Willard Neighborhood Water and Sewer Main Improvements
<br />December 20, 2022
<br />Page 2
<br />and general service quality will improve significantly. In addition, the potential for
<br />disruption due to water main breaks will be substantially reduced.
<br />Public Outreach and Contractor Participation
<br />To provide an opportunity for local vendors to submit bids, a Notice Inviting Bids was
<br />advertised in the Orange County Register newspaper on September 27 and October 4,
<br />2022. The project was also advertised on PlanetBids, and bids were received
<br />electronically via PlanetBids on October 18, 2022.
<br />The City notified a total of 624 regional vendors via PlanetBids, 18 of which are Santa
<br />Ana based. Fifty-five vendors requested bidding documents. A total of eleven bids were
<br />received. However, no bids were received from Santa Ana contractors.
<br />Bid Results Summ
<br />RANK
<br />BIDDER'S NAME
<br />LOCATION
<br />BASE BID
<br />1
<br />Big Ben, Inc.
<br />Irvine
<br />$3,163,400.00
<br />2
<br />Dominguez General Engineering, Inc.
<br />Pomona
<br />$3,619,000,00
<br />3
<br />TE Roberts, Inc.
<br />Orange
<br />$3,776,850.00
<br />4
<br />Lucas Builders, Inc.
<br />La Habra
<br />$4,156,900.00
<br />5
<br />Griffith Company.
<br />Brea
<br />$4,172,713.00
<br />6
<br />SRK Engineering.
<br />Escondido
<br />$4,241,300.00
<br />7
<br />Aid Builders, Inc.
<br />Los Alamitos
<br />$4,467,840.00
<br />8
<br />Stephen Doreck Equipment Rentals,
<br />Inc.
<br />Pico Rivera
<br />$4,817,060.00
<br />9
<br />ARB, Inc.
<br />Lake Forest
<br />$5,009,575.00
<br />10
<br />Excel Paving Co.
<br />Long Beach
<br />$5,189,950.00
<br />11
<br />Mike Bubalo Construction Co., Inc.
<br />Gardena
<br />$5,496,250.00
<br />Of the eleven bids received, all were deemed responsive. Big Ben, Inc., submitted the
<br />lowest responsive base bid, in the amount of $3,163,400 (Exhibit 2). As specified in the
<br />bid documents, the lowest bid shall be determined on the basis of the Base Bid. Based
<br />on the bid analysis and a contractor's reference check, staff recommends awarding the
<br />construction contract to Big Ben, Inc., in the amount of the base bid totaling $3,163,400
<br />(Exhibit 3). Big Ben, Inc., has performed the following work in the City of Santa Ana
<br />within the past 5 years: Baker -Glenwood Sewer Main Upgrade (Project No. 21-6446),
<br />and Lincoln Avenue Water & Sewer Main Improvements (Project Nos. 22-6468 & 22-
<br />6620).
<br />
|