Mr. Rudolfo Rosas <br />August 25, 2014 <br />Page 2 <br />1. Building location: minor adjustment to building location to provide adequate traffic control <br />during construction. <br />in. Code update - structural: update the structural plans and specifications for 2013 CBC. <br />n. Site modifications: confirm fire truck access, addition of gates, and minor modifications. <br />o. Electrical modifications: perform electrical coordination studies — load flow; short circuit <br />study; coordination study; and are flash study. <br />p. Control strategy coordination: coordinate work with Enterprise Automation, including <br />attendance at meetings and workshops. <br />q. Generator: confirm sizing of generator for full -start capacity. <br />r. Dual force main: prepare exhibits for a dual force main plan, profile and details. <br />s. Traffic control concepts: review traffic control concepts with the EBR documentation. <br />t. OCSD coordination: update the requirements for connecting to the OCSD trunk sewer and <br />obtain the necessary approval from OCSD. <br />Task 2: Update Plans <br />Tetra Tech will update the construction plans based on the revised design criteria agreed upon with the <br />City. The following is a summary of the plan sheets that will be changed and whether the change is <br />minor, major or basically new. <br />• General Sheets: Update G-1, G-2 and G-3 (minor). <br />• C-1 (Demolition Plan) — add notes on access (minor) <br />• C-2 and C-3 (10" FM & 15' S Plan & Profile) — add driveways, traffic control concepts and <br />access notes (minor). <br />• C-4 (Bristol 15' S) — add driveways, traffic control concepts and access (minor). <br />• C-5 (Site Demo Plan) — add temporary const. easement requirements and restrictions (minor). <br />• C-6 (Site Plan) — modify as required to meet fire access requirements, moving of building, and <br />gates (more than minor but not major). <br />• C-7 (Site Piping Plan) — relocate RPPD for interior piping (minor). <br />• M-1 (Control Room) — add window between MCC and stairwary, duct coating, wet well roof <br />changes (minor). <br />• M-2, M-3 & M-4 (Dry Well) — modify clearances to pick up about one foot, modifications to <br />pump, grinder, meter, add platform, stairway modifications, valves, check valv, etc. (major). <br />• M-5 — Odor control plan, section and details (new) <br />• D-1 (Connection Details) — add sequencing and traffic conceptlaccess notes (minor). <br />• D-2 (Trench Details) — modify per E1R (minor). <br />• D-3 (Mist. Details) — modify Detail 2 (radar), Detail 3 (wet well level float), Detail 6 (sump) <br />and Detail 7 (dry well washdown) (major). <br />• D-4 (Mist Details) — Detail 2 (drain valve) (minor). <br />• S-1, and S-2 — update to 2013 CBC (minor). <br />• S-3 (Foundation Plan) — modify stairway, epoxy coating of floor and add platform (major). <br />