MEMORANDUM <br />David Cavazos <br />To: City Manager Date: November 18, 2014 <br />Fred Mousavipour, Executive Director <br />From: Public Works Agency <br />Project 13-2636; Santa Ana Zoo New Ocelot Exhibit <br />Subject: Change Order No. 1 <br />CONTRACTOR : Lehman Construction, Inc. <br />P.O. Box 3569 <br />Tustin, CA 92781 <br />PROJECT DESCRIPTION: Santa Ana Zoo New Ocelot Exhibit <br />CHANGE ORDER NUMBER <br />CHANGE ORDER AMOUNT: $ 26,141.60 <br />ACCOUNTING UNIT -ACCOUNT -ACTIVITY NUMBER: 02213200-66220-13263602028 <br />JUSTIFICATION <br />EXTRA WORK AT AGREED PRICE <br />1. The plans require the contractor to connect a new 2 1/2 inch main for the new irrigation <br />system at the rear of the holding facility. However, after field investigation, the existing <br />water source was found to be under sized for the new system. Therefore, the contractor <br />was directed to connect to a 3 -inch line located 160 feet away. The cost will include the <br />additional trench work, and pipe materials. (PCO No. 1) A prior approval was grante <br />for this work on October 15, 2014. y <br />Agreed Cost = $2,336.09 <br />2. The contract documents require the contractor to excavate footings at a depth of 3#eet <br />below existing grade. During the excavation, the contractor encountered shallow a6tive <br />sewer laterals that are in conflict with the proposed footings. Therefore, the contractor <br />was directed to increase the footing depth and insert a sleeve around the sewer laterals <br />at these affected locations. This cost will include additional excavation, reinforcement <br />steel and sleeves. (PCO No. 2) <br />Agreed Cost = $1,908.81 <br />