Laserfiche WebLink
lei �Li)�n'It`t�! <br />February 19, 2013 <br />Page <br />8. Phase VII: Abandon existing 12 -inch and 8 -inch sewer mains and manholes. <br />9. Phase VIII. Construct grind and cap. <br />This is only an estimated schedule; the actual schedule and phasing may vary due to field conditions and <br />performance /production rates of the Contractor. Notwithstanding, the Contractor shall complete all work <br />under the contract within 140 working days from the date of the Notice to Proceed issued by the City of <br />Santa Ana. Construction on the project shall begin within one (1) month from the award of the contract. <br />Once work has begun on the project, the Contractor shall work continuously on the project until work is <br />substantially complete. <br />MWB /mn <br />P; \P00597\ 0086 \WordPro \04 \ConespondenceWo02 - 2013- 02- I9- rev.doc(300) <br />