Laserfiche WebLink
CITY OF SANTA ANA <br />SPECIFICATIONS <br />6 -9 LIQUIDATED DAMAGES <br />The provisions of this subsection apply except as herein modified: <br />It is agreed by the parties that if the improvements are not completed by the time prescribed to <br />complete the work, City and Contractor agree that Contractor will pay to City, not as a penalty, <br />but as predetermined liquidated damages, the sum specified in the Bid Proposal for each and <br />every working day's delay beyond the time prescribed to complete the work. <br />Similarly, it is further agreed that in if signal operations, road striping, and signing are not <br />coordinated or traffic lanes are not kept open for public use, on the days, at the times, and in <br />the manner specified in the Contract Documents and the City approved traffic control plans, <br />City and Contractor agree that Contractor will pay to City, not as a penalty, but as <br />predetermined damages, the sum specified in the Technical Provision. This predetermined <br />damage may also apply to other work stoppage or inconvenience caused by the contractor. <br />(a) Contractor fails to keep open any traffic lane for public use as required by these Special <br />Provisions and the City approved traffic control plans; <br />(b) Contractor fails to temporary stripe the roadway prior to opening up the roadway for <br />normal vehicular travel immediately following resurfacing; <br />(c) Contractor fails to permanently re- stripe the roadway and remove any conflicting <br />striping or delineation within seven (7) calendar days following resurfacing of that <br />section of roadway; <br />(d) Contractor fails to remove signs which conflict with new striping or fails to install signs <br />required by the Contract Documents which are necessary for safe traffic movement; <br />and /or <br />(e) Contractor fails to turn on or coordinate modification to existing signal operations as <br />required by these Special Provisions and the City approved traffic control plans. <br />Contractor agrees to pay such liquidated damages, and in case the same are not paid, <br />Contractor agrees that the Agency may deduct the amount thereof from any money due or that <br />may become due the Contractor under the contract. <br />It is further agreed that in case the work called for under the contract is not finished and <br />completed in all parts and requirements within the time specified, the Agency shall have the <br />right to extend the time for completion or not, as may seem best to serve the interest of the <br />City; and if it decides to extend the time limit for the completion of the contract, it shall further <br />have the right to charge to the Contract, his heirs, assigns or sureties; and to deduct from the <br />final payment for the work, all or any part, as it may deem proper, of the actual cost of <br />engineering, inspection, superintendence, and other overhead expenses which are directly <br />chargeable to the contract, and which accrue during the period of such extension. <br />S -6b <br />23A -70 <br />