EXHIBIT 1 E <br />2. Within a reasonable time prior to the start of any on -site work, delivery of materials, equipment, or personnel, Contractor will submit to <br />Owner the following: <br />A- A complete set of drawings Approved by Owner and subsequently by the City In which the Building Is located. <br />B- A fully executed Indemnity Agreement (To Be Provided by Owner Upon Request), <br />C- Certificate or Insurance In a form approved by Omer executed by Insurance companies acceptable to Owner. <br />D- A fully executed Notification -Rules for Contactors Cro Be Provided by Owner Upon Request). <br />E- A job schedule of the work to be accomplished, detailed by trade. <br />F- A complete list of all proposed Subcontractors and suppliers. Owner must approve all contractors and subcontractors before <br />commencement of their work. <br />0- The name and phone number (in ofuding emergency phana numbers) arpersonnal who are authorized to represent ilia Contractor. <br />3. No rovis lolls or changes or any kind maybe made 10 the Construction plans previously approved by Owner without prior written consent of <br />die Owner, Any proposed revisions or changes must be submitted to Owner in the form of a change order, for Owner's review and <br />approval prior to commencement of such changes, Revisions or changes altering the floor plan, base building systems, or building <br />operations must besubmitted, In writing, to the Owner for review and approval prior to commencement orwork. <br />4, All of Contractor's work must be scheduled so that it in no way conflicts with, Interferes with, or impedes Ole quiet and peaceful enjoyment <br />of other tenants or occupants of the project, or with the progress or Ovmer's work a• operations. Any work that is in confll et will be <br />rescheduled by the Contractor to such time as approved by Owner. Additionally, Owner shall have no liability for any costs or expenses <br />Incurred by Contractor (or Tenant) in connection with such rescheduling, <br />5. Contne or and subcontractors shall employ persons and mains for the orderly progress of the work without Interruption on account of <br />strikes, work stoppages or similar causes of delay, Additionally, Owner shall have no liability for any costs or expenses incurred by <br />Contractor (or Ten ant) in connection with such delays. <br />6. Materials slid foul storage will be limited to the areas for which access has been granted. <br />7. Clean-up and rubbish removed shall he provided by the Contractor at Contractor's expense. Contractor must, on u daily basis, remove all <br />rubbish, surplus and waste material resulting from the performance of his work. At the request of Owner, Contractor shall relocutc any <br />materials causing fill obstruction as directed by Owncr, Contractor will not be allowed to place a dumpster on site on a continuous basis <br />during construction, <br />Important note: The placement and location ofrubbish dumpsters and bins most be approved In advance by Owner. <br />8. In general, Owner will Interface with Contractor to the extent necessary for work to be completed within Ate guidelines of project <br />specilica0culs and for the enforcement orbuilding Arles and regulations. <br />91 Contractor will make m•rongemeuts For unloading, trash removal and hoisting after normal working hours due to the local city noise <br />ordinance. (No such nativity will be allowed between die hours of 10:00 p,m, to 7:00 am.) Al no time will the Contractor be given <br />exclusive reserved use of the freight elevator unless applied for by Contractor and approved by Owner. Contactor may be afforded access <br />to lending dock space And hoisting facilities for limited use at such time during normal working hours as is prearranged with Owner, or At <br />other times, with the cotlsent of Owner and upon payment of Owner's prcvalling fee for after-hours use and access. <br />10. Contrnemrwill be afforded unloading areas as prearranged with Owner, All materiels unloaded at these areas will be moved to at area of <br />use Iniacdistely and shill not be stored or used in a way which adversely impacts use of the Building, <br />III Contactor (rind T'enanp wfll be responsible for the security orits own materials, equipment and work, and ilia[ of his subcontractors, <br />Contractor will also be responsible for damage enused by Contractor or its subcontractors to die Project, Building And/or tenant areas, <br />including. but not limited to the loading dock and indoor and coiner public areas, Freight elevators, etc. Any such clareages will he <br />promptly repaired to the Owner's satisfaction lit sole cost of Coramccor. <br />12, Contractor will comity with all Applicable codes, laws And regulations porlahling to the work of Contractor, Iruled ing all sorely and health <br />regulations. The Contractor shall supply ilia Owner with a Master List or all Flevarcloos Materials And Iheir Material Salty Data Sheals <br />(MSDS) upon delivery to the,)ub situ. A discussion will than onsue pertuinfng to the safe storage, handling and use fir these matee•inls, As <br />+WWII us the Contractor's emergency preparedness plan 1'ur handling the containment And clean-up orpotential I Inzardous Mlaterfal spills. <br />13. Contactor will nut engage III oily labor practice that any delay or otherwise Impact the week of Owner or Any alien wnlrnetnr. <br />14. No hose building sysienss will be turned oil' or disengaged by C'unu'nctur or any subcontractor without prior written approval And <br />suilml iel by a represenmtive nfOvsnio• or Its Agent. Said systems include but are not Unified to sprinklers, electrical circuits, Air -handling <br />emits, sneuke heads and weer supply. Building electrical power shut -downs Are allowed, with ilia prior wwh[en consent el'O+vier, on <br />Salunlays between 10:00 P.m. and 3:00 a.m. only, A request for approval shall be mode to the Pmperly Manager a( Loral ten I It) tiny$ in <br />advmue. <br />401 IV Ch*Ceruer Ur— OIJ• rn/!-Saerunur Lear" -4- inhibit 1) <br />80A-456 <br />