Round 1 Bowling and Amusement 12/09/2024 Paradigm Design <br />Main Place Mall Expansion Grand Rapids, MI <br />Santa Ana, California <br />Project #2309147GR <br />SUBMITTAL PROCEDURES 01 3300 - 4 <br />ed. 2023-09-22 <br />1.Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if <br />coordination with subsequent submittals is required. Architect will advise Contractor when a <br />submittal being processed must be delayed for coordination. <br />2.Intermediate Review: If intermediate submittal is necessary, process it in same manner as <br />initial submittal. <br />3.Resubmittal Review: Allow 15 days for review of each resubmittal. <br />E.Resubmittals: Make resubmittals in same form and number of copies as initial submittal. <br />1.Note date and content of previous submittal. <br />2.Note date and content of revision in label or title block, and clearly indicate extent of revision. <br />3.Resubmit submittals until they are marked with approval notation from Architect's action <br />stamp. <br />F.Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, <br />fabricators, installers, authorities having jurisdiction, and others as necessary for performance of <br />construction activities. Show distribution on transmittal forms. <br />G.Use for Construction: Retain complete copies of submittals on Project site. Use only final action <br />submittals that are marked with approval notation from Architect's action stamp. <br />1.6 SUBMITTAL REQUIREMENTS <br />A.Product Data: Collect information into a single submittal for each element of construction and type of <br />product or equipment. <br />1.If information must be specially prepared for submittal because standard published data are <br />unsuitable for use, submit as Shop Drawings, not as Product Data. <br />2.Mark each copy of each submittal to show which products and options are applicable. <br />3.Include the following information, as applicable: <br />a.Manufacturer's catalog cuts. <br />b.Manufacturer's product specifications. <br />c.Standard color charts. <br />d.Statement of compliance with specified referenced standards. <br />e.Testing by recognized testing agency. <br />f.Application of testing agency labels and seals. <br />g.Notation of coordination requirements. <br />h.Availability and delivery time information. <br />4.For equipment, include the following in addition to the above, as applicable: <br />a.Wiring diagrams that show factory-installed wiring. <br />b.Printed performance curves. <br />c.Operational range diagrams. <br />d.Clearances required to other construction, if not indicated on accompanying Shop <br />Drawings.