Laserfiche WebLink
Bristol Street Improvements Project - Phase 4 <br />March 4, 2025 <br />Page 6 <br />The City had been awarded an OCTA M2 grant of $7,501,206 for street improvement <br />related expenditures. The City is responsible for funding the balance of street <br />improvements plus the costs of underground utility improvements. Construction costs <br />have rapidly escalated in the past four (4) years. According to the California Department <br />of General Services, California Construction Cost Index (CCCI), the average cost of <br />construction has increased by 34.4% in the past four (4) years (since 2021), over <br />double the rate for the previous five-year period (2016-2020). Staff applied for <br />additional construction funds and, on April 10, 2023, OCTA replaced the previous award <br />amount and awarded the City a total of $11,910,061. In addition to this grant, the City <br />will fund the balance of improvements from gas tax revenues, General Fund, water <br />capital, developer impact fees, and proceeds from sale of remnant Bristol properties. <br />Project Schedule and Contract Time <br />The completion date is November 30, 2026, with an option to extend to address any <br />unforeseeable conditions such as rain, natural disasters, or other delays beyond the <br />control of the City and of the Contractor. The contract time for this project is 368 working <br />days, as specified in the bid documents. Working days are counted in accordance with <br />the City's Standard Specifications, which exclude weekends, City -observed holidays, <br />and inclement weather days that prevent work. The projected project schedule is <br />provided below. <br />Milestone <br />Estimated Date <br />Notes <br />Administrative Startup <br />March 2025 <br />Contract execution, bonds, <br />insurance, traffic control plans <br />Material Procurement <br />March 2025, concurrent <br />with construction <br />Staff review and approval of <br />material submittals <br />Contractor Mobilization <br />April 2025 <br />Start of construction activities <br />Project Completion <br />November 2026 <br />Based on 368 working days <br />Project Phasing <br />As stipulated under the contract, the Contractor will be constructing this project in the <br />following phases to minimize duplication and impacts to completed components of the <br />project: <br />1. Phase I — Soundwalls, Temporary Street Lighting, and Potholing <br />Soundwall construction will be the first item of work along with temporary street <br />lighting on the east side of Bristol Street between Warner Avenue and St. Andrew <br />Place. Contractor will perform exploratory potholing as required for utilities. <br />2. Phase II — Underaround Utilitv Construction <br />In this phase, the Contractor will construct underground electric and <br />communications ducts and structures for the undergrounding of existing pole <br />