V I.E; L i_ Ocie a' Name(s) who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is /are-subscribed to the within instrument and acknowledged to me that he /she /they executed the same in his/he"r /thy "r authorized capacity(iios), and that by his /her /their sigmatUres(•3) on the instrument the person(sy, or the entity upon behalf of which the person(s)—acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is trite & correct. WITNESS �myhand & official seal. ���VW"t��1t� -- Sign at , re of Mo tary VubI is OptiDna— information' Description of Attached Document: RERNESSALYA@OATARAOERO CDMM. #2088708 = rc Notary Publio • Calitania �° Z Orange County Comm. Ex fires Ma 30, 2DiS Notary Sea[ Title or Type of Document: G'C' 1"E1 F V -( l�)AC V \T CDT:ro RAT ( 6( Document Date: _ Number of Pages: Sfgner(s) Other Than Named Above: Other information: CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS LIST OF SUB- CONTRACTORS Section 4100 et. seq. of the Public Contract Code requires listing of all subcontractors with the bid for all subcontract work exceeding the following amount: • Streets, highways including bridge projects: %% of the bid or $10,000, whichever is greater • Buildings, parks, or other projects: %% of the bid Section 1725.5 of the Public Contract Code requires all Subcontractors be registered with the State Department of Industrial Relations (DIRj. BIDDER proposes to subcontract certain portions of the work to the firms listed below: Name MOF-/ b i Name License # /Exp, �36(?) Lt b- License # /Exp. Dill Reg. # /Exp. D. D. pL,j..c$2rx 4 ",,1 t DIR Reg. # /Exp. Locationa7 Location Phone 76;�5- Phone Type Of Works (nyanJ ltir� Type Of Work Amount $ 5� `< '�, (-) � j Amount $ Name I,)Is100 L G�Nk oS, License 4/Exp. ?)5 5;025 i )' "7' -2o k 1 Dill Reg.# /Exp• �f7CO32'7J °'?�t4 Name License # /Exp. bIR Reg. # /Exp. License # License # Location j�?rac� V- c. o� Location Phone 00 Phone _ Type Of Work G f jyl tMW —Se 512Type Of Work Amount $ Amount $ Name O71 �—b IPQ License # /Exp. Dill Reg. # /Exp. License # _ Location Phone «76:L Type Of WorkjhFh� Amount $ PA1W L L- 4c o !�..... Signature of Bidder Name License # /Exp. DIR Reg. # /Exp. License # _ Location _ Phone _ Type Of Work Amount $ 11-10 OF P -17 23B -16 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS REFERENCES The following are the names, addresses, and telephone numbers for THREE public agencies for which BIDDER has performed water and sewer pipeline work within the past three years. 1. 1EyI G�. i ` ' 17x 11A GGi t2.'ios- Name and Address of Owner. UG, r tt�sc 1'(C lt�))`i 2 S— 4ci7 Name and Telephone Number ofperson familiar with ro'ect. t o 14-v, 'Z J Y121 { i3 i `)° r� r � ` ._ 2 Joao, � t c> Contract Amount Type of Work Date Completed GtT°t cad -)-h v-v3 t r Cwt 2. �Ca _g�. (,A— Name and Address of owner. Name and Telephone Number of person fasili r wi rojV . Contract Amount Type of Work Date dompleted L.L1P t„v 1AT-1 17k't ,S TL1' 3. t 1 V�! , mroyP T t Ps Y Uill-i'i'D Name and Address of owner. _ mart b-x-i) 9 A-6 -7S ) y�Name and Telephone Number of person familiar with project. 40 ki Contract Amount Type of Work Date Completed The following are the names, addresses, and telephone numbers of all brokers and sureties from whom BIDDER intends to procure insurance and bonds, S 7-1-7 SOO 'Ft Wi t--- .<�u t%. 1x�>�� -4- e, I, 6 S , C --A , 6� n c-:� t I F'n f2-k?) ? 1 Q - 0-71 P -11 OF P -1.7 23B -17 CITY OF SANTA ANA PROPOSAL PROJECT NO, 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS NON - COLLUSION AFFIDAVIT (Title 23 United States Code Section 112 and Public Contract Code Section 7106) In accordance with Title 23 United States Code Section 112 and Public Contract Code 7106 the BIDDER declares that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the BIDDER has not directly or indirectly induced or solicited any other BIDDER to put in a false or sham bid, and has not directly or indirectly colluded, conspired, connived or agreed with any BIDDER or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the BIDDER has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the BIDDER or any BIDDER, or to fix any overhead, profit, or cost element of the bid price, or of that of any other BIDDER, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the BIDDER has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid. Note: The above Non - collusion Affidavit is part of the Proposal. Signing this Proposal on the signature portion thereof shall also constitute signature of this Non - collusion Affidavit. BIDDERS are cautioned that making a false certification may subject the certifier to criminal prosecution. 1 /7 Signed State of California County of 0"MV76b- Subscribed and sworn to (or affirmed) before me on this M1 day of f L 20A, by j7d tJ \fit 1 f3C.K €3 proved to me on the basis of satisfactory evidence to be the perso*j'who appeared before me NERNES SALVADOR TABADERO COMM, #2066708 z Notary Public • California a = Orange County ��irM1 Comm. Ee ires May 30 2018 Notry Public Signature Notary Public Seal P -12 OF P -17 23B -18 CITY OF SANTA ANA PROPOSAL PROJECT NO, 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS NON- DISCRIMINATION CERTIFICATE The undersigned contractor or corporate officer, during the performance of this contract, certifies as follows: 1. The Contractor shall not discriminate against any employee or applicant for employment because of race, color, religion, sex, or national origin. The Contractor shall take affirmative action to ensure that applicants are employed, and that employees are treated during employment without, regard to their race, color, religion, sex, or national origin. Such action shall include, but not be limited to, the following: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship, The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause. 2, The Contractor shall, In all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, or national origin. 3. The Contractor shall send to each labor union or representative of workers with which he /she has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of the Contractor's commitments under this section, and shall post copies of the notice in conspicuous places available to employees and applicants for employment. 4. The Contractor shall comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor. 5. The Contractor shall furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his /her books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation, to ascertain compliance with such rules, regulations, and orders. 6. In the event of the Contractor's non - compliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, the contract may be canceled, terminated, or suspended in whole or In part and the Contractor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Execution Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order P -13 OF P -17 23B -19 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS 11246 of September 24, 1965, or by rule, regulations, or order of the Secretary of Labor, or as otherwise provided by law. 7. The Contractor shall include the portion of the sentence immediately preceding paragraph (1) and the provisions of paragraphs (1) through (7) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to Section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontract or purchase order as the administering agency may direct as means of enforcing such provisions, including sanctions for noncompliance; provided, however, that in the event the Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency, the Contractor may request that the United States enter into such litigation to protect the interests of the United States. 