STEP 1 <br />• HVAC CONTRACTOR, SETS RTU'S. SHOPPING CENTER BMS CONTRACTOR INSTALLS ALL REQUIRED SENSORS <br />(MECHANICAL CONTRACTOR AND BMS CONTRACTOR TO COORDINATE INSTALLATION). <br />• CONTRACTOR COMPLETES ENTIRE HVAC INSTALLATION INCLUDING ALL GRILLES, ELECTRICAL POWER . <br />• HVAC CONTRACTOR SHALL PROVIDE, CONNECT AND TEST OPERATION OF TEMPORARY THERMOSTATS USING THE <br />NEW 18/8 THERMOSTAT CABLE AS SHOWN ON SHEET M.1.0 ON THE FIELD INSTALLED SENSOR DETAIL. <br />STEP 2 <br />• LENNOX PERFORMS COMMISSIONING OF RTU'S AND ESTABLISHES PRODIGY SETTINGS SO PROGRAMMED VALUES IN <br />RTU CONTROLLER ARE DONE IN ACCORDANCE WITH THE INFORMATION IN THE DRAWINGS AND SPECIFICATIONS. <br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH ESTABLISHES PROPER SETTINGS FOR SUPPLY FAN HIGH AND <br />LOW SPEED OPERATION. (AS INDICATED IN HVAC UNIT SCHEDULE) <br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH CALIBRATES THE PHYSICAL POSITION OF THE OA DAMPER <br />WITH THE LENNOX DAMPER POSITION STATUS POINT. (VALIDATING THAT THE ECONOMIZER IS CLOSING PROPERLY, <br />PROPERLY STARTED UP AND THE DAMPER POSITIONS MATCH THE DAMPER POSITION FEEDBACK ON THE PRODIGY <br />BOARD) (FULLY CLOSED DAMPER INDICATES 0% OPEN FEEDBACK AT PRODIGY/FULLY OPEN DAMPER INDICATES <br />100% OPEN FEEDBACK AT PRODIGY). <br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH ESTABLISHES THE FOLLOWING PARAMETERS FOR DEMAND <br />CONTROLLED VENTILATION: <br />1. DEMAND CONTROL VENT -DAMPER START OPEN = 1050 PPM <br />2. DEMAND CONTROL VENT -DAMPER FULL OPEN = 1150 PPM <br />• LENNOX PROVIDES COMMISSIONING REPORT TO FSG, VERIZON RDC AND EXCEL & INFORM (AS LEED CXP).REPORT <br />INCLUDES ALL FAN SETTING INFORMATION SO ALL PARTIES ARE INFORMED OF HIGH AND LOW SPEED AIRFLOW / <br />OUTPUT %. <br />STEP 3 <br />• TEST & BALANCE OCCURS. <br />• MERV 13 FILTERS INSTALLED AND DATED PRIOR TO TEST AND BALANCE. <br />• TEST AND BALANCE CONTRACTOR ADJUSTS SHEAVES, PULLEYS, BELTS, ETC. ON BELT DRIVE FANS WITH VFDS TO <br />ACHIEVE SCHEDULED SUPPLY AIRFLOW AT HIGH FAN SPEED PER HVAC UNIT SCHEDULE. <br />• TEST AND BALANCE CONTRACTOR SETS PRODIGY OUTPUT TO ECM DIRECT DRIVE FAN MOTORS, TO ACHIEVE <br />SCHEDULED SUPPLY AIRFLOW AT BOTH HIGH AND LOW FAN SPEED PER HVAC UNIT SCHEDULE. <br />• TEST AND BALANCE CONTRACTOR ALSO BALANCES THE EXHAUST FANS. <br />• THE LENNOX RTU'S HAVE LENNOX FURNISHED, FIELD INSTALLED CO2 SENSORS AND A DEMAND CONTROLLED <br />VENTILATION SEQUENCE THAT ALLOWS THE OUTSIDE AIR DAMPER TO OPEN TO A HIGH MINIMUM POSITION WHEN <br />CO2 LEVELS ARE ABOVE A CERTAIN THRESHOLD. <br />• LOW MINIMUM AND HIGH MINIMUM OUTSIDE AIR FLOWS ARE SET AT THE RTU'S BY THE TEST AND BALANCE <br />CONTRACTOR BY PROGRAMMING THE DAMPER POSITION SETTINGS IN THE PRODIGY BOARD AND DOCUMENTING <br />THOSE SETTINGS. DAMPER PERCENTAGES, ALONG WITH OUTSIDE AIRFLOW MEASUREMENTS ARE TO BE <br />DOCUMENTED IN THE TEST AND BALANCE REPORT. DOCUMENTATION OF THE OUTSIDE AIRFLOW IS PERTINENT FOR <br />THE COMMISSIONING TESTER. <br />• LOW MINIMUM OUTSIDE AIRFLOW IS THE LOWEST OUTSIDE AIRFLOW INTRODUCED INTO THE RTU. <br />• HIGH MINIMUM OUTSIDE AIRFLOW IS THE MAXIMUM POSITION THE OUTSIDE AIR DAMPER MODULATES OPEN TO PER <br />THE DEMAND CONTROLLED VENTILATION SEQUENCE. THIS IS TO BE SET AT HIGH FAN SPEED OPERATION. <br />• PRODIGY PARAMETER SETUP -TEST & BALANCE -DAMPER -DEMAND CONTROL