Laserfiche WebLink
Approve Additional Contingency Funds for Warner Avenue Street Improvements Project <br />May 21, 2024 <br />Page 2 <br />installing parkways, raised median landscaping, storm drains, protected bike lanes, sound <br />walls, street lights, and traffic signals. <br />Lonerock, Inc. has completed underground utilities installation and the southern portion <br />of the Warner Avenue segment. However, due to a combination of cost escalation, labor <br />and market pricing steadily rising, and executed and anticipated change orders, costs for <br />Warner Avenue Improvements will surpass the $1,155,145 contingency identified for this <br />portion of the work (Exhibit 3). Additional contingency will also be needed for future <br />potential unforeseen work as the project progresses to completion. <br />The recommended action will increase the project contingency by an additional <br />$1,700,000 thereby increasing the total estimated construction delivery cost to <br />$14,755,867 as indicated in the Revised Cost Analysis (Exhibit 4) and as summarized in <br />the table below: <br />EXPENDITUR <br />ORIGINAL <br />ADDED <br />ADDITIONAL <br />E <br />AMOUNT <br />CIP <br />FUNDING <br />NEW TOTAL <br />CATEGORY <br />23/24 <br />Construction <br />Contract Bid <br />$9,486,525 <br />$9,486,525 <br />Amount <br />Construction <br />Administration, <br />$1,614,197 <br />$1,614,197 <br />Inspection, <br />Testing <br />Contingencies <br />$1,155,145 <br />$800,000 <br />$1,700,000 <br />$3,655,145 <br />Total <br />Estimated <br />$12,255,867 <br />$2,500,000 <br />$14,755,867 <br />Construction <br />$800,000 <br />Delivery Cost <br />Staff recommends the approval of the recommended action in order to continue the <br />construction of the Warner Avenue Street Improvements Project . <br />ENVIRONMENTAL IMPACT <br />In accordance with the California Environmental Quality Act, the recommended actions <br />are exempt from further review. On September 1, 2015, City Council approved the Warner <br />Avenue Final Environmental Impact Statement (SCH No. 2012101004) <br />FISCAL IMPACT <br />As indicated in the Cost Analysis, the estimated total construction delivery cost of the <br />project (14-6802) is $14,755,867, which includes construction, contract administration, <br />