HomeMy WebLinkAbout25H - AGMT - GO LOCAL MANAGEMENT OVERSIGHTREQUEST FOR
COUNCIL ACTION
CITY COUNCIL MEETING DATE:
JULY 2, 2012
TITLE
AMENDMENT TO THE AGREEMENT
WITH CINDY KREBS CONSULTING,
INC. FOR GO LOCAL PROJECT
MANAGEMENT OVERSIGHT
PROJECT NO. 092505)
CITY MANAGER
RECOMMENDED ACTION
CLERK OF COUNCIL USE ONLY:
APPROVED
As Recommended
As Amended
Ordinance on 151 Reading
Ordinance on 2nd Reading
Implementing Resolution
Set Public Hearing For
CONTINUED TO
FILE NUMBER
Authorize the City Manager and Clerk of the Council to execute the attached amendment to the
agreement with Cindy Krebs Consulting, Inc. to extend the term of the contract to April 30, 2013 in
the amount of $165,000 subject to non-substantive changes approved by the City Manager and
City Attorney.
BACKGROUND
The Cities of Santa Ana and Garden Grove are working collaboratively with the Orange County
Transportation Authority (OCTA) on the Santa Ana-Garden Grove Fixed Guideway Project. Santa
Ana and OCTA have entered into two cooperative agreements for development of the project to
define their respective roles and responsibilities through Steps 2 and 3 of Measure M2's Go Local
Program. A Step 2 agreement for Environmental Analysis was executed in 2008 for an amount of
5.9 million, and a Step 3 agreement for Preliminary Engineering was executed in 2011 for an
amount not to exceed $5.5 million, contingent on the project's acceptance into the Federal Transit
Administration's (FTA) Section 5309 New Starts/Small Starts Program.
In early 2010, OCTA directed the City of Santa Ana to prepare the project for FTA Section 5309
New Starts/Small Starts grant funding because the project was considered to be a strong
candidate under this program. The FTA became actively involved in discussions with OCTA and
the Cities of Santa Ana and Garden Grove soon thereafter, and project deliverables were revised
and refined to satisfy the specific requirements of the FTA and submitted to the FTA for approval.
DISCUSSION
The City required professional assistance from a qualified consultant with extensive transit
background to take the Go Local Transit Vision from concept to completion. In 2009 the City
enlisted the services of Cindy Krebs Consulting Inc. (CKC) to work closely with the City's Project
25H-1
Amendment to Agreement with
Cindy Krebs Consulting, Inc. for
Go Local Project Management Oversight
July 2, 2012
Page 2 of 2
Manager and other key City, OCTA and consultant staff assigned to the Go Local Project. CindyKrebshasfunctionedasanextensionofstafftoprovideoversightanddirectiontothemodern
streetcar consultant team and other consultants selected to assist the City with key deliverables
and implementation of the Go Local Transit Vision.
In 2010, after the City's consultant contract with Cordoba Corporation for the Go Local Step 2 was
awarded, OCTA directed the City of Santa Ana to prepare the project for the FTA. CKC has been
providing technical support and project management for the Go Local project and it is
recommended that her contract be extended to ensure the continuity and success of the project.
Upon execution of this amendment, CKC will be the Project Manager responsible for the projectschedule, project budget and the administration of consultant contacts for the Fixed GuidewayProject. This third amendment will bring the total contract amount to not to exceed $645,000 and
extends the term to April 2013.
FISCAL IMPACT
The Project Management services for the maximum of $165,000 are funded in the OCTA
Transitway Project (account unit 03217661-66220, project no. 092505).
APPROVED AS TO FUNDS AND ACCOUNTS:
I HA ,-- i
I God' ez II Francisco utierre
Executiv irector/ Executive Director/
Public Wo ks Agency Finance & Management Services Agency
RG/SA
Exhibit 1: Third Amendment
25H-2
THIRD AMENDMENT TO AGREEMENT
BETWEEN CITY OF SANTA ANA AND
CINDY KREBS CONSULTING, INC.
THIS THIRD AMENDMENT TO AGREEMENT, made and entered into this 2nd day of
July, 2012 by and between Cindy Krebs Consulting, Inc., a California Corporation (hereinafter
Project Manager" or "PM"), and the City of Santa Ana, a charter city and municipal corporation
organized and existing under the Constitution and laws ofthe State of California (hereinafter
City").