VENT -DAMPER MAX OPENING. <br />• TEST AND BALANCE REPORT IS PROVIDED TO FSG, LENNOX, VERIZON RDC, A/E OF RECORD AND EXCEL.LENNOX IS <br />PROVIDED WITH ALL AIRFLOWS, SET POINTS AND PARAMETERS FOR EACH UNIT AT EACH STORE. <br />STEP 4 <br />• SHOPPING CENTER BMS CONTRACTOR INSTALLS ALL REMAINING CONTROL CONTROLS, COMMISSIONS THE BMS. <br />STEP 5 <br />• FSG TO OVERLAY DEVICES AND SENSORS AS REQUIRED FOR 'MONITORNING ONLY' <br />STEP 6 <br />• LEED COMMISSIONING <br />• IN ADDITION TO THE PRE-FUNCTIONAL CHECKLISTS FROM THE MEP SUBCONTRACTORS, THE FOLLOWING <br />DOCUMENTS WILL BE REQUIRED BY THE COMMISSIONING TESTER, VERIZON REPRESENTATIVE, FSG AND LENNOX A <br />MINIMUM OF 4 DAYS PRIOR TO THE COMMISSIONING: <br />1. TEST AND BALANCE REPORT (INCLUDING LOW MINIMUM AND HIGH MINIMUM OUTSIDE AIRFLOW SETTINGS AND <br />PROGRAMMED DAMPER POSITIONS) <br />2. LENNOX RTU COMMISSIONING REPORT <br />3. BMS COMMISSIONING REPORT <br />HVAC START-UP PROCEDURE <br />2.00 BALANCING SPECIFICATIONS AND RESPONSIBILITIES OF THE TEST AND BALANCE AGENCY <br />2.01 SCOPE <br />IN ACCORDANCE WITH PROJECT DRAWINGS AND SPECIFICATIONS, THE TEST AND BALANCE AGENCY SHALL <br />PROVIDE ALL SUPERVISION OF QUALITY ASSURANCE: <br />A. THE FINAL RESULT OF TEST AND BALANCE SHALL BE TO PROVIDE UNIFORM AIR TEMPERATURES WITHIN A TWO- <br />DEGREE FAHRENHEIT CONDITION. <br />B. ALL INSTRUMENTS USED SHALL BE MAINTAINED IN GOOD WORKING ORDER. IF REQUESTED, A CALIBRATION <br />TEST SHALL BE CONDUCTED IN THE PRESENCE OF THE ARCHITECT OR VERIZON WIRELESS REPRESENTATIVE. <br />C. GAUGES AND THERMOMETERS INSTALLED AS PART OF THE PROJECT ARE NOT TO BE USED FOR TEST AND <br />BALANCE. THE TEST AND BALANCE AGENCY SHALL CALIBRATE ALL SUCH GAUGES AND THERMOMETERS AND <br />SHALL AFFIX A PERMANENT TAG TO EACH STATING THE CORRECTIONS TO BE APPLIED. <br />D. IN THE EVENT OF DISPUTE, VERIZON WIRELESS OR ARCHITECT/ENGINEER MAY CHOOSE TO PROVIDE <br />VERIFICATION OF TEST AND BALANCE REPORTS, AND SUCH VERIFICATION SHALL BE BY THE N.E.B.B. <br />INVESTIGATING TEAM WITH THE ARCHITECT AND ENGINEERS PRESENT. REPORTS FOUND TO BE INACCURATE <br />WILL BE DISALLOWED. <br />2.02 GENERAL <br />A. THE SYSTEM TESTING, ADJUSTING AND BALANCING IS THE PROCESS OF CHECKING AND ADJUSTING ALL OF THE <br />BUILDING ENVIRONMENTAL SYSTEMS TO PRODUCE THE DESIGNED OBJECTIVES. <br />B. THE TEST AND BALANCE AGENCY SHALL NOT INSTRUCT OR DIRECT THE MECHANICAL CONTRACTOR IN ANY OF <br />THE WORK. ANY PROPOSED CHANGES OR REVISION IN THE WORK SHALL BE SUBMITTED TO THE ARCHITECT IN <br />WRITING. THE ARCHITECT SHALL, IN CONJUNCTION WITH VERIZON WIRELESS, PROCESS THE PROPOSAL AS <br />APPROPRIATE. <br />2.03 AIR SYSTEM PROCEDURES <br />THE TEST AND BALANCE AGENCY SHALL PERFORM THE FOLLOWING TEST AND BALANCING FUNCTIONS: <br />A. FAN SPEEDS –TEST AND ADJUST FAN RPM TO ACHIEVE DESIGN CFM REQUIREMENTS. <br />1. FOR BELT DRIVE FANS WITH A VFD <br />a. ADJUST BELT AND SHEAVES TO ACHIEVE HIGH SPEED FAN DESIGN AIRFLOW WITH VFD AT 60 <br />HERTZ.VFD IS NOT TO BE USED FOR INITIAL BALANCING. <br />b. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER AIRFLOW SETTINGS (CFM)TO MATCH BALANCED <br />AIRFLOW DURING HEATING AND SECOND STAGE COOLING OPERATION <br />c. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER AIRFLOW SETTINGS (CFM)TO MATCH SCHEDULED <br />LOW SPEED FAN AIRFLOW DURING FAN ONLY AND FIRST STAGE COOLING OPERATION <br />2. FOR DIRECT DRIVE FANS WITH ECM MOTORS, ADJUST RTU CONTROLLER OUTPUT PERCENTAGE TO ACHIEVE <br />DESIGN AIRFLOW <br />a. