Laserfiche WebLink
ITEM 1.1 WORK STOPPAGE TO ACCOMMODATE MWD REQUIRED CHANGES <br />12/13/2023 (Wednesday) Vault Work - <br />Arrived on job site and set up traffic control <br />with a lane closure. Removed fence panels <br />around shield box. Removed steel plate off <br />top of the shield box. Pumped ground water <br />into water truck. Removed blind screw plug <br />from pipe stub. Plugged pipe stub with <br />1 <br />LS <br />9,610.38 <br />9,610.38 <br />concrete block and mortar. Removed plates <br />from trench line to remove jacks, base and <br />start backfilling trench. Re -plated trench and <br />shield box. Placed fencing around shield box. <br />Cleaned up and secured job site. Took down <br />traffic control. <br />12/14/2023 (Thursday) Vault Work - <br />Arrived on job site and set up traffic control <br />with a lane closure. Removed fencing around <br />shield box. Pumped water down to place <br />sand around pipe stub. Pulled shield boxes <br />out, backfilled with base and compacted. <br />Pulled plates around shield box and trench. <br />1 <br />LS <br />22,039.4 <br />22,039.47 <br />Backfilled trench with sand & base and <br />7 <br />compacted. Prepped trench and shield box <br />area to temp pave. Loaded up and hauled K- <br />rails, shield boxes, plates and fencing off of <br />street. Cleaned up and secured job site. <br />Took down traffic control. Demobilized <br />equipment back to yard. <br />12/15/2023 (Friday) Demobilization - <br />Arrived on job site and loaded traffic control. <br />Moved equipment and traffic control out of <br />the yard. Hauled off material from yard. <br />1 <br />LS <br />3,747.97 <br />3,747.97 <br />Covered piles of spoils with plastic and <br />sandbags. Demobilized awaiting further <br />instruction. Cleaned up and secured job site. <br />01/04/2024 (Thursday) SR-5 Vault - <br />Arrived on job site and set up traffic control <br />with multiple lane closures to access water <br />vault. Set up tripod with wrench and gas <br />monitor. Once inside of vault took multiple <br />1 <br />LS <br />3,092.19 <br />3,092.19 <br />measurements of fittings and vault. (Length, <br />width, thickness, vertical and horizontal, <br />etc.) Cleaned up and secured job site. Took <br />down traffic control. <br />