2. Within a reasonable time prior to the start of any on -site work, delivery or materials, equipment, or personnel, Contractor will submit to <br />Owner the following: <br />A- A complete set of drawings approved by Owner and subsequently by the City in which the Building is located. <br />B- A fully executed Indemnity Agreement (To Be Provided by Owner Upon Request), <br />G Certificate of Insurance in a form approved by Owner executed by insurance companies acceptable to Owner. <br />D- A filly executed Notification -Rules for Contractors (To Be Provided by Owner Upon Request), <br />F,- A job schedule of the work to be accomplished, detailed by trade. <br />F- A complete list of all proposed Subcontractors and suppliers. Owner must approve all contractors and subcontractors before <br />commencement of their work. <br />O- The name and phone number (including emergency phone numbers) of personnel who are authorized to represent the Contractor. <br />3. No revisions or changes of any kind may be made to the construction plans previously approved by Owner without prior written consent of <br />the Owner. Any proposed revisions or changes must be submitted to Owner in the form of a change order, for Owner's review and <br />approval prior to commencement of such changes. Revisions or changes altering the Floor plan, base building systems, or building <br />operations must be submitted, in writing, to the Owner for review and approval prior to commencement of work. <br />4. All of Contractor's work must be scheduled so that it in no way conflicts with, interferes with, or impedes the quiet and peaceful enjoyment <br />of other tenants or occupants of the Project, or with the progress of Owner's work or operations. Any work that is in conflict will be <br />rescheduled by the Contractor to such time as approved by Owner. Additionally, Owner shall have no liability for may costs or expenses <br />incurred by Contractor (or Tenant) in connection with such rescheduling, <br />6. Contactor and subcontractors shall employ persons and means for the orderly progress of the work without intermption on account of <br />strikes, work stoppages or similar causes of delay. Additionally, Owner shall have no liability for any costs or expenses incurred by <br />Contractor (or Tenant) in connection will) such delays. <br />6. Materials and tool storage will be limited to the areas for which access has been granted. <br />7. Clean-up and rubbish removal shall be provided by the Contractor at Contractor's expense. Contractor must, on a daily basis, remove all <br />rubbish, surplus and waste material resulting fl'om the performance of his work. At the request of Owner, Contractor shall relocate any <br />materials causing an obstruction as directed by Owner. Contractor will not be allowed to place a dumpster on site on a continuous basis <br />during construction. <br />Important note: The placement and location of rubbish dumpsters and bins must be approved in advance by Owner. <br />8. In general, Owner will interface with Contractor to the extent necessary for work to be completed within time g ldeones of project <br />specifications and for the enforcement of building rules and regulations. <br />9. Conutnuor will make arrangements fa' unloading, trash removal and hoisting after normal working hours due to die local city noise <br />ordinance. (No such activity will be allowed between the hours of 10:00 p.m. to 7:00 a.m.) Al no time will the Contractor be given <br />exclusive reserved use of the freight elevator unless applied for by Contractor and approved by Owner. Contractor may be afforded access <br />to loading clock space and hoisting facilities for limited use at such time during normal working hours as is prearranged with Owner, or at <br />other times, with the consent of'Owaer and upon payment of Owner's prevailing fee for after-hours use and access. <br />to, Contractor will be afforded unloading areas as prearranged with Owner, All materials unloaded at these areas will be moved to an area of <br />use immediately and shall not be allied or used in a way which adversely impacts use orthe Building, <br />It Contractor (and Tenant) will be responsible fa' the security of its own materials, equipment and work, and that of his subcontractors. <br />Contractor will also be responsible for damage caused by Contractor or its subcontractors to the Project, Building and/or tenant areas, <br />including. but not limited to the loading dock and indoor and outdoor public areas, freight elevators, etc. Any such damages will be <br />promptly repaired to the Owner's satisfaction at sole cost of Contractor. <br />12, Comrnetor will comply with all applicable codes, laws and regulations pertaining to the work of Contactor, including all safety and health <br />regulations. The Contractor sholl supply the Owner with a Muslcr List of all Hazardous Materials and their Matedul Sale y Doti Sheets <br />(MSDS) upon delivery to the,job site. A discussion will then ensue pertaining to the safe storage, handling and use of these materials, as <br />well us time Contractor's emergency preparedness plan lbr handling the containment and clean-up of potential Hi7arLIaus Hlntarial spills. <br />13Contractor will not engage in any labor practice that may delay or otherwise impact the workofOwner crony otherecmnaclor. <br />14. No base building sysrenms will be tamed ol'I' or disengaged by Contractor or any subcontractor without prior written approval and <br />supervision by u representative of Owner or its agent. Said systems include but are not limited to sprinklers, electrical circuits, air -handling <br />units, smoke heads and water supply. Building electrical power shut -downs are allowed, with the prior written consent ol'Owner, on <br />Sarurdn-vs between 10:00 p.nm. and J:00 a.m. only. A request for approval shall be made to the Property Manager at least ten (10) Joys; in <br />advance. <br />801 WChic Celli, Ur -Croy nj.Swdu.Im Leave .4- Exhiluq 1) <br />