<br />Rejection of Bids for El Salvador Center Renovation <br />and Park Improvements. <br />November 7, 2005 <br />Page 2 <br /> <br />package. Lastly, Great West Contractors, Inc. also submitted an <br />incomplete bid that did not include the bid schedule and the total sum of <br />the bid. In addition to being non-responsive, these bids also exceeded <br />the engineer's estimate. Based on the above, staff recommends that all <br />bids be rejected. Following Council action, staff will review the scope <br />of the project and re-advertise for bids. <br /> <br />ENVIRONMENTAL IMPACT <br /> <br />There is no environmental impact associated with this action. <br /> <br />FISCAL IMPACT <br /> <br />There is no fiscal impact associated with this action. <br /> <br />~~ <br /> <br />James G. ](oss <br />Executive Director <br />Public Works Agency <br /> <br />~7>~ <br /> <br />Pwa_f_serv\Engineering\Construction\RFCA\04-6375 reject and re-adv 2005-11-07 120 WD <br /> <br />23B-2 <br />