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER FAN OUTPUT SETTINGS (PERCENTAGE) TO <br />PROVIDE SCHEDULED HIGH SPEED FAN AIRFLOW DURING HEATING AND SECOND STAGE COOLING <br />OPERATION <br />b. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER FAN OUTPUT SETTINGS (PERCENTAGE) TO <br />PROVIDE SCHEDULED LOW SPEED FAN AIRFLOW DURING FAN ONLY AND FIRST STAGE COOLING <br />OPERATION <br />B. CURRENT AND VOLTAGE –MEASURE AND RECORD MOTOR CURRENT AND VOLTAGE. <br />C. PITOT TUBE TRAVERSE –PERFORM A PITOT TUBE TRAVERSE OF MAIN SUPPLY AND RETURN DUCTS WITH <br />OUTSIDE AIR DAMPER CLOSED TO OBTAIN TOTAL CFM AND VERIFY RTU LEAKAGE RATE. <br />1. IF LEAKAGE RATE IS FOUND TO BE GREATER THAN THE LOW MINIMUM OA SETTING, WORK WITH HEATING <br />CONTRACTOR TO DETERMINE THE CAUSE OF THE LEAKAGE AND CORRECT <br />2. DOCUMENT FINAL RTU LEAKAGE RATE <br />D. OUTSIDE AIR –TEST SYSTEM MINIMUM OUTSIDE AIR FLOW USING A VEGRID OR ROTATING VANE ANOMOMETER <br />OR OTHER MEASUREMENT DEVICE.TAB CONTRACTOR SETS THE DAMPER OPENING PERCENTAGES IN THE <br />PRODIGY CONTROLLER AS REQUIRED TO ACHIEVE OUTSIDE AIRFLOW PER THE FOLLOWING: <br />1. THE LOW MINIMUM OA SETTING MUST BE PERFORMED WITH THE UNIT IN BOTH LOW AND HIGH FAN SPEED <br />OPERATION <br />2. PRODIGY PROGRAMMING: <br />a. SETUP -TEST & BALANCE -DAMPER -MIN DAMPER POSITION BLOWER HIGH <br />b. SETUP -TEST & BALANCE -DAMPER -MIN DAMPER POSITION BLOWER LOW <br />3. THE HIGH MINIMUM OA SETTING MUST BE PERFORMED WITH THE UNIT IN HIGH SPEED FAN OPERATION <br />4. PRODIGY PROGRAMMING: <br />a. SETUP -TEST & BALANCE -DAMPER -DEMAND CONTROL VENT -DAMPER MAX OPENING <br />5. TEST AND BALANCE CONTRACTOR TO DOCUMENT THESE DAMPER OPENING PERCENTAGES ALONG WITH <br />OUTSIDE AIRFLOW MEASUREMENTS IN TEST AND BALANCE REPORT. <br />6. TEST AND BALANCE REPORT TO BE PROVIDED TO VERIZON RDC MANAGER, FSG AND COMMISSIONING <br />AGENT AND TESTER. <br />E. TEST AND BALANCE CONTRACTOR TO CONTACT LENNOX SUPPORT AT 800-367-6285 AND SELECT OPTION 2 FOR <br />TECH SUPPORT DURING TEST AND BALANCE IN ORDER TO CONFIRM CORRECT PROGRAMMING PARAMETERS IN <br />THE PRODIGY CONTROLLER. <br />2.04 VERIFICATION OF TEMPERATURE CONTROL <br />THE TEST AND BALANCE AGENCY SHALL BE ASSISTED BY THE CONTROL CONTRACTOR IN VERIFYING THE <br />OPERATION AND CALIBRATION OF ALL TEMPERATURE CONTROL SYSTEMS. THE FOLLOWING TESTS SHALL BE <br />CONDUCTED: <br />A. VERIFY THAT ALL CONTROL COMPONENTS ARE INSTALLED IN ACCORDANCE WITH PROJECT REQUIREMENTS <br />AND ARE FUNCTIONAL, INCLUDING ALL ELECTRICAL INTERLOCKS, DAMPER SEQUENCES, AND FIRE AND SMOKE <br />DETECTORS. <br />B. VERIFY THAT ALL CONTROLLING INSTRUMENTS ARE CALIBRATED AND SET FOR DESIGN OPERATING <br />CONDITIONS. <br />C. VERIFY THE ACCURACY OF THE FINAL SETTING BY TAKING TEMPERATURE READINGS. THE READINGS SHALL BE <br />IN A TYPICAL CONDITIONED SPACE FOR EACH SEPARATELY CONTROLLED ZONE. <br />2.05 TEST AND BALANCE REPORT <br /> <br />A. MERV-13 FILTERS SHALL BE INSTALLED PRIOR TO TEST AND BALANCE. <br />B. CONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS LISTED UNDER THE COMMISSIONING IN THE LEED <br />PROTOTYPE GREEN SPECIFICATIONS. <br />C. SYSTEM SHALL BE TESTED, ADJUSTED AND BALANCED WITH SUPERVISION BY NEBB CERTIFIED