Schedule <br />The start of all tasks is contingent upon our authorization to proceed. <br />•CONCEPT <br />TASK 1: Preliminary Concept Planning <br />4 weeks <br />TASK 2: Final Concept Planning <br />6 weeks <br />City Review and Approval <br />2 weeks <br />-A-T 2: CONTACT DOCUMENTS <br />TASK 1: Schematic Design <br />4 weeks <br />City Review and Approval <br />2 weeks <br />TASK 2: Design Development <br />4 weeks <br />City Review and Approval <br />2 weeks <br />TASK 3: Construction Documents <br />12 weeks <br />TASK 4: Agency Approvals <br />8 weeks* <br />TASK 5: Bid & Award <br />8 weeks <br />TASK 6: Construction Administration <br />15 months <br />*Target approval date is 3.31.2024 <br />r <br />CITY OF SANTA ANA: CHEPA'S PARK MASTER PLAN AND COMMUNITY CENTER 1 18 <br />