Laserfiche WebLink
Project 06 -1723 <br />RFA Change Order No. 6 <br />June 22, 2012 <br />Page 2 <br />3. After installing Stage 2 traffic control for the construction of the southern half of the <br />bridge it was determined by Traffic Engineering that the traffic control needed some <br />adjustments to provide safer movements for the side street traffic. The costs are to <br />compensate the contractor to sandblast, restripe, and install additional delineators per <br />the revised traffic control plan. (PCO 23). <br />AGREED COST = $19,601 <br />4. While forming the MSE wall cap located at the northeast corner of the bridge it was <br />determined that the designed planters within the wall cap would not fit. The <br />concentrated amount of reinforcement within in the cap could not be moved or cut_ The <br />costs are to compensate the contractor to form and pour a new planter on top of the <br />wall cap. (PCO 24). <br />AGREED COST = $49,476 <br />5. While laying out the new sidewalk, curb and gutter and asphalt where the street joins <br />the existing mobile home park, located at the northeast corner of the bridge, it was <br />discovered that there was a bust in the elevation. In order to effectively join the new <br />street with the private property the existing curb needed to be realigned. The costs are <br />to compensate the contractor to remove and replace a section of asphalt and curb and <br />gutter at the join between the street and private property_ (PCO 25). <br />AGREED COST = $1 ,942 <br />6. During a preconstruction meeting with the City's Water Department it was determined <br />before the contractor ties the new water line into the existing a thrust block would be <br />needed around the existing valve, if one did not exist. The costs are to compensate the <br />contractor to pothole and verify that there is an existing thrust block_ (PCO 26). <br />AGREED COST = $1,156 <br />7. After making the modifications to Phase 2 traffic control plans in PCO 23, the mobile <br />home park located at the northeast corner of the bridge advised the City that traffic <br />control modification restricted its residents from entering and exiting the mobile home <br />park. This restriction was causing some motorists to make unsafe movements. It was <br />determined that the contractor's work area could be adjusted to accommodate the <br />installation of a turning pocket at the mobile home park. The costs are to compensate <br />the contractor to revise its construction area by relocating the K -rail, removing some <br />curb, patching the area with asphalt and restriping the street. (PCO 27). <br />AGREED COST = $24,157 <br />8. In order to accommodate the new planter, per PCO24, the irrigation needed to be <br />relocated out of the MSE wall cap_ The costs are to compensate the contractor to <br />relocate the irrigation line to the new planter. (PCO 29). <br />AGREED COST = $1,357 <br />