8. Pursuant to California Labor Code Section 1735, as added by Chapter 643 Stats. 1939, and as amended, no discrimination shall be made in the employment of persons upon public works because of race, religious creed, color, national origin, ancestry, physical handicaps, mental condition, marital status, or sex of such persons, except as provided in Section 1420, and any contractor of public works violating this Section is subject to all the penalties imposed for a violation of the Chapter. Signed: DlsF- Flr- WC*Z -5� , Title: FC-C-NI9C- -t -`1'"' Firm: Y-- &l ->N 1 4i'C 4z�1 t11C Date: 4 �-oic> - �T P -14 OP P -17 23B -20 CITY OF SANTA ANA PROPOSAL PROJECT NO, 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS STATEMENT REGARDING APPRENTICESHIP REQUIREMENTS The undersigned BIDDER is familiar with the requirements of Section 1777.5 of the State Labor Code regarding employment of apprentices, and understands that contractors on contracts exceeding $30,000 or 20 working days shall: 1. Apply to the joint apprenticeship committee administering the apprenticeship standards of the craft or trade in the area of the site of the public work for a certificate approving the contractor under the apprenticeship standards for the employment and training of apprentices in the area or industry affected. 2. Employ the number of apprentices or the ratio of apprentices to journeymen stipulated in the apprenticeship standards. 3. Contribute to the fund or funds in each craft or trade in which he /she employs journeymen or apprentices on the public work, in the same amount or upon the same basis and in the same manner as the other contractors, except contractors not signatory to the trust agreement shall pay a like amount �o the California Apprenticeship Council. Signed:�4} Title:' Firm: KEN- i,&. I\ }i(. - Date: ! 1 at 1 `2-01 G P -15 OF P -17 23B -21 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS STATEMENT REGARDING "ANTI- KICKBACK" REQUIREMENTS The undersigned is submitting this proposal for performing by contract the work required by these bid documents, agrees to comply with the Copeland "Anti- Kickback" Act (18 USC 74) as supplemented in the Department of Labor regulations (29 CFR, Part 3). This act provides that each contractor or subcontractor shall be prohibited from inducing, by any means, any person employed in the construction or repair of public work, to give up any part of the compensation to which he/she is otherwise entitled, qd 9 Signed: — Title: Firm: P 1Gs.Ij1 Date: 4 P -16 OF P -17 23B -22 CITY OF SANTA ANA PROPOSAL PROJECT N0, 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS PUBLIC CONTRACT CODE SECTION 10162 QUESTIONNAIRE In conformance with Public Contract Code Section 10162, the BIDDER shall complete, under penalty of perjury, the following questionnaire: Has the BIDDER, any officer of the BIDDER, or any employee of the BIDDER who has a proprietary interest in the BIDDER, ever been disqualified, removed, or otherwise prevented from bidding on, or completing a federal, state, or local government project because of a violation of law or a safety regulation? Yes No If the answer is yes, explain the circumstances in the following space. P -17 Or P -17 23B -23 MAYOR Miguel A. Ptdida MAYOR PRO TU l Viconte Sanniento COUNCILMEMBERS Angelica Amemua P. David S enavddes Michele Martinoz Roman Reyna S11 Tinajero April 11, 2016 ADDENDUM ONE CITY OF SANTA ANA 20 Civic Center Plaza . P.O. Box 1988 M -36 Santa Ana, Californla 92702 (714) 6475013 w`nwa.santa- ana.org CITY MANAGER David Cavazos CITY ATTORNEY Sonia R. Carvalho CLERK OF THE COUNCIL Maria D. Huizar SUBJECT: PROJECT NO, 16.6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS The following changes have been made to the Specifications for the subject project: CHANGES 1. New security policy to access restricted office areas: Contractors will be required to comply with the City's new security policy and fallow the attached procedures when conducting business in the City of Santa Ana City Hall and Ross Annex Buildings, Contractors will need to sign -in for the Pre -bid Meeting and Bid opening for Project 16 -6461 to receive elevator access to the 3rd floor lobby, Contractors should allow themselves additional time to register and sign -in to avoid missing important information on the pre -bid meeting and the time -stamp deadline as noted on the Notice Inviting Bids. Addendum One contains total of (3) page FOR THE CITY OF SANTA ANA `dwir?- 'Willi a m" eGa 1/-v e z P. E. City E' ngineer SANTA ANA CI I Y COUNCIL N4�unl l P =dd:: Vmc'�tl.; Saumenw hAluniip M1.lunme: Anggl,I A,.n!/,a P Da, w 62namdez Ruman aeyna SAI IinBlvm �IAyOi M1inycu Pro I am. VVnM 1 VV:I"l WaN 3 Wald 4 WtlN 5 Ward li nq: Al.11115WClLVL11tl1,cl 1,o'9 r,al wza,z re.a u3�z �a,,a. ?I- ''��.1 lb_' 1,l r4 !, 23B -24 H Carty of Santa Ana Administrative Guideline Visitor identification rind At,,ceas Control for Reatricted Office Ar%is ergs Personnel Services The purpose of this guideline is to establish uniform procedures to properly identify visitors and control access at City Mall and (toss Annex. II. P 'er r A. Identification and slgn -In process for all visitors 9. All visitors, including employee/contractor family members and delivery service drivers, must sign -In with the receptionist; be registered in the visitor log, show photo Identification, and be issued a temporary visitor pass prior to accessing the basement and floors two and above at City Mall and Rosa Annex. Exceptions a, In accordance wlfih §54963.5 and §54953.0 of the Government Code, members of the public attending legislative body meetings, such as city council, council committees, board and commission, and board of directors meetings, may not be asked to sign -in or identify themselves in order to attend such meetings:. is Temporary visitor passes are NoT required for unformed fire or law enforcement personnel. B. Visitors vvhthout photo identification or not registered in till oniino visitor ltag. , A visitor who does not have a photo identffioation card in his or her possession can be granted access by the receptionist, security personnel, or a City employee, Entry is granted based on: a: ThelodIVINUMI boingroEOgnixad; of b. The need to enter has been established by a City staff member; and o. The person registers in the visitor log. 2: A visitor not registered by staff in the online visitor log will be granted access only after: a. Identity has been verified; and b. The need to enter has been established by a City staff member; and c. TI e visitor, is adder) to the visitor log by the receptionist which would Include the following Information: Q Visitor name * Reason for visit m Staff contact person Contact person phone number 23B -25 a Facility and floor being visited If the vishor does not have anyone to verify their Identity and tho,need to enterhras not been 0@0..8ifolishod, raooess shall be denied to restrioted ofifivs area. f.) ocurrmnts which establish Identity 1. City ID badge, 2. State driver's Ilcense. ,. ID card issued by federal, state, or local government agencies or entities, provided it contains a photograph or information such as riame, date of Wirth, sex, height, eye color, and address, n. Driver's license or ID card issued by a state outlying possession of the U3, provided it contains a photograph or Irformation such as name, data of birth, sex, Irelcght, eye color and address, 6. US, and foreign passport or consulate card, 6, Schooi iden4lflcation card, with a photograph, 7. Library card, with a photograph, 8. Voter registration card, with a photograph. 