PERSONNEL <br />D. TEST & BALANCE REPORT TO INCLUDE OUTSIDE AIRFLOW READINGS. <br />E. EQUIPMENT SHALL BE BALANCED TO AIR FLOWS WITHIN: <br />1. TERMINAL DEVICES & BRANCH LINES: ±10% OF DESIGNED LOADS <br />2. MAIN DUCTS & AHU's: +5% OF DESIGNED LOADS <br />3. OUTDOOR AIR: + 5% OF DESIGNED LOADS <br />4. EXHAUST AIR: ± 10% OF DESIGNED LOADS <br />F. AN EMAIL TYPEWRITTEN COPY OF THE TEST AND BALANCE REPORT IS ALLOWABLE AND SHALL BE SUBMITTED <br />TO THE ARCHITECT. <br />G. THE REPORT SHALL CONTAIN THE FOLLOWING GENERAL DATA IN A FORMAT SELECTED BY THE TEST AND <br />BALANCE AGENCY: <br />1. PROJECT NUMBER. <br />2. PROJECT TITLE. <br />3. PROJECT LOCATION. <br />4. PROJECT ARCHITECT. <br />5. PROJECT MECHANICAL ENGINEER. <br />6. TEST AND BALANCE AGENCY. <br />7. TEST AND BALANCE ENGINEER. <br />8. OWNER. <br />9. MECHANICAL SUBCONTRACTORS. <br />10. DATES TESTS WERE PERFORMED. <br />11. CERTIFICATION. <br />H. THE TEST AND BALANCE REPORT SHALL BE RECORDED ON REPORT FORMS CONFORMING TO THE <br />RECOMMENDED FORMS IN THE N.E.B.B. NATIONAL STANDARDS. <br />1. PREFACE -A GENERAL DISCUSSION OF THE SYSTEM, ANY ABNORMALITIES AND PROBLEMS ENCOUNTERED <br />(DEFICIENCIES OUTSTANDING LISTED). <br />2. INSTRUMENTATION LIST -THE LIST OF INSTRUMENTS INCLUDE TYPE, MODEL, MANUFACTURER, SERIAL <br />NUMBER AND CALIBRATION DATE. <br />3. SYSTEM IDENTIFICATION -IN EACH REPORT, THE V.A.V. BOXES, ZONES, SUPPLY, RETURN, DATA SHEETS, <br />ALONG WITH A DRAWING SHOWING THE ABOVE. <br />4. AIR HANDLING EQUIPMENT TEST REPORT FORMS -RECORD THE FOLLOWING ON EACH AIR-HANDLING <br />EQUIPMENT TEST FORM: <br />a. MANUFACTURER, MODEL NUMBER AND SERIAL NUMBER <br />b. ALL DESIGN AND MANUFACTURER-RATED DATA. <br />c. TOTAL ACTUAL CFM BY TRAVERSE IF PRACTICAL, IF NOT PRACTICAL, THE SUM OF THE OUTLETS MAY BE <br />USED, OR A COMBINATION OF EACH OF THESE PROCEDURES. <br />d. SUCTION AND DISCHARGE STATIC PRESSURE OF EACH FAN, AS APPLICABLE. <br />2.06 ACCEPTANCE OF TEST AND BALANCE REPORT <br />A. AT THE TIME OF ACCEPTANCE OF THE TEST AND BALANCE REPORT, THE TEST AND BALANCE AGENCY SHALL, IF <br />REQUESTED, RECHECK IN THE PRESENCE OF THE VERIZON WIRELESS REPRESENTATIVE, SPECIFIC AND <br />RANDOM SELECTIONS OF DATA RECORDED IN THE CERTIFIED TEST AND BALANCE REPORT. <br />B. POINTS AND AREAS FOR RECHECK SHALL BE SELECTED BY THE VERIZON WIRELESS REPRESENTATIVE. <br />C. MEASUREMENTS AND TEST PROCEDURES SHALL BE THE SAME AS THE ORIGINAL TEST AND BALANCE. <br />D. SELECTIONS FOR RECHECK, SPECIFIC PLUS RANDOM, SHALL NOT NORMALLY EXCEED 15% OF THE TOTAL <br />NUMBER TABULATED IN THE REPORT, EXCEPT WHERE SPECIAL AIR SYSTEMS REQUIRE A COMPLETE RECHECK <br />FOR SAFETY REASONS. <br />E. IF RANDOM TESTS DEMONSTRATED A MEASURED FLOW DEVIATION OF 15% OR MORE FROM THAT RECORDED, A <br />NEW CERTIFIED TEST AND BALANCE REPORT MUST BE SUBMITTED, AND A NEW INSPECTION TEST MADE, ALL AT <br />NO ADDITIONAL COST TO VERIZON WIRELESS. <br />1.00 GENERAL SPECIFICATIONS FOR AIR BALANCING AND TESTING <br />1.01 GENERAL RESPONSIBILITIES <br />SYSTEM SHALL BE TESTED, ADJUSTED AND BALANCED WITH SUPERVISION BY NEBB CERTIFIED PERSONNEL. THE <br />T.A.B. REPORT SHALL INCLUDE MINIMUM & MAXIMUM OUTDOOR AIR FLOW READINGS. <br />A. GENERAL CONTRACTOR WILL BE RESPONSIBLE FOR HIRING THE SERVICES OF AN INDEPENDENT, THIRD-PARTY, <br />CERTIFIED TEST AND BALANCE AGENCY. UPON COMPLETION OF THIS