Laserfiche WebLink
Project 06 -1723 <br />Request for Approval of Change Order No. 8 <br />October 15, 2013 <br />Page 2 of 2 <br />CONTRACT COST SUMMARY <br />Amount % of Contract <br />Original Contract Total $ 6,010,329.00 <br />Previous Change Orders $ 1,591,149.00 Increase* 26.47% <br />Change Order #9 $ 12,311.00 Increase" 0.2% <br />Total Change Orders to Date $ 1,603,460.00 Increase <br />Adjusted Contract Total $ 7,601,478.00 <br />" Contingency was increased to 30% by RFCA dated January 17, 2012 <br />Contingency was increased to 35% by RFCA dated June 3, 2013 <br />SCHEDULEIMPACT <br />Increase contract time by 80 working days. <br />26.67% <br />APPROVED AS TO FUNDS AND <br />ACCOUNTS: <br />William Galvez, Interi xecutive Director Francisco Gutierrez, Execu ive ector PO <br />Public Works Agency Finance & Management Services Agency <br />