2023, and ending upon project completion, and authorize the City Manager to
<br />execute the contract subject to non -substantive changes approved by the City
<br />Manager and the City Attorney.
<br />2. Approve the Project Cost Analysis for a total estimated construction delivery cost
<br />of $16,634,625, which includes $12,795,865 for the construction contract,
<br />$1,224,820 for contract management, $694,560 for contract administration,
<br />inspection, and testing, and a $1,919,380 project contingency for unanticipated or
<br />unforeseen work.
<br />16. Approve Agreements with Johnson -Frank & Associates, Inc., Stantec
<br />Consulting Services, Inc., and Towill, Inc. for On -Call Professional Land
<br />Surveying Services, with an Aggregate Amount Not to Exceed $2,450,000 for
<br />Three -Year Terms (RFP No. 19-090) (Non -General Fund)
<br />Department(s): Public Works Agency
<br />Recommended Action:
<br />Authorize the City Manager to execute federal Caltrans agreements with
<br />Johnson -Frank & Associates, Inc., Stantec Consulting Services, Inc., and Towill,
<br />Inc. to provide on -call land surveying services on an as -needed basis, in an
<br />aggregate amount not to exceed $950,000 for a three-year term beginning May 2,
<br />2023 and expiring May 1, 2026, with an option for two, one-year extensions,
<br />subject to non- substantive changes approved by the City Manager and City
<br />Attorney (Agreement No. 2023-071).
<br />2. Authorize the City Manager to execute non-federal agreements with
<br />Johnson -Frank & Associates, Inc., Stantec Consulting Services, Inc., and Towill,
<br />Inc. to provide On -Call Land Surveying Services on an as -needed basis, in an
<br />aggregate amount not to exceed $1,500,000 for a three-year term beginning May
<br />2, 2023 and expiring May 1, 2026, with an option for two, one-year extensions,
<br />subject to non -substantive changes approved by the City Manager and City
<br />Attorney (Agreement No. 2023-072).
<br />17. Approve an Agreement with David Evans and Associates, Inc. in an Amount
<br />Not to Exceed $410,000 for the Landscape Architectural Design Services for a
<br />New Park at 10th St. and Flower St. for a Three -Year Term (Project No. 22-1342)
<br />(Revive Santa Ana Program)
<br />Department(s): Public Works Agency
<br />Recommended Action: Authorize the City Manager to execute an agreement with
<br />David Evans and Associates, Inc. to provide design, development of contract
<br />documents, and construction support for the proposed 10th and Flower Park project
<br />in the amount of $369,455, with a contingency of $40,545 for a total amount not to
<br />exceed $410,000, for a three-year term beginning May 2, 2023 and expiring May 1,
<br />2026, with an option for two, one-year extensions, subject to non -substantive
<br />CITY COUNCIL 12 May 02, 2023