RECITALS:
A. The parties entered into Agreement A-2009-091, dated June 8, 2009, by which Project ManagerhasprovidedservicesastheCity's Program Transit Management Consultant (PTMC) to assist in
forming and implementing the Go Local Transit Vision (said "Agreement").
B. Said Agreement has been amended on July 19, 2010, and again on May 16, 2011 to adjust the
number ofservice hours PM will provide, and to provide compensation for those services.
C. The parties hereto now would like to more fully define the services to be provided by Project
Manager, extend the agreement for an additional nine-month period, and add compensation for
PM's services during the extended term.
WHEREFORE, in consideration ofthe covenants contained in said Agreement, and subject to all
the terms and conditions of said Agreement, except those amended in this Third Amendment to
Agreement, the parties agree as follows:
1. Section 1, SCOPE OF SERVICES, shall be deleted in its entirety and replaced with the
following:
Project Manager shall serve as the City's project manager for the Santa Ana Fixed
Guideway Project ("Project"), responsible for delivering the completed Project on time and
within the budget, as set forth in Exhibit A-1, attached hereto and incorporated by this
reference. Additionally, PM shall administer City's consultant contracts to ensure the
services and deliverables comply with the guidelines of the City's funding partners and
regulatory agencies, including but not limited to OCTA, and the Federal Transit
Administration (FTA). PM shall review and approve invoices and deliverables submitted byconsultants, then forward to City staff for payment. PM shall meet with the Executive
Director of Public Works or his designee, on a regular basis to keep him informed regardingtheprogressoftheProject, issues which may arise to threaten the schedule or budget, and to
receive direction regarding City's concerns, interests and vision regarding the Project.
Project Manager shall represent the City at meetings with OCTA, FTA and other regulatoryagencies; develop written correspondence including memos, letters, staff reports, meetingminutes, agendas and presentations to the City Council and OCTA Board as necessary to keeptheCity, its funding partners and regulatory agencies informed ofthe progress ofthe Project; and
provide written and oral progress reports to the Project team, including consultants and the
Executive Director and his staff.
25H-3
EXHIBIT A-I
Scope of Work
Santa Ana Transit Program Oversight
The City of Santa Ana requires professional assistance to take its Go Local Transit
Vision - Fixed Guideway Project from concept to completion. Serving as the City of
Santa Ana's Fixed Guideway Project Manager, Cindy Krebs Consulting, Inc. (PM) will
provide the following services:
a. Provide management and oversight to the city's consultant team lead by
Cordoba Corporation, to develop and deliver Santa Ana's Fixed Guideway
Project. Project management shall include monitoring the Project's progress to
ensure it is on time, within budget, in conformance with design and
environmental criteria and is efficiently and effectively implemented.
b. PM shall:
1. Develop and maintain the schedule for the Fixed Guideway project and
prepare updates at key milestones for presentation as necessary to the
Executive Director or his designees and the consulting team, City Council,OCTA and other agencies involved in a regulatory or funding function.
2. Receive and implement direction regarding the Project from the Executive
Director or his designee.
3. Review and evaluate OCTA and FTA processes to ensure the consultant
team submittals comply with statutory, regulatory and administrative
requirements. PM shall review and provide comments on documents
produced by the technical team before they are forwarded to OCTA and/or
FTA, in addition to tracking key deliverables and implementation schedules
and issues.
4. Coordinate all fixed guideway team meetings, the monthly PDT meetings,and the Pre-PE technical team meetings with the consultant team and Citystaffto:
Discuss project status
Identify issues
Develop solutions
Provide oversight and direction for the Project
Prepare meeting minutes.
5. Attend the following Orange County Transportation Authority (OCTA)meetings and prepare meeting summaries for each:
Board of Directors
Transit Committee
25H-5
Rail Technical Advisory Committee.
Meeting summaries shall include decisions approved, new issues presented,
responsible personnel and timelines for completion of tasks/deliverables.
6. As necessary, attend meetings of the Mayor and City Council to provide
information and status updates on Santa Ana's Fixed Guideway Project.
7. Receive and review for completeness and accuracy, consultant deliverables,
prior to submittal to OCTA, CalTrans, FTA and/or other regulatory or funding
agencies.
8. Review and approve consultant team invoices to ensure compliance with the
Scope of Work, schedule and budget. Send approved invoices, and all back-
up work product and deliverables to City staff, for payment and retention in
the City Project files.
25H-6