SCOPE OF SERVICES <br />from the beginning of one task until the next task will need to be issued. For example, if a new task has <br />80,000 LF and it is divided by 3,200 LF per day, it would take roughly 25 working days to complete. <br />Therefore, the City could anticipate the need for the next assigned task in approximately 5 weeks. <br />The scheduling of operators and equipment for a task would be determined by the task size, pipe size <br />and if the City is requiring the task be completed in a specific time -frame. With advance notice, we <br />have the capability to complete any task the City may present. <br />Houston & Harris has personnel for emergency work 24(7 on-call for cleaning and video. The on-call <br />operators and equipment can also be utilized for storm drain and overflow situations where the City <br />may need additional manpower and equipment. <br />Current Workload and Accommodation for This Contract <br />Presently Houston & Harris has fourteen (14) on-going contracts. Four (4) of these will reach <br />completion soon. Of the remaining contracts four (4) are clean and video, three (3) are cleaning <br />contracts and three (3) are video inspection contracts. In addition to the on-going contracts we also <br />have short-term contracts and daily work throughout the year. This work is scheduled based on the <br />manpower and equipment required, the need of the client and our contract schedule. On-going <br />contracts always take priority. Regarding accommodating this project, the equipment & personnel <br />currently assigned to the existing contract would remain the same as well as the prioritized scheduling. <br />City of Santa Ana <br />Closed Circuit Television (CCN) Inspection of Sanitary Sewers__. <br />RFP NO.: 17-055 <br />f 21031. Barton Road <br />M<s Grand Terrace, CA 02313 <br />90 (� 0�gg•422.0841 F <br />