<br />AGREEMENT 1-2354 <br />Exhibit A <br /> <br />~-' <br />..--' <br /> <br />CENTERLINE LIGHT RAIL TRANSIT PROJECT <br />SCOPE OF WORK <br /> <br />... <br /> <br />PRELIMINARY ENGINEERING <br /> <br />Background <br /> <br />The Board of Directors of the Orange County Transportation Authority (The AUTHORITY) has <br />selected the Locally Preferred Alternative (LP A) for The CenterLine Light Rail Transit Project <br />(CenterLine). The AUTHORITY requires Preliminary Engineering services (referred to herein <br />as CONSULTANT) to advance the Conceptual Engineering for The CenterLine light rail tr.ansit <br />project to approximately the 30% Preliminary Engineering level. The selected LP A is an elevàt'ed <br />and surface running light rail transit (LRT) system that serves Santa Ana, Costa Mesa, and Irvine, <br />CA, The vehicles will be low-floor, articulated, light rail vehicles consisting of 1-3 cars. Light <br />rail trains will operate in-street, within reserved rights-of-way, and on aerial .stnlcture as they <br />travel through central Orange County on the LP A, <br /> <br />In addition to providing Preliminary Engineering drawings and specifications, this phase of work <br />is to include an updated project scope, updated design criteria and standards, a project cost <br />estimate, and a schedule for completing final engineering and project construction. The work <br />does not involve performing the preparation, processing, and clearance of FEISIFEJR; this work <br />is to be addressed in a separate procurement. However, the CONSULTANT shall be responsible <br />for coordinating and providing project management oversight of the FEISIFEJR effort. <br /> <br />The CONSULTANT will use as its baseline the work accomplished to date in the Conceptual <br />Engineering phase.. Using work performed under that contract is to minimize any reanalysis of <br />issues already resolved, unless such reanalysis is specifically directed by The AUTHORITY. <br /> <br />The CONSULTANT is also encouraged to consider in all aspects of this work the economic and <br />operational benefits to The AUTHORITY that can be derived by employing the designs and <br />coordinating the materials used by other passenger rail systems in the Southern California region, ' <br />specifically the Los Angeles light rail system, the San Diego Trolley, and Metrolink. Materials' <br />that can be jointly procured, shared, and used in emergencies, if they are common, are to be <br />identified, New designs and approaches are to be considered only if they clearly improve the <br />final product. <br /> <br />In regards to public participation and public relations, the CONSULTANT and The <br />AUTHORITY will be responsible to: Integrate the technical and consensus-building aspects of <br />the project throughout the time frame by immediately agreeing on a schedule and decision making <br />process to initiate collaborative, successful project planning; and adjust technical documents as <br />the study proceeds to respond to the most important priorities of the Santa Ana, Costa Mesa, and <br />Irvine communities as feasible within the overall CenterLine program, <br /> <br />(\ <br />