9. U,S, military card, with a ,photograph. 16, Native Arnerio�an Tribal document 23B -26 MAYOR Miguel A, Pulldo MAYOR PRO 1EM V10031te SMnr1lent0 COUNCILMEM6ERS Angallea Anazrua P. Davlcl aerlavldes MICI7sle Martlnaz Roman Reyna Sal Tinaloro April 12, 2016 ADDENDUM TWO CITY OF SANTA ANNA 20 Chia Center Plaza o P.0 Box 1986 M,30 Santa Ana, Callt'ornle ;77472 (714) Cr47 -6013 wwww.santa•ann.oi UPTPlCtAi- 6r ur:,�' 7 1l.A.L David Cavazos CITY ATTORNEY Sonia R. Carvalno CLLRK OF THE COUNCIL Marla D. Holzer SUBJECT: PROJECT NO. 16.6461: WARNER INDUSTRIAL. COMMUNITY WATER AND SEWER IMPROVEMENTS The following changes /clarifications have been made to the specifications of the subject project. 1. TABLE OF CONTENTS .M 7•,10 PUBLIC CONVENIENCE AND SAFETY 7- 10,1,2 Outreach Program & Coordination In addition to the standard notices, the contractor will be required to create and Implement an Outreach Program that consists ofthefollowing items t'hatwill be required prior to commencement of construction. m Assign or hire an Outreach Coordinator /Spokesperson and provide; Name, title, phone number, and ernall. This person should be available during and after working hours. P Provide business Coordination Logs (sample). These logs will need to Include the business name, address, person contacted, date of contact, Purpose (sample) and preferred days/timas for construction to minimize impacts. it is the contractor's responsibility to contact all businesses within the project limits, inform them of the construction activities, and determine the times for construction that will minimize impacts to access and public inconvenience, These efforts shall be coordinated with the City Engineer or his representative to minimize businesses disruptions. The Inspector will verify coordination efforts on a regular basis. SANTA ANA CITY COUNCIL N119wil A. Pdko I viawto Harlylk"ln MchelaMoNnwa Mgellao Ammeci* I P. Y)aNdidenxvlaex IRomakayon SaA'rinetoro Mayor Moyar I'm renr worn I Word 2 Word x Wor<r4 Wrvrd A Werda ^14'11 IhMliAA- 413.4!a I ervlr -lave i in.u.e I ala- BID £ nutvasn 2M21 MAYOR MYguel A, Pulldo MAYOR PRO 1'EM Vicente SaPT1lel1tM COUNCILNIEMeCRS Angellua Amenua P. DoMd awnakles Mlrhela Martinez Roman Payna Sal Tinalero CrTY OF SARTA ANA 7_0 Chic Center Plaza m P.C. Box 1998 M -36 Santa Aria, Californfa 92702 (71 4) 0474013 u6w_v_ N•ana.Mrk UI I Y MAIN At K Divld Cavazos CITY ATTORNEY SM118 R. Calvalha Ut RK OF THE COUNCII. Maria D. Hulzar The Contractor prior to commencement of work will need to provide all items listed above for approval from the City Engineer or his representative. It is the contractor's responsibility to submit all paperwork and documentation in a timely manner to receive authority to proceed with construction. Payment for the outreach program shall be included in other Items of work no additional compensation will be allowed. SPECIAL PROVISIONS Page 31; Section 6.01, 2nd Paragraph Contractor shall excavate open trench 100 feet ahead of the pipe laying operations to allow for any adjustments In grade necessary to resolve unforeseen utility conflicts. REPLACE with; Contractor shall excavate open trench 15U feet ahead of the pipe laying operations to allow for any adjustments in grade necessary to resolve unforeseen utility conflicts. 3. SPECIAL PROVISIONS Page 3.1; Section 7.02, 2n6 Paragraph Contractor shall excavate open trench 100 feet ahead of the pipe laying operations to allow for any adjustments in grade necessary to resolve unforeseen utility conflicts. REPLACE with: Contractor shall excavate open trench 150 feet ahead of the pipe laying operations to allow for any adjustments in grade necessary to resolve unforeseen utility conflicts. 4. SIC? PROPOSAL Page P -4 of P -17; Time for Completion of Improvements and Liquidated Damages The bidder also proposes to commence construction of the Work within thirty (30) days after the Issuance of a Notice to Proceed, and to continue in a diligent and workman -like mariner without interruption, and to complete the construction thereof within the time specified above. SANTA AIVA ( I PY COU NCI. MnalalA Pladn Meanlo 9armama i Where MaAwv. AngoWMnesava P. Mavld, Blolividnw Roman ROY,16 gal 71118101. Map, 1 Mryru I'm Tan W`nA 1 We, d2 1. VMOO Wad4 wnrd3 MW 9A U n, Q9W A.vlZ&A.Ae11�1'Y. l MOM Poo-nnx my a Cym oil J1Ii00921R @_.1f„".R?tiWA aAYIlh@MIW- .4n(t® 11L.LIp1,4VP?L[tle.a'.W 01 MAYOR Miguel A. Pulldo MAYOR PROTEM Vicente sonviiento COUNCII.M°.MBERS Angollca Amezoua P. David Henavides Ivilchele Marthtez. Roman Rayna sal'rinajaro REPLACE with; 11'Y OF SANTA MA NA 20 Civic Canter Plaza • P O, Box 1 H8 IN -s® Santa Ana, Gallforrda e2702 04I'r•5010 wWW.59 r1 aa a,ol:tl CI I Y MANAULH David Cavazos CITY ATTORNEY Sonla R. Carvalho CLERK Or THE COUNCIL Marla D. HOzalr The bidder also proposes to commence construction of the Work within ten 10 da s after the Issuance of a Notice to Proceed, and to continue in a diligent and workman -like manner without interruption, and to complete the construction thereof within the time specified above, 5. SPECIFICATIONS Page 36, 38, and 40; Sewer Bypass The sewer bypass and pumping plans shall be conforming to section 7 -842 of the Standard Specifications, These shell be submitted for approval by the City Engineer prior to commencement of work. REPLACE with: The sewer bypass and pumping plans shall be conforming to section 7 -8,6,2 of the. Standard Specifications. These plans shall be submitted for approval by the City Engineer prior to commencement of work. 6. PRE -BID MANDATORY MEETING Attendance Sheet In the attachment you will find the list of potential bidders for Project '16-Ml; Warner Industrial Community Water and Sewer Improvements. All proposed bids from non attendees will be rejected. SANTA ANA CITY COUNCIL Mleuel A. PAdo Vicente %rmlmnlo Wilda mmlinaz i Arlynlal 14nlnxCAtl 1 a. sevid 13anElddu'; I Roman IReyna i 'U i'Irtnjera Ma /a' Mayor Pro Tern Waal 'I Wal'12 Wpna Wadl M"II5 Ward0 1- Yull141SaL'u �.?ae�iente(?. sw�, aAassn mRRas_tad>_,.leo ya,�lu ¢.arj ue�/J� tlllsnoRlAssW.rno(aarunr!! I IaernldP��nxu"Jwu.�lu .IVaNeroA*ss.+¢s:�^14nAk 1 MAYOR MIguol A. l lklo (MAYOR PRO -1 EM Viclento S2rm ionko COUNCII.MEMDERS Angalica ArnaZOUa P , David sonavidea MlgPaale Martinaz Rorrmn Reyna Sal "1'lnaj:ro All other items remain CITY OF SANTA ANA 20 clvic Center Plaza a P.C. Box 1988 M-38 Santa Ana, California 92702 (714) 647 -5013 wv wsan a 3rla,o� This Addendum contains total of five (5) pages FCR THE CITY OF SANTA ANA l° Edwin "William" alvez, P.E. City Engineer Ul I Y MANAGER David C,.avazoo CITY ATiORNI:.Y Sonia R. Carvaiho CLERK On 'NE COUNCIL Marla 0, Hulzar SAN IA ANA CI1Y COUNCIL MiguelA PUlirlo V,=(Q Sarcnlllnlu i ROOM MIU9now i Angrdlca AAwxcua P. U3vld B.I,Rodua r lYlnRflyln Sol Tloallaro !la /' Mal'4tt l' IM I q0l WOi d l Waitl ll ''Paw:i Vfiud -h Wards Wad fi mellLlm E,j.LLa mr,"Stlhmp n..ulu:A1l&,1A omm9 k.L00.11].Li:i116ml uavnu a MSB_eIIu I adt' R..P11"' Nana 23B-31 {I T70 l`�`�I If1��1J1"1' h� c rl ? a lZ IA 15 CL 23B-31 Pipeline, Inc. LIST OF COMPLETED PUBLIC WORKS PROJECTS Project Name: Kana Project # 6821 - Eastside Water Facility PH2 790 Zone Pipeline Location: Merrill Avenue & Bon View Ave., Chino Description: 9,160' of 24" PVC C905 Waterline, Traffic Control, Permanent PAving Owner: Watson Land Company Project Manager: Chris Trujillo / Cell #310 - 729 -4623, 310 - 952 -6432 Contract Amount: $ 2,838,260.00 Start Date: 9/25/2015 Date Of Completion: 5/25/2015 Kana Pipeline Public Works Resume [Confidential] /Page 1 of 25 as of 1/2015. 