21. Installation of seismic gas shutoff valve on gas service per PCO CC-64. <br /> AGREED COST: $3,409.00 <br /> 22. Security services on original scope and overages community center construction per PCO CC- <br /> 65. <br /> AGREED COST: $107,308.41 <br /> 23. Cost increase associated project delays due to changes from bid set to approved Planning & <br /> Building set per PCO CC-66. <br /> AGREED COST: $259,000.00 <br /> 24. Installation of sheet metal closure piece at metal deck in 310 Building roof per PCO CC-67. <br /> AGREED COST: $20,000 <br /> 25. Credit issued for removal of mural from project scope per PCO CC-68. <br /> AGREED COST: ($50,000.00) <br /> TOTAL AGREED COST:$637,112.41 <br /> Page 3 of 4 <br />