Request for Approval of Change Order No. 1 <br />September 5, 2013 <br />Project No.: 12 -6760 <br />Page 2 of 2 <br />CONTRACT COST SUMMARY <br />Original Contract Total $259,331 <br />Amount % of Contract <br />Previously Approved Change Order $ -0- 0% <br />This Change Order $1,500 Increase 0.6% <br />Total Change Order to <br />Adjusted Contract Total <br />SCHEDULEIMPACT <br />,500 Increase <br />$260,831 <br />0.6% <br />The contract time was extended 9 days to allow the contractor time to procure the <br />materials, perform the work included in this change order. The revised completion date <br />will be October 14, 2013. <br />Edwin "William" Galvez, Interim utive <br />Director Public Works Agency <br />K: \construction\projects \12- 6760 \CO #01 \MEM RFA CCO #01 <br />APPROVED AS TO FUNDS AND <br />ACCOUNTS: <br />Francisco Gutierrez, Executive Director <br />Finance & Management Services Agency <br />