23B -32 BAs_. „e Protect Name: Kana Project# 5172 — Airport Industrial Storm Drain Extension Replacement. Location: Van Buren and Morris, adjacent Riverside Airport Description: 242 LP of 60" RCP installed within 84" steel casing for boring underneath adjacent railroad, 36" Storm Drain Inlet, Junction Structure Total Man- hours: 586 Owner: City of Riverside, Purchasing Division 3900 Main Street, Riverside, CA 92522 Protect Manager: Mike Wolffe; cell (951) 901 -5440 email: MWoIffkriversideca.eov ; office (951) 826 -5990 Contract Amount: $ 306,500.00 Start Date: 10/18/2011 Date Of Completion: 11/30/2011 Kana Pipeline Public Works Resume [Confidential] /Page 2 of 25 as of 1/2015. 23B -33 Project Name: Kana Project # 4812 - OCTA Tustin Metrolink Parking Structure Location: Tustin, CA (2975 Edinger Ave./ TG 860 D -1) Description: Night work to relocate sewer and storm drainage pipeline work so as not to disturb adjacent businesses, as well as water and f "ireline systems to make way for a new parking structure for the Orange Co mty Transit Authority. Highlights: Pipeline work generally consisted of relocating sewer, and storm drainage pipeline systems, in addition to a new water and fireline system in order to build a new parking structure adjacent to existing set of office buildings for OCTA. Specifically, 4" -24" storm drain pipelines with catch basins, storm drain manholes, junction structure and a storm water filter vault; Sewer pipes ranging from 4" to 8" with corresponding manholes, cleanouts and a sewer bypass; Water pipelines between 2 " -8" with related valves, hydrants, backflows, detector check, fire department connection (FDC) and infrastructures. Total Man- hours: 2,806 Owner: City of Tustin, 200 Centennial Way, Tustin, CA 92780 Project Manager: Scott Lesard, Sr. PM, Bomel Construction (714) 921 -1660 Contract Amount: $ 531,996.00 Start (Date: 11/02/10 Date Of Completion: 10/6/2011 Kana Pipeline Public Works Resume [Confidential] /Page 3 of 25 as of 1/2015. 23B -34 Proiect Name: Kana Project# 4301 - Crescent Drive Underground Garage — Beverly Hills Location: 455 N. Crescent Drive, Santa Monica Boulevard Description: 1,400' of 18" VCP Sewer Main, 1,000' of 8" DIP Water main. Additional detail: Kana installed sewer and water pipeline systems in busy streets to sustain a future underground parking garage located next to Beverly Hills City Hall, This project consisted of abandoning and removing existing sewer manholes, constricting 8ea. 48" sewer manholes, saw cutting and zipping trench lines, installing a 18" VCP clay pipe sewer main in the street right of way, rerouting sewer pipelines, sewer video, base paving, capping, slurry sealing streets, restriping and traffic loops; approximately 1,000 LF 8" and 6" ductile iron (DIP CL 52) water pipeline main and lateral pipe, respectively, for post office, fire hydrants , removed and replaced sidewalk; Kana's Subsurface Utility Engineering Department conducted approximately 70 potholes to verify location of existing utilities, and necessary traffic control to maintain driver, pedestrian and construction work zone safety. Total Man - hours: 5,201 Owner: City of Beverly Hills Proiect Manaeer: Jason Lin (562) 903 -2277 Contract Amount: $ 1,213,564.00 Start Date: 11/02/2009 Date Of Completion: 07/01/2010 ]Cana Pipeline Public Works Resume [Confidential] /Page 4 of 25 as of 1/2015, 23B -35 ._. Pipeline, Project Name: Kana Project 4 4670 - Lampson Avenue Well Phase 2 — Offsite Water & Sewer Location: Lampson Avenue. Description: 1,300 of 8" Sewer Main & 3,500 of 16" Ductile Iron Water Main, 160' of 12' DIP water main. Total Man - hours: 3,805 Actual / 100 Initial Contract Working Days/ 176 Actual Working Days Owner: City of Seal Beach 211.8`'Street Seal Beach, CA 90740 Project Engineer: Contract Amount:_ Start Date: Date Of Completion: David Spitz 562- 431 -2527 x1331 $ 2,018,673.00 06/16/2010 10/08/2010 Kana Pipeline Public Works Resume [Confidential] /Page 5 of 25 as of 1/2015. 23B -36 Proiect Name: Kana Project # 4824 -Domestic Waterline Improvements E -13 & E -14 Location: San Juan Capistrano (the oldest city in Orange Countyl) Description: 2,600' of 12" PVC C900 Water line, 12 ", 10" and 8" Line Stops, gate valve replacements, 14 fire hydrant replacements, air release assemblies, blow off assemblies, utility overcrossing, Jack & Bore; all related testing and disinfection, AC Removal and replacement. Total Man - hours: 2,929 Owner: City of San Juan Capistrano 32400 Pasco Adelanto San Juan Capistrano, CA 92675 Proiect Engineer: Joe Mankawich (949) 487 -4313 Direct./ (949) 443 -6348 Main Public Works Line ( "Naomi" x 6337) imankawich9sanjuancapistrano .org Contract Amount: $664,950.00 Start Date: 10/4/2010 Date Of Completions 02/21/2011 Kana Pipeline Public Works Resume [Confidential] /Page 6 of 25 as of 1/2015. 23B -37 AMMW i li�'Kana Pipeline, Inc. Project Name: Kana Project # 4666 - Long, Beach & Imperial Highway Sewer .Main Replacement Location: Long Beach Boulevard & Imperial Highway Description: 84" MH LACSD Type "E ", 440' of 8" VCP, connect to existing 54" Truck sewer, Total Man - hours: 1,800 Owner: City of Lynwood Proieet Enpineer: Ken Putnam (818) 808 -5442 kputnamoQinfeng.co Contract Amount: $349,000.00 Start Date: 06/01/2010 Date Of Completion: 01/13/2011 I {ana Pipeline Public Works Resume [Confidential] /Page 7 of 25 as of 1/2015. 23B -38 Location: City of Ontario, 700 W. Rosewood Ct. Description: 7,500' of 8" Recycled & domestic water line, 30OLF of 8 "CML &C Steel Pipe, gate valves, blow off assemblies, hot taps to existing 42" slid 36" pipeline, fire hydrant assemblies (4), 1" water services (38ea.), asphalt concrete pavement for trench, rubber polymer modified slurry, removal, salvaging and abandonment, traffic striping and markings, adjustment of water valves cover to grade, all testing sheeting, striping, shoring, bracing, traffic control, SWPPP and BMP's, and related work to perform this, and all- related projects safely, 'Dotal flan - hours: 4,839 Owner: City of Ontario 1425 South Bon View Avenue Ontario, CA 91761 Project EnL=ineer: Peter Tran, P.E. (909) 395 -2677 / ptran(g ci.ontario.ca.us Contract Amount: $931,000.00 Start Date: 05124/2010 Date Of Completion: 10/14/2010 Kana Pipeline Public Works Resume [Confidential] /Page 8 of 25 as of 1/2015. 23B -39 YM Project Name: ICana Project# 5060 — Eastside and Main Street Water Distribution Replacement. Location: Main Street & Stoddard Ave Description: 12,300 LF of 8" Ductile Iron Pipeline, fire hydrants, installed over 500 combined domestic water, reclaimed, and (reline services (1 ", 2" & 4" domestic and 4" & 6" fire services), Total Man - hours: 10,837 / 208 Approx Working days. / 200 Original Contract Time in Days. Owner: City of Riverside, Purchasing Division 3900 Main Street, Riverside, CA 92522 Project Manager: Leonardo Ferrando (951) 826 -5694 / lferrando(2riversideca.gov Contract Amount: $ 1,687,570.50 Revised Start Date: 3/4/2011 Date Of Completion: 12 /28/2011 Kana Pipeline Public Works Resume [Confidential] /Page 9 of 25 as of 1/2015. 