15. Doors to all work areas, including stairwells and mechanical and electrical closets, will remain closed at all time. Propping doors open is
<br />expressly prohibited,
<br />16. All Contractor and subcontractor personnel, materials, tools and equipment are to enter and exit the Building through the service elevator
<br />only. Owner may at any time initiate n check f Vcheck out system, or a badge system, for all people and material in the Building and the
<br />Contractor will agree to cooperate with any such system.
<br />17, Before ordering material ordoing work which is dependent upon proper size or installation, the Contractor shall field verify all dimensions
<br />for accessibility with building conditions, and shall be responsible for same.
<br />19. Contractor shall not permitted any identifying signage or advertising within the Project or Building.
<br />19. During construction, Contractor shall maintain supervisory personnel on the site at all times. Such personnel shall be fully authorized to
<br />coordinate, respond for and authorize Contractor's work as necessary so as to enable all work to proceed in a timely and well -ordered
<br />fashion. Should Contractor perform work which would cause or require Owner to provide personnel to be present or otherwise perform
<br />any work, Contractor shall reimburse Owner for the expense of such personnel.
<br />20, Contractor shall be responsible for the protection of its work and die area adjacent to his work.
<br />21. Contractor will ensure that all stairwells, mechanical rooms, electrical and telephone closets, etc, accessed by Contractor or subcontractors
<br />in conjunction with Contractor's work, will be cleaned and Flee of debris nightly.
<br />22, Public areas adjacent to premises where Contractor's work is being performed shall remain free of debris and materials at all times.
<br />23. Contractor shall be responsible for all his actions on site as well as those of its subcontractors, aid shall indemnify, defend and hold
<br />harmless the Owner acid the other Owner Parties from and against any and all claims, losses, or damages, threatened or incurred, arising
<br />From the actions or omissions of Contractor or its subcontractors.
<br />24, If keys are required by contractors, they must be checked out from the Property Management Office. No key will be distributed If proper
<br />identification is not provided.
<br />25, No cutting or patching of Owner's premises or installations, or those of any Building occupant, shall be permitted without the prior written
<br />consent of Owner. Request for permission to do cutting shall include explicit details and description of work and shall not under any
<br />circumstances diminish die sh neutral integrity of die Building or die integrity of any of components or systems. The work is to be done
<br />only with the explicit written permission of die Property Manager, and only on an "Off-liours" basis, Stich work is to be done only under
<br />the direct supervision of a competent member of the Contractor staff. Any such area is to be promptly repaired and returned to a fully
<br />functioning, complete, and clean condition.
<br />26. All work is to be done to a minimum standard of quality as required by the Base Building Drawings and Specifications (to be made
<br />available by Owner upon request). It is the responsibility of die Contractor to be fully knowledgeable of the Base Building Drawings and
<br />Specifications.
<br />27, All Life Safely Systems for the Building are to be maintained, end all of the Tenant's work is to be properly interfaced with and connected
<br />to the Base Building systems as required by Laws, or by Building operation. All work is to be done in such a way as to protect all Base
<br />Building operations and warranties. Any required disconnection of life safety devices should be "foreseen" and the Property Management
<br />Office must be notified at least 24 hours In advance. Costs for false Fire darns due to contractors` or subcontractors' negligence will be
<br />billed to and paid by the Contractor. All life -safety systems testing must be performed on no "after-hours" basis and coordinated with the
<br />Building Manager.
<br />28, When work is performed by Contractor or subcontractor, charges will apply for additional services performed by Owner which may
<br />include, but are not necessarily limited to the following:
<br />A - overtime or after-hours elevator usage
<br />B - utility usage f'or construction activities beyond standard power and water used in connection with general oFtce uses
<br />C - extra and continuous cleanup of elevalors and public spaces as required due to construction activity; Contractor to provide die
<br />usual protection of existing improvements, and exercise care and good sense
<br />D - extended or alter -hours use of the loading dock
<br />29. In addition to cleaning requirements described above, Contractor shall, in preparation Ibr substantial completion or occupancy of Lhe
<br />project by Teruel, perform final cleaning of Contractor's Work.
<br />3t. When Conti actor takes over an men from the Owner, before commencing work Contractor shall Ascertain Lha( the area is in a safe and
<br />stmitary condition, and mninmin the men as necessary (at its sole cost nod expense) in it safe and sanitary condition and to a standard
<br />meeting all applicable laws and regolatiuns.
<br />31. Owner requires job progress meetings, The Contractor will attend with a representative authorized to speak and act an the Contractor's
<br />behalf. Additionally, the Contractor shall notify the Dwacr ofscheduled jot) progress meetings.