SA-2 Pressure Control Station Relocation <br />and Transmission Main Improvements <br />RFP No. 21-127 <br />Vault Design Option <br />The City is considering placing the relocated SA-2 PRS Facility within a building or within a below <br />ground service vault. Tetra Tech has dealt with this issue on following relevant projects: <br />For MNWD's ID 1 Master Meter Relocation, Tetra Tech evaluated several potential locations and at <br />each location looked at within a building, within a wall enclosure and within a below grade vault; <br />For OCWD's Mid -Basin Injection Wells, Tetra Tech designed the four well injection facilities within <br />large below grade vault structures. <br />For IRWD's Well 78 Replacement, Tetra Tech designed the new well within a below grade vault <br />structure with multi -story apartment structures only 50 feet away from the vault (Warner Avenue <br />and Culver Drive); <br />For IRWD's Well ET-2 Replacement, Tetra Tech designed the new well within a below grade vault <br />structure adjacent to a large commercial center (Irvine Center Drive and Culver Drive); and <br />For the City's San Lorenzo Lift Station, Tetra Tech designed the new wet well and lift station facility <br />(and corresponding shoring specifications) adjacent to an existing hotel complex and residential <br />development. <br />Tetra Tech can provide the City with the 3D renderings of the Mid -Basin Injection Well Facilities if the <br />City so desires. Tetra Tech has an excellent understanding of the shoring requirements, noise <br />concerns, and construction restrictions when constructing adjacent to a residential house and across <br />the street from an existing school. <br />Electrical/Control, <br />Tetra Tech has an excellent understanding of the City's electrical and control designs as a result of our <br />previous projects: Well 32 Rehabilitation; SA-7 Relocation; SA-5 Vault Upgrade; and SA-1 Hydro - <br />Generator Replacement. In addition, Enterprise Automation, one of the City's Control System <br />Design Programmers, is now a Tetra Tech company. They will be available to provide valuable <br />assistance and input throughout the design process. <br />Permitting <br />SA-2 is a City facility and will need to have the design work coordinated with all involved agencies, <br />including the City's Building and Public Works. Tetra Tech has an excellent understanding of the City's <br />permitting requirements due to the following projects: <br />SA-7 Relocation and Well 32 Rehabilitation Projects (City's Building and Parks); <br />Mesa's Well Pipelines and Well 32 Rehab Pipeline (City's Public Works); and <br />OCWD's Mid -Basin Project (City's Building, Parks, Fire and Public Works). <br />Coordination with MWD and SCE is vital for the success of this project. Tetra Tech has been <br />coordinating with MWD for the SA-5 Vault Relocation Project. In addition, Tetra Tech has added Scott <br />Foster Engineering, Inc. to our team to assist with satisfying MWD's potential request for a transient <br />analysis of the new pressure control system. Scott Foster has performed surge analysis on over <br />15 different MWD pipelines so understands what MWD is looking for. <br />Tetra Tech has been in coordination with SCE for the SA-1 Hydro -generator. This previous dealings <br />with SCE will allow Tetra Tech to accelerate the design and obtaining approval for the SA-2 hydro - <br />generator. Tetra Tech has an excellent working relationship with SCE as can be seen by the latest <br />coordination effort with SCE at the John Garthe Pump Station Facility. <br />TETRA TECH Page 17 <br />