23B -40 Project Name: ICana Project# 5162 — Sewer Replacement and Road Reconstruction Location: Chapman Ave., Fullerton, CA Description: Removing and replacing old sewer pipeline mainlines with new sewer main for the City of Fullerton, along Chapman Ave and nearby side streets amidst residential neiehborhood. Installed approximately 4,000 LF of 8" VCP Sewer Main installation; 150 LF of 8" Ductile Iron Sewer Main, sewer manholes, lateral reconnections, removed existing VCP sewer main pipeline, manholes, and sewer cleanouts; installed an Access Ramp per APWA and access ramp retrofit; installed now sidewalk, curb a gutter and cross gutters, alley returns, aggregate base, asphalt concrete, adjusted sewer manholes and water valves to grade; installed street light conduit; carried out Water Pollution Control, Traffic Control, Clear and Grub, Sheeting, Shoring and Bracing. Note, This was a 100% import and 100% export material soil project. Total Man- hours: 5,733 Owner: City of Fullerton, 303 W. Commonwealth Ave., Rm # 207, Fullerton, CA 92832 Proiect Manager: Eric Villagracia, (714) 738 -6853 Contract Amount: $1,415,119.45 Start Date: 5/23/2011 Date Of Completion: 9/15/2011 Kana Pipeline Public Works Resume [Confidential] /Page 10 0£25 as of 1/2015, 23B -41 Project Name: Kana Project # 5215 — Plumosa Drive Waterline Location: 4444 Plumosa Dr. (X Lemon Blvd.) Description: Water Pipeline Replacement Project, Phase 1, on Plumosa Drive. Installed approx 3,000 LF of 12" C -900 PVC pipe for domestic water, fire hydrants, water pipe line laterals, abandonments, relocations, slung backfill, pavement repair, and all necessary traffic control, permits, BMP's and NPDBS compliances. Total Man - hours: 3,693 Owner: Yorba Linda Water District (YLWD) Project Manager: Joe Polimino, Construction Supervisor (714) 701 -3104 jolimino a,ylwd.coin Contract Amount: $668,112.50 Start Date: 06/15/2011 Date Of Completion: 12/14/2011 Kana Pipeline Public Works Resume [Confidential] /Page 11 of 25 as of 1 /2015. 23B -42 A�:... At=7Kana Pipeline, Inc. Proiect Name: Kana Project 4 5212 — Concrete Street Water Pipeline Improvements Santa Ana Location: Various streets throughout Santa Ana, CA Description: Karla Pipeline installed several thousand feet of water pipeline main and related infrastructures along Concrete Street in various locations.Over 6,000 LF 8" and 12" PVC C900 water main pipeline, 1" & 2" water services, resilient wedge gate valves, a fire line main and lateral with new fire hydrant assemblies, and hot taps; traffic control and pavement markings; cold mill and asphalt pavement overlays /grind and cap. Total Man - hours: 5,792 Owner: City of Santa Ana Project Manager: Edward Torres, Project Manager of Construction (714) 647 — 5018 / etorres@santa- ana•org Contract Amount: $ 723,755.00 Start Date: 07/11/2011 Date Of Completion: 3/23/2012 Kana Pipeline Public Works Resume [Confidential] /Page 12 of 25 as of 1/2015. 23B -43 o � :i'i. Pipeline, Inc Pro iect Name: Kana Project # 4337 — Sewer Rehabilitation, Cypress, CA Location: Cypress, CA (Katella and Holder) Description: Installed approximately 8" VCP 419LF, and 12" VCP 1,332 LF pipeline installation, including street resurfacing, curb and gutter reconstruction, mobilization, traffic control, 14 house sewer lateral reconnects, removal and disposal of conflicting existing sewer lines, 1,751 LF, flush ex sewer and install 8" PVC Lining for 255 LF, Install Sancon 200 coating inside manholes, 1,000 - gallon ground water treatment for groundwater dewatering purposes. Total Man-hours: 3,506 Owner: City of Cypress, 5275 Orange St., Cypress, CA 90630 Project .Manager: Cameron Dadbeh General Manager (714)229 -6740 Contract Amount: $ 700,855.00 Start Date: 12/14/2009 Date Of Completion: 4/30/2010 Kana Pipeline Public Works Resume [Confidential] /Page 13 of 25 as of 1/2015. 23B -44 tom. Project Name: Kana Project # 5822 — Irvine Regional Park — Water Main work Location: Orange, CA (Jamboree X Santiago Cyn/ TG 800 J -2) Description: 2 Phases of work: Total: PVC 0900 CL 150 pipe —12" at 1,475LF, 10" at 9,198 LF, 8" at 7,682 LF, 8" FH Lateral 1,682 LF, 6" office at 172 LF, thrust blocks, bends, 6",8 ",10" and 12" gate valves, 29 fire hydrant assemblies, and a connection to existing FH, 7ea, 2" Air Vacuum Relief Valve Assemblies, 10" RPDA, temp connection to water main, water main abandonments, ; Also includes, mobilization and demobilization, SWPPP, Traffic Control, Stub Out to Lake, Connect existing Domestic Water, Abandon Existing Water Lines, Remove and Replace Trench Asphalt Pavement, SOC Trench Restoration, Potholing of existing Utilities, Arborist and Tree Protection, Concrete Work, Testing Total Man - hours: 7,744 total man hours; 6,651 original man-hours budgeted. Owner: County of Orange, OCCR / OC Parks 1501 E. St. Santa Ana, CA 92705 Project Manaser: Doug Giltner, Sr, PM, (714•) 425 -8937; dou . iltner occr.oc og v.eom Ref: Project No. OCCR12 -007 /Additional Reference: 3`d Part F/T Onsite Inspector = Denis A Dembik ( "DAD "), QSP, Construction Manager, Harris & Associates 34 Executive Park Suite 150, Irvine, CA (949) 655 -3900 / C (714) 318 -8706 ddembik@.harri-assoc.com Contract Amount: $ 2,392,181.90 Start Date: 7/24/12 Date Of Completion: 5/10/13 Kana Pipeline Public Works Resume [Confidential] /Page 14 of 25 as of 1/2015. 23B -45 Location: Huntington Beach, CA, CA (All between I hh 12`b, 14' 15o1i 16Th 27th 23`d, and 24d' streets, from N Pacific Ave., to Pacific Coast Highway (PCH); ref: TG 826 J7) Description: Furnish and install 907 LF 6" and 240 LF 1.2" DR -14 PVC AWWA C900, a 12" bore of steel casing under CalTrans alley approach, 1" and 2" water services and % and I" water meter assemblies with meter box; removing existing meter box; chlorination and testing of all new water main and appurtenances, Asbestos Cement (AC) pipe legal disposal; 4" blow off assemblies, remodel 4 sewer house connection laterals conflicting with proposed waterline, remove and salvage exist FH including removing buy, valve and appurtenances; conducted preconstruction survey of existing home and street as required by contract does., temp water services and blow off, 4" temp hot tap to existing 6" AC Pipeline valve; all related traffic control, Also includes mobilization, demobilization and cleanup as well as alley rehabilitation for all sites. Total Man - hours: 4,956 total hours; approx 200 working days to complete. Owner: City of Huntington Beach, 2000 Main Street, HB, CA 92648 Project Manager: Duane D. Wenthworth, CM, (714) 536 -5517; dwentworth(Asurfeity- hb,org (Lili Hemadez 714 - 374 -5386 Contract # 1412 Amount: Contract $ 1,324,306.24 Start Date: 11/13/12 Date Of Completion: 5/18/2013 �e Kana Pipeline Public Works Resume [Confidential] /Page 15 of 25 as of 1/2015. 