Laserfiche WebLink
TUSTIN AVENUE/ROSE DRIVE <br />RTSSP GRANT APPLICATION OCTOBER 2019 <br />SECTION 6: PROJECT SCHEDULE BY TASK <br />Project start date: August 1, 2020 <br />Project end date: July 31, 2023 <br />Primary Implementation <br />Task <br />Starting Date <br />Ending Date <br />Task 1: Project Administration <br />August 1, 2020 <br />June 30, 2023 <br />Task 2: Data Collection <br />August 1, 2020 <br />September 30, 2020 <br />Task 3: Field Review and Plans Specifications, and Estimates <br />August 1, 2020 <br />October 31, 2020 <br />Task 4: Corridor "Before" Study <br />November 1, 2020 <br />November 7, 2020 <br />Task 5: Signal Timing Optimization and Implementation <br />August 1, 2020 <br />May 1, 2021 <br />Task 6: Corridor "After" Study <br />May 5, 2021 <br />May 12, 2021 <br />Task 7: Synchronization System Construction <br />December 1,2020 <br />May 31, 2021 <br />Task 8: Primary Implementation Project Report <br />June 15, 2021 <br />June 15, 2021 <br />Task 9: Ongoing Operations & Maintenance <br />August 1, 2021 <br />June 30, 2023 <br />Ongoing Monitoring and Maintenance <br />Task <br />Starting Date <br />Ending Date <br />a. Monitoring and improving optimized signal timing <br />August 1, 2021 <br />June 30, 2023 <br />b. Communications and detection support <br />August 1, 2021 <br />June 30, 2023 <br />c. OMM Memo <br />August 1, 2021 <br />June 30, 2023 <br />Revl:4n12021 <br />Page 16 of 23 <br />