<br />City of Glendale, Department of Water and Power — Owner 
<br />141 N. Glendale Avenue, Level 4, Glendale, CA 
<br />Raja Takidin 818 548-3906 (RTakidin@ci.glendale.ca.us) 
<br />Diederich Reservoir Back -Up Pipeline Project 
<br />Furnish and install 3,0501f 30" CML&C with all appurtenances and connect to 
<br />Deiderich Reservoir 
<br />Original $4,319,400/Final $4,933,870. Change orders directed by Owner 
<br />Complete 6/22/12 — 487 calendar days 
<br />South Coast Water District — Owner/Engineer 
<br />31592 West Street, Laguna Beach, CA 92651 
<br />Marissa Potter 949 248-2099 (mpotter@scwd.org) 
<br />Camino Capistrano at Via Canon Water Main Replacement and JTM Reach 7 
<br />Via Canon Relocation 
<br />Furnish and install 2,0651f 30"CML&C water main, 2801f 10" PVC C900 water 
<br />main w/tie ins, valves and appurtenance 
<br />$1,057,557 
<br />Completed 2/11 - 110 work days 
<br />Irvine Ranch Water District — Owner/Engineer 
<br />15600 Sand Canyon Rd. Irvine, CA 92618 
<br />Kelly Lew 949 453-5549 (lew@irwd.com) 
<br />Bake Parkway Recycled Water Pipeline, Los Alisos Water Reclamation Plant 
<br />Influent Sewer Improvement, Irvine Desalter Project Brine Line from Bake 
<br />Parkway to Los Alisos Water Reclamation Plant 
<br />Furnish and install 5,0331f 12" C900 PVC, 5,0451f 24" CML&C, 7321f 12" steel 
<br />water, 3311f 27" VCP sewer, 2751f 36" VCP sewer with all appurtenances and two 
<br />Cal Trans bridge crossings 
<br />Original $5,796,400/Final $7,589,608 Change orders directed by Owner 
<br />Completed 2/08 — 627 work days additional 
<br />City of Los Angeles, Wastewater Conveyance Construction Division 
<br />1149 s. Broadway, Suite 620, Los Angeles, CA 90015 
<br />Jon Haskett 213 485-5864 (jon.haskett .lacity.org 
<br />North Outfall Sewer at the LA River 
<br />Phase 1 $10,099,242, complete 5/08 334 days 
<br />Phase 11 $4,248,162, complete 2/09, 236 days 
<br />Repair and replace 48" concrete lined NOS adjacent to and under L.A. River, 
<br />including construction of largest and longest sewage bypass systems in 
<br />California: 3, 000+feet 39,000GPM. Construct two 38" access shafts to insert 4401f 
<br />42" Hobas fiberglass liner and 291f 54" semi -elliptical Hobas liner into existing 
<br />NOS, 12,OOIf 24" HDPE Restore river bank to Army Corps of Engineers standard. 