the freeway (about 77 feet of 12" Class 350 DIP and 102 feet of 12-inch DR 14 PVC <br />pipe); and the construction of the new 24-inch piping on the east side of the freeway <br />(about 137 feet of 24-inch CML&C steel pipe). The scope includes the construction <br />of the jacking and receiving pits (excavation, shoring, backfill and compaction), removal <br />and replacement of existing 21-inch storm drain on the east side of the freeway, valves, <br />fittings, concrete encasements for thrust restraint, concrete anchor blocks, potholing of <br />crossing utilities and points of connections, connection to existing water mains, the <br />abandonment of the 12-inch and 24-inch piping on the east side of the freeway, and <br />restoration of surface improvements. <br />Location of Project Sites <br />The work will be performed: within the City's property at the existing SA-7 Pressure <br />Reducing Station located off Ritchey Street; within the proposed City of Santa Ana <br />property being obtained from Western Exterminator Company; within the temporary <br />construction easement within Western Exterminator Company (2201 Ritchey Street) <br />property; within the limits of Ritchey Street as shown on the construction plans; and within <br />the proposed waterline easement, temporary construction easement and temporary <br />waterline construction access easement from RICOH Company (1123 Warner Avenue) <br />property. <br />Orange County Transportation Authority (OCTA) is in the process of obtaining the new <br />City of Santa Ana property and the temporary construction easement from Western <br />Exterminator Company. OCTA anticipates obtaining the new City property and the <br />adjacent temporary construction easement from Western Exterminator Company by <br />March or April 2022. <br />For bidding purposes, the Contractor shall assume the work within the new Santa Ana <br />property and adjacent temporary construction easement will not be able to be started until <br />June or July 2022 and should prepare his schedule accordingly. The Contractor shall not <br />access or be allowed to perform any work within the proposed City of Santa Ana property <br />or the temporary construction easement until OCTA has notified them in writing that the <br />City has the property and work can begin. <br />OCTA is in the process of obtaining the new City of Santa Ana waterline easement, the <br />temporary construction easement and the temporary waterline construction access <br />easement from Ricoh Company. OCTA anticipates obtaining the new City waterline <br />easement and the temporary construction easements from Ricoh Company by March 2022. <br />For bidding purposes, the Contractor shall assume the work within the Ricoh Company <br />property will not be able to be started until July 2022 and should prepare his schedule <br />accordingly. The Contractor shall not access or be allowed to perform any work within the <br />permanent waterline easement or the temporary construction easements from Ricoh <br />Company until OCTA has notified them in writing that the City has obtained the <br />easements and work can begin. <br />City of Santa Ana RFP 21-066 <br />Page Al-3 <br />