My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
5306 W McFadden Ave - Plan
PBA
>
Building
>
ProjectDox
>
M
>
McFadden Ave
>
5306 W McFadden Ave
>
5306 W McFadden Ave - Plan
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
2/24/2026 10:50:47 AM
Creation date
2/24/2026 10:50:27 AM
Metadata
Fields
Template:
Plan
Permit Number
101122413
101122414
Full Address
5306 W McFadden Ave
Street Number
5306
Street Direction
W
Street Name
McFadden
Street Suffix
Ave
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
447
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
Show annotations
View images
View plain text
ST. BARBARA CATHOLIC SCHOOL TASK 2 75-24272-01 <br />DIOCESE OF ORANGE SEPTEMBER 12TH, 2024 <br />SANTA ANA, CA BID & PERMIT SET <br /> <br />CONTRACT MODIFICATION PROCEDURES 012600 - 3 <br />Work within the general scope of the Contract consisting of additions, deletions or other <br />revisions, the Contract Sum and Contract Time being adjusted accordingly. <br />B. A Construction Change Directive shall be used in the absence of total agreement on the terms of <br />a Change Order. <br />C. Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with <br />the change in the Work involved. As soon as possible, but no longer than seven days of receipt, <br />the Contractor shall advise the Owner and the Architect of the Contractor’s agreement or <br />disagreement with the cost or the method, if any, provided in the Construction Change Directive <br />for determining the proposed adjustment in the Contract Sum or Contract Time. If the <br />Contractor does not timely disagree with the adjustments, the Construction Change Directive <br />will be deemed an agreed “Change Order”. The Contractor’s notice shall reasonably specify the <br />reasons for its disagreement and the amount or other terms that it proposes. Without such timely <br />written notice, the Contractor shall conclusively be deemed to have accepted the Owner’s <br />adjustment. The Contractor’s disagreement shall not relieve the Contractor its obligation to <br />comply promptly with any written notice issued by the Owner or the Architect. The adjustment <br />shall then be determined by the Owner on the basis of reasonable expenditures and savings of <br />those performing the Work attributable to the change, in strict accordance with this Paragraph <br />and other applicable provisions of the Contract Documents. <br />PART 2 - PRODUCTS (NOT USED) <br />PART 3 - EXECUTION (NOT USED) <br />END OF SECTION 012600
The URL can be used to link to this page
Your browser does not support the video tag.