My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
Item 30 - Design Services for the Standard — McFadden Park Project
Clerk
>
Agenda Packets / Staff Reports
>
City Council (2004 - Present)
>
2021
>
08/17/2021 Regular
>
Item 30 - Design Services for the Standard — McFadden Park Project
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
4/9/2024 11:56:39 AM
Creation date
8/17/2023 4:11:59 PM
Metadata
Fields
Template:
City Clerk
Doc Type
Agenda Packet
Agency
Clerk of the Council
Item #
30
Date
8/17/2021
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
57
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
b) 60%, 90%, and 100% <br />1) The Consultant shall submit the following documents for review and approval: <br />Each milestone submittal shall include the electronic files of the following <br />documents: Plans, Standard Special Provisions (SSP), preliminary quantities <br />and estimates, pay item list, design calculations and all reports supporting the <br />design (i.e. geotechnical report, hydraulic report). <br />2) The City reviews and comments on the PS&E package within four (4) weeks <br />of receipt of the complete milestone PS&E package. <br />3) Constructability review meeting shall take place at 90% and shall include <br />Consultant and City engineering staff. Prior to the City conducting the <br />constructability review, the Consultant shall submit the QA/QC set of PS&E <br />performed by the Consultant independently. <br />4) The City may request a set of QA/QC plans and estimates at any point during <br />the design process to include methods for design and calculations. <br />5) The Consultant shall provide a final colored rendering of the project reflecting <br />all items identified within the final construction documents. <br />c) Final PS&E for Approval and Bidding <br />The Consultant shall submit all electronic files (CADD, Word document, and <br />Excel) and one set of PDF of the following documents for construction Bid <br />purpose: <br />Signed final design plans <br />Signed final specifications <br />Signed QA/QC Checklist <br />Final cost estimate and final quantity calculations <br />Final design calculations <br />3. Construction Bidding Phase: <br />Bidding procedures will be the responsibility of the City. While the PS&E construction <br />package is advertising for bids, all questions concerning the intent shall be referred to <br />the City for resolution. In the event that any item requiring interpretation in the <br />drawings or specifications is discovered during the bidding period, said items shall be <br />analyzed by the Consultant for decision by the City. <br />4. Construction Support Phase: <br />City of Santa Ana RFP 21-055 <br />Page Al-6 <br />