My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
23A - PROJ - WATER MAIN IMPROVEMENTS
Clerk
>
Agenda Packets / Staff Reports
>
City Council (2004 - Present)
>
2014
>
12/02/2014
>
23A - PROJ - WATER MAIN IMPROVEMENTS
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
11/26/2014 3:00:25 PM
Creation date
11/26/2014 2:51:39 PM
Metadata
Fields
Template:
City Clerk
Doc Type
Agenda Packet
Agency
Public Works
Item #
23A
Date
12/2/2014
Destruction Year
2019
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
134
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
CITY OF SANTA ANA <br />SPECIFICATIONS <br />SECTION 6 — PROSECUTION, PROGRESS AND ACCEPTANCE OF THE WORK <br />6 -3 SUSPENSION OF THE WORK <br />Add the following to this subsection: <br />Should suspension of work be ordered by reason of the failure of the contractor to carry out <br />orders or to perform any provisions of the contract; or by reason of weather conditions being <br />unsuitable for performing any item or items of work; the contractor, at its expense, shall do all <br />the work necessary to provide a safe, smooth, and unobstructed passageway through <br />construction for use by public traffic during the period of such suspension. In the event that <br />the contractor fails to perform the work above specified, the City will perform such work and <br />the cost thereof will be deducted from payment due or to become due to the contractor. <br />If the Engineer orders a suspension of all of the work or a portion of the work which is the <br />current controlling operation or operations due to unsuitable weather or to such other <br />conditions as are considered unfavorable to the suitable prosecution of the work, the days on <br />which the suspension is in effect shall not be considered working days. <br />If a portion of work at the time of such suspension is not a current controlling operation or <br />operations, but subsequently does become the current controlling operation or operations, the <br />determination of working days will be made on the basis of the then current controlling <br />operation or operations. <br />If a suspension of work is ordered by the Engineer, due to the failure on the part of the <br />contractor to carry out orders given or to perform any provision of the contract, the days on <br />which the suspension order is in effect shall be considered working days if such days are <br />working days as defined. <br />6 -7 TIME OF COMPLETION <br />Add the following to this subsection: <br />Where a single shift is worked, eight (8) consecutive hours shall constitute a day's work at <br />straight time for all workers. Forty (40) hours between Monday and Friday shall constitute a <br />week's work at straight time. Holidays as herein referred to shall be deemed to be: <br />LJ New Year's Day <br />LJ Martin Luther King Day <br />LJ President's Day <br />❑ Memorial Day <br />LJ Independence Day <br />❑ Labor Day <br />LJ Columbus Day <br />LJ Veterans Day <br />❑ Thanksgiving Day <br />& day after <br />❑ Christmas <br />S -6a <br />23A -69 <br />