<br />Valley Adams Water Main Neighborhood
<br />Improvements
<br />May 21, 2007
<br />Page 2
<br />
<br />NAME OF BIDDER
<br />
<br />1. Robert G. Castongia, Inc.
<br />2. West Valley Construction
<br />3. J. A. Salazar Construction & Supply
<br />4. Fletcher Creamer & Son, Inc.
<br />5. Dominguez General Engineering
<br />6. Desigio Construction, Inc.
<br />7. Steve Buba10 Construction Co.
<br />8. Accord Engineering, Inc.
<br />9. Vasilj, Inc. DBA Ivanko
<br />10. SJ & B Group
<br />11. Cedro Construction, Inc.
<br />12. Majich Bros., Inc.
<br />13. Zondiros Corp.
<br />14. Palp, Inc. DBA Excel Paving Co.
<br />15. Mike Bubalo Construction Co" Inc.
<br />16. Mladen Buntich Construction, Inc.
<br />
<br />CITY
<br />
<br />Downey
<br />San Jose
<br />La Habra Hghts
<br />Sylmar
<br />Rosemead
<br />Arcadia
<br />Monrovia
<br />Santa Ana
<br />Irwindale
<br />Riverside
<br />Santa Paula
<br />Altadena
<br />Torrance
<br />Long Beach
<br />Baldwin Park
<br />Upland
<br />
<br />BID AMOUNT
<br />
<br />$1,244,477.00
<br />$1,371,430.00
<br />$1,516,441.50
<br />$1,635,559.00
<br />$1,636,450.00
<br />$1,648,782.00
<br />$1,679,747.00
<br />$1,733,867.00
<br />$1,795,602.00
<br />$1,816,824.00
<br />$1,848,488.00
<br />$1,861,700.00
<br />$1,879,212.38
<br />$2,005,202.00
<br />$2,240,300.00
<br />$2,496,683.00
<br />
<br />A total of 16 bids were received and all were responsive. The lowest bid
<br />was submitted by Robert G. Castongia, for $1,244,477, which is below the
<br />Engineer's estimate of $2,000,000.
<br />
<br />ENVIRONMENTAL IMPACT
<br />
<br />In accordance with the California Environmental Quality Act, the
<br />recommended action is exempt from further review. Categorical Exemption,
<br />ER No. 2007-06 has been filed.
<br />
<br />FISCAL IMPACT
<br />
<br />The funding analysis shows a total estimated construction
<br />$1,585,000 for the project (exhibit 2). Funds are available in
<br />Utility Capital Projects fund (account no. 66-579-6635).
<br />
<br />cost of
<br />the Water
<br />
<br />APPROVED AS TO FUNDS AND ACCOUNTS:
<br />
<br />~ 1l~~7 ~ C/~
<br />
<br />Executive Director
<br />Public Works Agency
<br />
<br />~~~~""r,')~ '~:-L.'
<br />Francisco Gutierrez ,
<br />Executive Director riJ 1';
<br />Finance & Mgmt. Services Agency
<br />
<br />K:\Construction\RFCA-draft\07-3204 AWARD 05-07-07 160 ND
<br />
<br />23B-2