23B -46 Pipeline, Pro ect Name: Dana Project # 6426 — Sunset Beach Water Phase 2 Location: Various Streets near the beach; near homes, Description: New Pipeline for the Sunset Beach Water Main and Pavement Replacement Construction Project CC -1429 Highlights: Bids were opened publicly in mid October of 2013 where Kana Pipeline was officially awarded the project after providing the lowest responsive and responsible bid, placing 3rd lowest behind a non- responsive bidder and another bidder who withdrew their bid. This pipeline work is part of the City's water main replacement program, where it was identified that 1,200 LF of old, existing water mains in eight different alleys throughout Sunset Beach were required to be abandoned or replaced; from Warner Avenue to Anderson Street. This project involves replacing existing 34" asbestos cement pipelines installed in the 1950's, with new 6 -inch PVC (plastic) pipelines. The project will also include reconstruction of alleys after waterline is installed. It was determined that combining both the water improvements with the street improvements would avoid a second, separate construction impact to local residents and businesses for future pavement rehabilitation, Fire hydrants will also be installed along Pacific Coast Highway which will allow better accessibility to the Fire Department, Total Man - hours: 4,956 total hours; approx 200 working days to complete. Owner: City of Huntington Beach, 2000 Main Street, HB, CA 92648 Project Mananer: Lily Hernandez, PE, (714) 374 -5386, lernandez cr,surfcit -leg, or Michael Helma, CM (562) 342 -7027, mahelma(ktransystems.com Contract Amount: Original $ 1,647,715.00 Start Date: 12/6/2013 Date Of Completion: 7/2014 Kana Pipeline Public Works Resume [Confidential] /Page 16 of 25 as of 1/2015. 23B -47 Pro iect Name: Kana Project # # 5629 - The Preserve CFD #2003 -3 Location: Chino, CA (Pine Ave. at W. Preserve Loop; TG Pg #712 F -1) Description: Scope of work includes sewer, domestic and reclaimed water and storm drain installation; utility potholing; approximately 5,000 LF of 10 ", 12" and 15" VCP clay sewer, l8ea, 10" manholes, includes a 29" jack and bore steel pipe casing underneath Pine Ave.; Domestic water scope of work includes over 5,500 LF of 12" PVC C900CL200 pipe; over I GOLF of 8" PVC C900 CL200 installation; Bea, 12" gate valves and 2ea 6" gate valves, bends, blow off assemblies, flanges and a 30" blind flange, reclaimed water installation of 3,000 LF of 8" PVCC900CL200 Purple pipe, 8" gate valves, air vac assemblies, 12 "x6 "cross, 12 "x6" reducer, fire hydrant assemblies, Over 1,200 LF of 24 ", 42" and 60" RCP storm drain pipe, catch basins, junction structures, Clear and grub, SWPPP Implementation, Traffic Control; Total Man - hours: In Progress Owner: LCD Homecoming at The Preserve, 1156 N, Mountain Ave., Upland, CA 91786 / Lucas Companies, Project Manager: Jason Miller (909) 946 -7521; jason millernlewisop.com Contract Amormt: $ 1,406,352.00 Start Date: 12/19/2011 Date Of Completion: 9/12/2013 Kana Pipeline Public Works Resume [Confidential] /Page 17 of 25 as of 1/2015. r Proiect Name: Kana Project # 6120 -- Water Main System Replacement 2012 -2013/ PO P0014 Location: Fullerton, CA, (Jobsite Located at W. Valencia Dr., between Basque Ave. and Richman Ave.); USA's on Rolling Hills Dr. at E. Rosalia Dr and Maple Ave. Description: Furnish and install 3,340 LF of 8" PVC CL150, and 2,680 LF of 12" and 2,750 of 16" water pipeline main; 4: and 8" meter connections, 8" and 12" gate valves, hot taps, fire hydrant removals and installations, I" air vac assemblies, 4" blow off assemblies, residential driveway reconstruction, curb access ramp and modified curb access ramp, cross batter /spandrel, local depression, asphalt concrete and aggregate base, adjustment to sewer manholes to grade and adjustment of water valves to grade; Includes mobilization and demobilization, NPDES compliance, clear and grub, traffic control, signing, striping and loops. Total. Man- hours: 7,534.00 man-hours Owner: City of Fullerton, CA 303 West Commonwealth Avenue Fullerton, CA 92832 Proiect Manager: Vince Oseguera, CM, (714) 738 -6851, VinceraOQa ci.fullerton.ca.us Contract Amount: $ 2,286,000.00 Start Date: 2/28/13 Date Of Completion: 10/9/2013 Kana Pipeline Public Works Resume [Confidential] /Page 18 of 25 as of 1/2015. 23B -49 Location: Garden Grove, CA (Trask Ave., / Lily Street) Description: Furnish and install approx 3,500 LF of PVC C900 CL200 in 4 ", 6 ", 8 ", and 12" sizes; install corresponding 4 -12" gate valves, connections to main, abandonments in place; 50ea. 1" water services, 4" water service, removal and installation of 7 ea. Fire hydrants, sheeting, shoring, bracing, traffic loop detectors, slurry seal over asphalt including temp stripingand all related traffic control. Total Man- hours: Budgeted Man -hours 2,430 Owner: City of Garden Grove 11222 Acacia Parkway, Garden Grove, CA 92840 Project Manager: Rebecca Li, Assoc. Engineer /PM (714) 741 -5562, rebeccalgei.garden- grove.ca.us Contract Amount: $ 825,000.00 Start Date: 5/28/13 Date Of Completion: 8/30/13 Kana Pipeline Public Works Resume [Confidential] /Page 20 of 25 as of 1/2015. 23B -50 _a Project Name: ICana Project # 6167 - Trask Ave - Lily St. Water Improvements Location: Garden Grove, CA (Trask Ave., / Lily Street) Description: Furnish and install approx 3,500 LF of PVC C900 CL200 in 4 ", 6 ", 8 ", and 12" sizes; install corresponding 4 -12" gate valves, connections to main, abandonments in place; 50ea. 1" water services, 4" water service, removal and installation of 7 ea. Fire hydrants, sheeting, shoring, bracing, traffic loop detectors, slurry seal over asphalt including temp stripingand all related traffic control. Total Man- hours: Budgeted Man-hours 2,430 Owner: City of Garden Grove 11222 Acacia Parkway, Garden Grove, CA 92840 Proiect Manager: Rebecca Li, Assoc. Engineer/PM (714) 741 -5562, rebeccala,ci. arg den- exove.ca.us Contract Amount: $ 825,000.00 Start Date: 5/28/13 Date Of Completion: 8/30/13 Kana Pipeline Public Works Resume [Confidential] /Page 20 of 25 as of 1/2015. 23B -51 Pipeline, Inc. Project Name:_ Kana Project # 5893 20" SC -4 Transmission Line Location: 28811 Ortego Hwy x Antonio, San Juan Capistrano, CA Description: Join existing 20" Steel main to 500 LF of 20" CML &C, 4' blow offs, 4" combination air vac assemblies, CPT Test Station, 96" Water Vault, 8" weld nozzle and hot tap, Total Man- hours: Budgeted Man -hours 731 Owner: RMV Community Development, LLC Project Manager: Scott Leetzow sleetzow @ranchomv.coin (951) 712 -6591 Contract Amount: $ 307,247.00 Start Date: 9/23/12 Date Of Completion: 8/26/2013 Kana Pipeline Public Works Resume [Confidential] /Page 21 of 25 as of 1/2015. 23B -52 CITY OF SANTA ANA PROPOSAL PROJECT NO. 16 -6461 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS KNOW ALL PRESENT that, Kana Pipeline, Inc. as BIDDER, and Fidelity and Deposit Company of Maryland as SURETY, are held and firmly bound unto the CITY OF SANTA ANA, as AGENCY, in the penal sum of Ten Percent ofthe "Total Amount Bid Dollars ($___101/,) of Bid ), which is ten percent (10 %) of the total amount bid by BIDDER to AGENCY for the above - stated project, for the payment of which sum, BIDDER and SURETY agree to be bound, jointly and severally, firmly by these presents. THE CONDITIONS OF THIS OBLIGATION ARE SUCH that, whereas BIDDER is about to submit a bid to AGENCY for the above- stated project, if said bid is rejected, or if said bid is accepted and a contract is awarded and entered into by BIDDER in the manner and time specified, then this obligation shall be null and void, otherwise it shall remain in full force and effect in favor of AGENCY. IN WITNESS WHEREOF the parties hereto have set their names, titles, hands, and seal this 13th day of April 20 16. BIDDER* SURETY* tttl# C- 1tN -lr) V, IA -cx> Fidelity and Deposit Company of Maryland 777 S. Figueroa St. 93900, Los Angeles, CA 90017 (213) 270 -0715 Subscribed and sworn to before me this day of See Attached Notary Acknowledgment for Surety Signature: Notary Public in and for the County of , State of *Provide BIDDER/ SURETY name, address, and telephone number and the name, title, address, and telephone number of authorized representative. P -9 OF P -17 23B -53 California All - Purpose Acknowledsement State of California County of