JOB, TEST AND BALANCE AGENCY WILL BE <br />REQUIRED TO GENERATE A CERTIFIED AIR BALANCE REPORT. <br />B. GENERAL CONTRACTOR SHALL BE RESPONSIBLE TO SCHEDULE AND COORDINATE WITH TEST AND BALANCE <br />CONTRACTOR TO PROVIDE THEM WITH ALL REQUIRED PAPERWORK AND TO BE PREPARED FOR THE TEST AND <br />BALANCE AT THE SCHEDULED TIME. <br />C. THE PLANS AND SPECIFICATIONS HAVE INDICATED DEVICES FOR THE PURPOSE OF ADJUSTING THE SYSTEM TO <br />OBTAIN OPTIMUM OPERATING CONDITIONS. IT WILL BE THE RESPONSIBILITY OF THE MECHANICAL <br />SUBCONTRACTOR TO INSTALL THESE DEVICES IN A MANNER THAT WILL LEAVE THEM ACCESSIBLE AND READILY <br />ADJUSTABLE. THE TEST AND BALANCE AGENCY SHALL PROVIDE GUIDANCE IF THERE IS A QUESTIONABLE <br />ARRANGEMENT OF A CONTROL OR BALANCING DEVICE. <br />D. THE MECHANICAL CONTRACTOR AND THE SUPPLIERS OF THE HVAC EQUIPMENT SHALL ALL COOPERATE WITH <br />THE TEST AND BALANCE AGENCY TO PROVIDE ALL NECESSARY DATA ON THE DESIGN AND PROPER <br />APPLICATION OF THE SYSTEM COMPONENTS. IN ADDITION, THEY SHALL FURNISH ALL LABOR AND MATERIALS <br />REQUIRED TO ELIMINATE ANY SYSTEM DEFICIENCIES. <br />1.02 RESPONSIBILITIES OF THE MECHANICAL CONTRACTOR <br />A. THE MECHANICAL CONTRACTOR SHALL COMPLETE THE INSTALLATION AND OPERATE ALL HVAC SYSTEMS TO <br />ENSURE THEY ARE WORKING PROPERLY, AND SHALL PERFORM ALL OTHER ITEMS AS DESCRIBED HEREINAFTER <br />TO ASSIST THE TEST AND BALANCE AGENCY IN PERFORMING THE TESTING AND BALANCING OF THE HVAC <br />SYSTEMS. <br />B. AIR DISTRIBUTION SYSTEMS <br />1. VERIFY INSTALLATION FOR CONFORMITY TO DESIGN. <br />2. TERMINATE ALL SUPPLY, RETURN, AND EXHAUST DUCTS AND PRESSURE TEST THEM FOR LEAKAGE, AS <br />REQUIRED BY SPECIFICATION AND OR INDUSTRY STANDARDS. <br />3. ENSURE THAT ALL SPLITTERS, EXTRACTORS, VOLUME AND FIRE DAMPERS ARE PROPERLY LOCATED AND <br />FUNCTIONAL. DAMPERS SERVING REQUIREMENTS OF MINIMUM AND MAXIMUM OUTSIDE, RETURN, RELIEF, <br />AND EXHAUST AIR SHALL PROVIDE TIGHT CLOSURE AND FULL OPENING, WITH A SMOOTH AND FREE <br />OPERATION. <br />4. VERIFY THAT ALL SUPPLY, RETURN, EXHAUST, AND TRANSFER GRILLES, REGISTERS, DIFFUSERS AND HIGH <br />PRESSURE TERMINAL UNITS ARE INSTALLED AND OPERATIONAL. <br />5. ENSURE THAT AIR HANDLING SYSTEMS, UNITS AND ASSOCIATED SECTIONS, ACCESS DOORS, ETC., ARE <br />BLANKED AND/OR SEALED TO ELIMINATE EXCESSIVE BYPASS OR LEAKAGE OF AIR. <br />6. ENSURE THAT ALL FANS (SUPPLY, RETURN, RELIEF AND EXHAUST) ARE OPERATING AND FREE OF <br />VIBRATION. MEASUREMENT OF CURRENT AND VOLTAGE SHALL BE MADE TO VERIFY THAT THE MOTORS DO <br />NOT EXCEED NAME PLATE RATING. <br />7. MAKE ANY NECESSARY CHANGES TO THE SHEAVES, BELTS AND DAMPERS, AS REQUIRED BY THE TEST AND <br />BALANCE AGENCY, AT NO ADDITIONAL COST TO THE OWNER. <br />8. INSTALL CLEAN FILTERS PRIOR TO TESTING. <br />1.03 PRETEST AND BALANCE CHECK LIST TO BE PROVIDED TO THE INSTALLING CONTRACTOR <br />SYSTEM START UP <br />A. CHECK FUNCTIONS AND COMPONENTS LISTED IN 1.02. <br />DUCT SYSTEMS AND AIR DISTRIBUTIONS: <br />A. VERIFY THAT END CAPS, FLEXIBLE DUCTS, ACCESS PANELS, AND ALL PIECES OF AIR DISTRIBUTION ARE <br />INSTALLED PER SPECIFICATIONS OR INDUSTRY STANDARDS. <br />1.04 NOTIFICATION FOR TESTING AND BALANCING WORK TO BEGIN <br />A. THE MECHANICAL CONTRACTOR SHALL NOTIFY THE TEST AND BALANCE AGENCY IN WRITING WITH A COPY TO <br />VERIZON WIRELESS AND THE ARCHITECT WHEN