ST. BARBARA CATHOLIC SCHOOL TASK 2 75-24272-01 <br />DIOCESE OF ORANGE SEPTEMBER 12TH, 2024 <br />SANTA ANA, CA BID & PERMIT SET <br /> <br />PROJECT MANAGEMENT AND COORDINATION 013100 - 5 <br />6. Allow up to 14 working days for review by owner and architect. <br />1.7 REQUEST FOR INFORMATION (RFI) <br />A. General: Immediately on discovery of the need for additional information, clarification, or <br />interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the <br />form specified. <br />1. Architect will return without response those RFIs submitted to Architect by other entities <br />controlled by Contractor. <br />2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's <br />work or work of subcontractors. <br />B. Content of the RFI: Include a detailed, legible description of item needing information or <br />interpretation and the following: <br />1. Project name. <br />2. Project number. <br />3. Date. <br />4. Name of Contractor. <br />5. Name of Architect. <br />6. RFI number, numbered sequentially. <br />7. RFI subject. <br />8. Specification Section number and title and related paragraphs, as appropriate. <br />9. Drawing number and detail references, as appropriate. <br />10. Field dimensions and conditions, as appropriate. <br />11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the <br />Contract Time or the Contract Sum, Contractor shall state impact in the RFI. <br />12. Contractor's signature. <br />13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop <br />Drawings, coordination drawings, and other information necessary to fully describe items <br />needing interpretation. <br />a. Include dimensions, thicknesses, structural grid references, and details of affected <br />materials, assemblies, and attachments on attached sketches. <br />C. RFI Forms: Software-generated form with substantially the same content as indicated above, <br />acceptable to Architect. <br />1. Attachments shall be electronic files in PDF format. <br />2. RFIs will be submitted through owner provided web-based program (eBuilder). <br />D. Architect's Action: Architect will review each RFI, determine action required, and respond. <br />Allow seven working days for Architect's response for each RFI. RFIs received by Architect <br />after 1:00 p.m. will be considered as received the following working day. <br />1. The following Contractor-generated RFIs will be returned without action: <br />a. Requests for approval of submittals.