Orange On -I 4cl `zb1 before me, Herres SalvadotTabadero Notary Public Date Na ne & Title of Oftiaer personally appeared a 1) t+--i_ LL Narrt0) of SigneKs) who proved to me on the basis of satisfactory evidence to be the person(s) whose name($) is /are subscribed to the within instrument and acknowledged to me that he /she /they executed the same in hiss /their authorized capacity(ies), and that by his /Her /their signatures($') on the instrument the person(s), or the entity upon behalf of which the person(45 acted, executed the instrument. I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true & correct. WITNESS my hand & official seal. .Signature of Notary Public #ERNES SARAaBA TAB;RR'O COMM, #2666708 i tNotary Public • California Orange County Comm. Expires May 30,2018t Notary Seal O at i ona l 1 n fo� Description of Attached Document: Title or Type of Document: t') P i'-"50 V D Document Date: ,Number of Pages: Signer(s) Other Than Named Above: Other information: California All - Purpose Acknowledgement State of California County of Orange On _ A 1 `� 1170(,- before me, Hemes Salvador - Tabadero Date Name & Title or personally appeared V� X 1J ti= L L�� Name(,) or signer(&) who proved to me on the basis of satisfactory evidence to be the person(&) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he /she /they executed the same in his/her /their authorized capacity(ias), and that by his /her /their signatures(s) on the instrument the person(s), or the entity upon behalf of which the person(ls acted, executed the instrument. i certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true & correct. WITNESS my hand & official seal, Notary ORtional Information Description of Attached Document: Title or Type of Document: o (17 e'o � 0 Document Date: Signer(s) Other Than Named Above: Other information: HERNES SAIMADOR TABA0ER0 COMM. #2066708 a Notary Public • California D Orange County Comm. Ex ires Ma 30, 2018 Number of Pages: Notary Seal Ci3t',tt°OMMIA zi UI,�tilt d'-'? ffira fit47 14 _ Q() u 1189 A notary public, or other officer aampieting ihls certificate verifies only the identity of the individual who signed the documant to vrN,lb this coRificate k attached, and not the truthfulness, accuracy, or validity of that k)CUlnef t. State of California ) County of .. , Orange (-)n n �P� _ �Q� before me., _Rb ondr G. Ab ©l, N,o_t� atyPublic, a Date Here Insert Name and Otte of the Officer personally appeared I-]egthet Saltarelli Narnels) of Signer(s) who proved to me on the ba sis of satisfactory evidence to he the person(g) whose iiain°(,x) islam subscribed to the within instrument and acknowledged to rno that t,p /she /f y, executed the same In P isther /iX h74 authorized capacity(pC j. and that by kilc /her /0199 signafi r'or6) on the instrument the person,N), or the entity upon behalf of which the parson(s) acted, exectited the Instrument. r RH2 DA CC ABEL � O COM'bA. # 2061838 � ORANGE C, CALIFORNIA 0 ORANGE DEC 142 n � COMM. EXPIRES UEC. 14, 2617 - I certify under PENALTY OF PERJI, i ?Y under the laws of the State of California that the foregoing paragraph is true and correct. WITNESS my hand and of #ic:i<al -seal. toy Srgnatlure of AoMmy Pithlic OPTJONAL TtaofJ9h tai ;ti n i optional, tional, r' .. iipla -ig hi J1TliiCli7c94i07i 08i1 d �= rcli2rv'Pl, i t, f'r� CicJ _t ric l?' or fraudulrvig reattachment of this form to an unintended docwncwt. Description of Attached Ow,,wce:rtt Title or Type of Dacurnent _._. _.. _..._ _ document Date:- __....... Number of Pages: _ _. Signer's) Color 'rhan Nanned Above: Capacity(les) Maimed by Signar(s) Signer's Name: _. _ _-_- ._._ Signer's Name: _ Corporate Officer -- 'Dtie(s): _ _ Corporate Officer ... Title(s)' ._.. Partner ,_ Limited General Partner -- Limited General Individual x Attorney in Fact Individual Attorney in Fact Trustee Guardian or Conservator Trustee Guardian or Conservator Other: _. _ ___.. .._ Other: Signer Is Representing: Signer Is Representing: �4"iACS%UTY�' „ZtS�te;KtCX;4,u St .` r.; 45�KRS�+: S. GYZK�.'< 5(" 6' Zr- aC£ �: �'. �ZtLF.' y'C3�SY2"SCLFCS�,vzv«4 %'t..3:[. ��i4" %'L"S:V'4n- ;!•:S:L'��4v_°e;!�'i Cc }P014 National Notary Association , v +ww.Nationalidotary,org r 1.600•L)S NOTARY (1 -1300- 876.68271 Item )75907 23B -56 ZURICH AMERICAN INSURANCE COMPANY COLONIAL AMERICAN CASUALTY AND SURETY COMPANY FIDELITY AND DEPOSIT COMPANY OF MARYLAND POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That the ZURICH AMERICAN INSURANCE COMPANY, a corporation of the State of New York, the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, a corporation of the State of Maryland, and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND a corporation of the State of Maryland (herein collectively called the "Companies "), by THOMAS O. MCCLELLAN, Vice President, in pursuance of authority granted by Article V, Section 8, of the By -Laws of said Companies, which are set forth on the reverse side hereof and are hereby certified to be in fall force and effect on the date hereof, do hereby nominate, constitute, and appoint James A. SCHALLER, Mike PARIZINO, Rachelle RHEAULT, Rhonda C. ABEL, Kim LUU, Jeri APODACA and Heather SALTARELLI, all of Newport Beach, California, EACH its true and lawful agent and Attorney -in -Pact, to male, execute, seal and deliver, for, and on its behalf as sorely, and as its act and deed: any and all bonds and undertakings, and the executign of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Companies, as folly and amply, to all Interns and purposes, as if they had been duly executed and acknowledged by the regularly elected officers of the ZURICH AMERICAN INSURANCE COMPANY at its office in New York, New York., the regularly elected officers of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at its office in Owings Mills, Maryland„ and the regularly elected officers of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at its office in Owings Mills, Maryland„ In their own proper persons. The said Vice President does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article V, Section 8, of the By -Laws of said Companies, and is now In force. IN WITNESS WHEREOF, the said Vice- President has hereunto subscribed his /her names and affixed the Corporate Seals of the said ZURICH AMERICAN INSURANCE COMPANY, COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 19th day of August, A.D. 2015. ATTEST: ZURICH AMERICAN INSURANCE COMPANY COLONIAL AMERICAN CASUALTY AND SURETY COMPANY FIDELITY AND DEPOSIT COMPANY OF MARYLAND •�'GM•.'I.BNa..a .. .