ALL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS <br />ARE COMPLETE AND READY FOR TESTING AND BALANCING. THE MECHANICAL CONTRACTOR SHALL ATTEST <br />THAT HE HAS COMPLETED ALL ITEMS. <br />B. THIS INSPECTION SHALL ESTABLISH THAT THE SYSTEMS MEET THE BASIC REQUIREMENTS FOR TESTING AND <br />BALANCING. SHOULD THE INSPECTION REVEAL THE NOTIFICATION TO HAVE BEEN PREMATURE, ALL COSTS FOR <br />THE INSPECTION AND WORK PREVIOUSLY ACCOMPLISHED BY THE TEST AND BALANCE AGENCY SHALL BE PAID <br />FOR BY THE MECHANICAL CONTRACTOR. FURTHERMORE, SUCH ITEMS THAT ARE NOT READY FOR TESTING <br />AND BALANCING SHALL BE COMPLETED AND PLACED IN OPERATIONAL READINESS BEFORE TESTING AND <br />BALANCING SERVICES SHALL AGAIN BE REQUESTED. <br />AIR BALANCING AND TESTING <br />15A.4 TEMPERATURE CONTROLS <br />GENERAL REQUIREMENTS <br />SHOPPING CENTER BMS CONTRACTOR, AS PART OF THIS SCOPE OF WORK, SHALL PROVIDE A SYSTEM OF <br />TEMPERATURE CONTROLS INCLUDING THERMOSTATS, CONTROL PANELS, TIME SWITCHES, OVERRIDE TIMERS, <br />DAMPER MOTORS AND RELAYS REQUIRED TO PROVIDE THE DESIRED SEQUENCE OF OPERATION. PROVIDE <br />INTEGRATED WIRING DIAGRAMS SHOWING INTERCONNECTIONS BETWEEN FIELD-INSTALLED EQUIPMENT AND <br />PACKAGE WIRING FURNISHED WITH THE HVAC EQUIPMENT. <br />PER MALL STANDARDS, EACH RTU SHALL BE MONITORED AND CONTROLLED BY SHOPPING CENTER'S BMS.A <br />MINIMUM OF ONE CONTROLLER TO BE INSTALLED IN EACH HVAC UNIT. EACH CONTROLLER TO HAVE AS A MINIMUM, <br />THE FOLLOWING POINTS: <br />• FAN DISCHARGE TEMP <br />• MIXED AIR TEMP <br />• SPACE TEMP <br />• FLOW STATUS SWITCH <br />• COOLING CIRCUIT <br />• HEATING CIRCUIT <br />• FAN START/STOP <br />• ECONOMIZER MODULATION <br />• OUTDOOR AIR TEMP <br />DIVISION 15 CONTRACTOR TO PROVIDE TEMPORARY HONEYWELL OR EQUAL ELECTRONIC NON-PROGRAMMABLE <br />TYPE THERMOSTAT, MANUAL CHANGEOVER, SWITCHING SUB-BASE, MULTI-STAGE AS REQUIRED TO MATCH UNIT <br />COOLING/HEATING STAGING. LOW-VOLTAGE TYPE NON-PROGRAMMABLE HEATING AND COOLING THERMOSTATS <br />SHALL BE HONEYWELL SERIES T FOCUSPRO 5000 OR EQUAL WITH INTEGRAL SUB-BASE. INSTALL THERMOSTATS AT <br />48" AFF TO MEET ADA REQUIREMENTS UNLESS OTHERWISE NOTED ON THE PLANS. <br />EQUIPMENT SUPPLIER SHALL PROVIDE SUPERVISION AND ON-JOB CHECKOUT SERVICE AS REQUIRED TO ENSURE <br />THAT INSTALLATION MEETS REQUIREMENTS OF THE SPECIFICATION. <br />AFTER COMPLETION OF INSTALLATION, SHOPPING CENTER BMS CONTRACTOR SHALL CALIBRATE & ADJUST ALL <br />THERMOSTATS, CONTROL VALVES, MOTORS & OTHER EQUIPMENT PROVIDED AS PART OF THE TEMPERATURE <br />CONTROL SYSTEM. HE SHALL THEN PLACE IN COMPLETE OPERATING CONDITION SUBJECT TO THE APPROVAL OF <br />THE ENGINEER. <br />TEMPERATURE CONTROLS SHALL BE CALIBRATED TO +/- 2-DEG F. <br />TEMPERATURE CONTROLS SHALL ALLOW AN OCCUPANT ADJUSTMENT RANGE OF +/- 2-DEG F. <br />TEMPERATURE CONTROLS SHALL BE LABELED WITH ASSOCIATED HVAC UNIT AND INSTALLED PER MANUFACTURER'S <br />SPECIFICATIONS INCLUDING LOCATING THE UNITS ON SURFACES THAT ARE NOT EXPECTED TO EXPERIENCE <br />RAPIDLY CHANGING TEMPERATURES. <br />EQUIPMENT <br />ALL AUTOMATIC CONTROL VALVES AND DAMPERS SHALL BE FURNISHED AND INSTALLED BY THE MECHANICAL <br />CONTRACTOR. <br />MANUFACTURERS AND MODEL NUMBERS ARE LISTED FOR REFERENCE AS TO QUALITY AND FEATURES REQUIRED <br />FOR THE CONTROL DEVICES. PROVIDE CONTROL DEVICES AS REQUIRE BY SHOPPING CENTER BMS. <br />15A. 5 SEQUENCE OF OPERATION <br />HVAC UNITS (EXCLUDING COMPUTER ROOM UNIT) <br />SHALL SWITCH TO OCCUPIED MODE ONE HOUR BEFORE DOOR OPEN TIME AND SHALL SWITCH TO UNOCCUPIED MODE <br />ONE HOUR AFTER DOOR CLOSE TIME. <br />INTERIOR RELATIVE HUMIDITY IS LIMITED BY DESIGN TO LESS THAN 50% RELATIVE HUMIDITY TO COMPLY WITH <br />VERIZON WIRELESS OPR. <br />SETPOINTS <br />OCCUPIED SETPOINTS SHALL BE: <br />72ºF -COOLING <br />68ºF –HEATING <br />LOCALLY CHANGING THE HEATING/COOLING SETPOINT SHALL ENABLE A 120 MINUTES SETPOINT (± 2*F ADJUSTMENT) <br />OVERRIDE. <br />UNOCCUPIED SETPOINTS SHALL BE: <br />80ºF –COOLING <br />60ºF -HEATING <br />ECONOMIZATION –IF EQUIPMENT IS SO EQUIPPED <br />ECONOMIZER CONTROL SHALL COMPARE OUTDOOR AIR ENTHALPY TO RETURN AIRE ENTHALPY AND SELECT THE <br />LOWER ENTHALPY (RETURN OR OUTDOOR AIR) FOR COOLING. <br />IF OUTDOOR AIR IS SELECTED FOR COOLING, THE OUTDOOR AIR DAMPER SHALL BE PROPORTIONED OPEN TO <br />MAINTAIN BETWEEN 50 DEG. F. AND 56 DEG. F. SUPPLY AIR DISCHARGE TEMPERATURE. <br />DEMAND VENTILATION –IF EQUIPMENT IS SO EQUIPPED <br />PER ASHRAE 90.1, DURING UNOCCUPIED HOURS THE OUTDOOR AIR DAMPERS SHALL BE SET TO CLOSED. DURING <br />OCCUPIED HOURS, THE OUTDOOR AIR DAMPER SHALL OPEN TO THE LOW MINIMUM POSITION AS PROGRAMMED INTO <br />THE RTU PRODIGY CONTROLLER. PRODIGY PROGRAMMING SHALL BE ESTABLISHED BY THE TEST & BALANCE <br />CONTRACTOR TO ACHIEVE THE LOW MINIMUM OUTSIDE AIRFLOW INDICATED IN THE HVAC UNIT SCHEDULE DURING <br />BOTH LOW SPEED AND HIGH SPEED FAN OPERATION. IF INDOOR CO2 LEVELS RISE ABOVE 1050 PPM (BASED ON AN <br />OUTDOOR BASELINE CO2 LEVEL OF 400 PPM AND 650 PPM DIFFERENTIAL -ADJUSTABLE) THE OUTDOOR AIR DAMPER <br />SHALL MODULATE TOWARD THE HIGH MINIMUM POSITION AS PROGRAMMED INTO THE RTU PRODIGY CONTROLLER. <br />OUTDOOR AIR DAMPER SHALL BE AT HIGH MINIMUM POSITION AT CO2 LEVELS OF 1150 PPM. PRODIGY <br />PROGRAMMING SHALL BE ESTABLISHED BY THE TEST AND BALANCE CONTRACTOR TO ACHIEVE THE HIGH MINIMUM <br />OUTSIDE AIRFLOW INDICATED IN THE HVAC UNIT SCHEDULE DURING HIGH FAN SPEED OPERATION. <br />EMS CO2 LEVEL ALARM <br />THE EMS SHALL ALARM IF INDOOR CO2 LEVEL EXCEEDS 1400 PPM (ADJUSTABLE) FOR A PERIOD OF 120 MINUTES <br />(ADJUSTABLE). ALARM SHALL CLEAR WHEN THE INDOOR CO2 LEVEL DROPS BELOW 1300 PPM (ADJUSTABLE) FOR 5 <br />MINUTES (ADJUSTABLE). <br />INDOOR BLOWER <br />OCCUPIED –THE BLOWER SHALL OPERATE CONTINUOUSLY <br />UNOCCUPIED -THE BLOWER SHALL OPERATE ON DEMAND, HEATING/COOLING <br />RUNTIMES <br />ACCUMULATED RUNTIMES FOR THE COMPRESSOR AND INDOOR BLOWER SHALL BE PROVIDED. <br />OUTDOOR AIR LOCKOUT <br />WHEN TWO OR MORE UNITS SERVE A COMMON AREA (SALES FLOOR ZONE) THE OPERATING MODE <br />(HEATING/COOLING) SHALL BE SET BY THE OUTDOOR AIR TEMPERATURE. WHEN THE OUTSIDE AIR TEMPERATURE IS <br />GREATER THAN 50°F (ADJ) THE OPERATING MODE SHALL BE COOLING. WHEN THE OUTSIDE AIR TEMPERATURE IS <br />LESS THAN 50°F (ADJ) THE OPERATING MODE SHALL BE HEATING. <br />PROVIDE FREEZESTAT IN THE SUPPLY AIR DUCT TO SHUT DOWN THE SUPPLY FAN AND CLOSE THE OUTDOOR AIR <br />DAMPER IF TEMPERATURE IN THE SUPPLY DUCT DROPS BELOW 40-DEGREES FAHRENHEIT. <br />RESTROOM AND JANITOR CLOSET EXHAUST FAN <br />RESTROOM / JANITOR CLOSET EXHAUST FAN (EF-1) SHALL BE INTERLOCKED TO TIMECLOCK TO ALLOW FOR <br />CONTINUOUS OPERATION DURING OCCUPIED HOURS AND SHALL SHUT DOWN DURING UNOCCUPIED HOURS. <br />TELCO SPLIT