�h v gg0 A hhhgo n, Secretary Vice President Eric D. Barnes Thomas O. McClellan State of Maryland County of Bold more On this 19th day of August, A.D. 2015, before the subscriber, a Notary Public of the State of Maryland, duly a>mmlssloaed and qualified, THOMAS O. MCCLELLAN, Vice President, and ERIC D. BARNES, Secrotary, of the Companies, to me personally known to be the individuals acid officers described in and who executed the preceding fnsb'ument, and acknowledged the execution of same, and being by me duly sworn, deposeth surd Salta, that helshe is the said officer of the Company aforesaid, and that the seals affixed to the preceding insnvmenu are are Corporate Soaks of said Companies, and that the said Corporate Seals and the signature as suoh officer were duly affixed and subscribed to the said instrument by the authority and direction of the said Corporations. IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above written POA-F 012 -9310Q 23B -57 9(3�;ah116i fF q Maria D, Adamsld, Notary Public My Commission Expires: July 8, 2019 POA-F 012 -9310Q 23B -57 EXTRACT FROM BY -LAWS OF THE COMPANIES "Article V, Section 8, Attorneys -in -Pact. The Chief Executive Officer, the President, or any Executive Vice President or Vice President may, by written instrument under the attested corporate seal, appoint attorneys -in -fact with authority to execute bonds, policies, recognizmrees, stipulations, undertakings, or other like husbuments on behalf of the Company, and may authorize any officer or any such attornoy -Iii-fact to affix the corporate seal thereto; and may with or without cause modify of revoke any such appointment or authority at any time." CERTIFICATE I, the undersigned, Vice President of the ZURICH AMERICAN INSURANCE COMPANY, the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY', and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify that the foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that Article V, Section 8, of the Bylaws of the Companies is still in force. This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of Directors of the ZURICH AMERICAN INSURANCE COMPANY at a meeting duly called and held on the 15th day of December 1998. RESOLVED: "That the signature of the President or a Vice President and the attesting signature of a Secretary or an Assistant Secretary and the Seat of the Company may be affixed by facsimile on any Power of Attorney, -Any such Power or any certificate thereof bearing such facsimile signature and seal shall be valid and binding on the Company." This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of Directors of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at a meeting duly called and held on the 5th day of May, 1994, and the following resolution of the Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a meeting duly called and held on the IOth day of May, 1990. RESOLVED: 'That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically reproduced signature of any Vice - Resident, Secretary, or Assistant Secretary of the Company, whether made heretofore or hereafter, wherever appearing upon a certified copy of any power of attorney issued by the Company, shall be valid and binding upon the Company with the same forme and effect as though manually affixed. IN TESTIMON] - E,[2L,( ,� have hereunto subscribed my name and affixed the corporate seals of the said Companies, this day of J' LU 120—. 40tPO3i e'py11NeUUq,���4 -1 w'r \,4y, ,'z ,. t Gerald F. Haley, Vice President 23B -58 CITY OF SANTA ANA Exhibit 3 CONSTRUCTION CONTRACT PROJECT 15 -6454 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER This CONSTRUCTION CONTRACT is made and entered into this 17`1' day of May, 2016, by and between the CITY OF SANTA ANA, CALIFORNIA, a charter city and municipal corporation organized and existing under the Constitution and laws of the State of California, hereinafter referred to as "CITY" and Kara Pipeline, Inc., hereinafter referred to as "CONTRACTOR". WITNESSETH: The CITY and the CONTRACTOR, for the consideration hereinafter named, mutually agree as follows: CONTRACTOR agrees to perform all the work and furnish all the materials at its own cost and expense necessary to construct and complete in a good and workmanlike manner and to the satisfaction of the City Engineer of the CITY, the Project No. 15 -6454: Warner Industrial Community Water and Sewer Improvements identified in and in accordance with the Contract Documents prepared by the City's Public Works Agency and approved by the City Council. 2. The complete Construction Contract consists of the "Contract Documents," as defined by the Standard Specifications for Public Works Construction and which include the following: • ..Notice Inviting Bids • ..Instructions to Bidders • ..Bid Proposal • ..Bid Bond • ...Contract Forms • ...Contract Bonds • ...General Provisions • ...Special Provisions ..Teetuiical Provisions ... Project Plans — Appendices In case of conflict between the Contract Documents, the precedence of documents shall be as established in the Standard Specifications for Public Works Construction. CITY agrees to pay and CONTRACTOR agrees to accept in fill payment to complete Project No. 15 -6454: Warner Industrial Community Water and Sewer Improvements the sum total amount not to exceed $3,457,000, as set forth and identified in the BID PROPOSAL, which is attached hereto and incorporated herein as Exhibit "A ". The BID Page 1 of 3 23B -59 CITY OF SANTA ANA CONSTRUCTION CONTRACT PROJECT 15 -6454 WARNER INDUSTRIUAL COMMUNITY WATER AND SEWER PROPOSAL contains a schedule of unit price(s) or lump sum(s) based on approximate quantities only, and the City does not expressly or by implication agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work or to omit portions of the wort, as may be deemed necessary or advisable. 4. CONTRACTOR agrees to complete the Work of Improvement within the time specified in the Time for Completion of Improvements section of the BID PROPOSAL (Exhibit "A ") including commencing construction within the timeframe therein specified after issuance of a Notice to Proceed. 5. The CONTRACTOR will pay, and will require all subcontractors to pay, all employees on the Work of Improvement a salary or wage at least equal to the prevailing salary or wage established for such work as set forth in the wage determinations for this work in accordance with applicable State and Federal law. 6. CONTRACTOR shall, after award of this Contract, furnish two bonds to be approved by the CITY, one in the amount of One Hundred Percent (100 %) of the Contract price, to guarantee the faithful performance of the work (Performance Bond), and one in the amount of One Hundred Percent (100 %) of the Contract price to guarantee payment of all claims for labor and materials furnished (Payment Bond). This Contract shall not become effective until such bonds are supplied to and approved by the CITY. 7. CONTRACTOR shall, prior to the release of the performance and payment bonds or the retention payment, furnish a warranty performance and payment bond (Warranty Bond). Said Warranty Bond shall also be required as a condition of project acceptance. For projects up to $500,000, the Warranty Bond amount shall be the greater of $10,000 or 20% of the final contract price. For projects above $500,000, the Warranty Bond amount shall be the greater of $100,000 or 10% of the final contract price. 8. CONTRACTOR shall, after award of this Contract, furnish Certificates of Liability Insurance and Worker's Compensation Insurance as outlined in the General Provisions, to be approved by the CITY./ H Page 2 of 3 23B -60 CITY OF SANTA ANA CONSTRUCTION CONTRACT PROJECT 15 -6454 WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IN WITNESS WHEREOF, the parties hereto have executed this Construction Contract on the day and year first above written. ATTEST: MARIA D. HUIZAR Clerk of the Council APPROVED AS TO FORM: SONIA R. CARVALHO City Attorney 13Y r e Sandoval hief Assistant City Attorney CITY OF SANTA ANA DAVID CAVAZOS City Manager RECOMMENDED FOR APPROVAL: Fred Mousavipour, P.E. Executive Director, Public Works Agency CONTRACTOR: Kana Pipeline, Inc By:_ Title: Page 3 of 3 23B -61 23B -62 COST ANALYSIS PROJECT NO. 16 -6461: WARNER INDUSTRIAL COMMUNITY WATER AND SEWER IMPROVEMENTS Construction Contract Contract Administration Inspection and Testing Contingencies TOTAL ESTIMATED DELIVERY COSTS Exhibit 4 23B -63 $3,457,000 $237,922 $280,628 $518,550 $4.494.100 23B -64