AC UNIT (CRU-1 / ACCU-1) <br />SYSTEM SHALL BE AVAILABLE FOR OPERATION 24/7. UPON A RISE IN SPACE TEMPERATURE SETPOINT OF 78 <br />DEGREES F (ADJUSTABLE), CRU-1 / ACCU-1 SHALL ENERGIZE AND CYCLE COMPRESSOR AS REQUIRED TO MAINTAIN <br />SPACE TEMPERATURE. <br />UPON A DROP IN SPACE TEMPERATURE BELOW SETPOINT, CRU-1 / ACCU-1 SHALL DE-ENERGIZE <br />HEAT PUMP AC UNIT (FCU-1 / HP-1) <br />REFERENCE THE HEAT PUMP UNIT CONTROL MATRIX FOR SEQUENCE OF OPERATIONS. <br />HVAC TEMPERATURE CONTROLS <br />Mechanical and Electrical Engineers <br />Lilker Associates <br />1001 Avenue of the Americas <br />New York, NY 10018 <br />tel 212.695.1000 <br />fax 212.695.1299 <br />www.lilker.com <br />Kenneth A. Gruskin AIA <br />No. Date Description <br />Consultant: <br />Checked By: <br />Drawn By: <br />Job Address: <br />Drawing Title: <br />Revision Issue: <br />Professional Seal: <br />Drawing Number: <br />2022 Gruskin Architecture + Design, P.C.c <br />This document and the ideas and designs incorporated <br />herein, as an instrument of professional service, is the <br />property of GRUSKIN ARCHITECTURE + DESIGN, P.C., <br />and is not to be used in whole or in part for any other <br />project without the written authorization of GRUSKIN <br />ARCHITECTURE + DESIGN, P.C. <br />North <br />Arrow: <br />Job Name and Number: <br />Date Issued For <br />All Rights Reserved <br />Client: <br />Landlord: <br />Permit: <br />Bid: <br />Construction: <br />0006261 <br />AR91629 <br />5421 <br />9613 <br />39209 <br />10635 <br />2537 <br />11016 <br />5734 <br />ARC 2596 <br />4674 <br />2666 <br />AI 09999 <br />2796 <br />0401 011223 <br />2572 <br />17680 <br />RA-015432-B <br />025528-1 NY <br />TX <br />VA <br />VT <br />MA <br />MT <br />RI <br />PA <br />NY <br />NJ <br />NH <br />MD <br />LA <br />ME <br />KS <br />FL <br />DE <br />CT <br />AZ <br />AL <br />C-1967WY <br />RA011075GA <br />AR10400066IN <br />C-29898CA <br />NM 004168 <br />ARC-400347CO <br />HI AR 11489 <br />PR 19965 <br />OR 4899 <br />SC 6834 <br />NC 9961 <br />13761OH <br />05713IA <br />WV 3727 <br />IL 001-019152 <br />UT 5881358-0301 <br />ID AR-984459 <br />1301052379MI <br />ARC100723DC <br />WI 9900-005MN44326 <br />A-3547NE <br />3811AR <br />5967KY 101374TN <br />MS 3860 <br />1666ND <br />A-2005029740MO <br />a4895OK <br />NV 5521 <br />WA 10344 <br />13167AK <br />SD 11532 <br />C: <br />\ <br />R <br />e <br />v <br />i <br />t <br /> <br />L <br />o <br />c <br />a <br />l <br /> <br />F <br />i <br />l <br />e <br />s <br />\ <br />2 <br />4 <br />0 <br />0 <br />1 <br />3 <br />0 <br />8 <br />_ <br />V <br />E <br />R <br />I <br />Z <br />O <br />N <br />_ <br />S <br />a <br />n <br />t <br />a <br /> <br />A <br />n <br />a <br />_ <br />C <br />A <br />_ <br />ME <br />C <br />H <br />A <br />N <br />I <br />C <br />A <br />L <br />_ <br />v <br />2 <br />3 <br />_ <br />r <br />t <br />r <br />o <br />v <br />a <br />t <br />o <br />T <br />7 <br />V <br />P <br />K <br />. <br />r <br />v <br />t <br />2023-0069 <br />Proposed <br />Store Design <br />for: VERIZON <br />Metro Pointe <br />3500 South Bristol Street <br />Suite 100 <br />Santa Ana, CA 92704 <br />3/15/2024 <br />3/15/2024 <br />HVAC SPECIFICATIONS <br />M.0.1 <br />BS <br />RT <br />34 OF 81 <br />3500 S Bristol St Unit# 100 - <br />101119098, 20182666 & <br />401390437/11/2024