STEP 1
<br />• HVAC CONTRACTOR, SETS RTU'S. SHOPPING CENTER BMS CONTRACTOR INSTALLS ALL REQUIRED SENSORS
<br />(MECHANICAL CONTRACTOR AND BMS CONTRACTOR TO COORDINATE INSTALLATION).
<br />• CONTRACTOR COMPLETES ENTIRE HVAC INSTALLATION INCLUDING ALL GRILLES, ELECTRICAL POWER .
<br />• HVAC CONTRACTOR SHALL PROVIDE, CONNECT AND TEST OPERATION OF TEMPORARY THERMOSTATS USING THE
<br />NEW 18/8 THERMOSTAT CABLE AS SHOWN ON SHEET M.1.0 ON THE FIELD INSTALLED SENSOR DETAIL.
<br />STEP 2
<br />• LENNOX PERFORMS COMMISSIONING OF RTU'S AND ESTABLISHES PRODIGY SETTINGS SO PROGRAMMED VALUES IN
<br />RTU CONTROLLER ARE DONE IN ACCORDANCE WITH THE INFORMATION IN THE DRAWINGS AND SPECIFICATIONS.
<br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH ESTABLISHES PROPER SETTINGS FOR SUPPLY FAN HIGH AND
<br />LOW SPEED OPERATION. (AS INDICATED IN HVAC UNIT SCHEDULE)
<br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH CALIBRATES THE PHYSICAL POSITION OF THE OA DAMPER
<br />WITH THE LENNOX DAMPER POSITION STATUS POINT. (VALIDATING THAT THE ECONOMIZER IS CLOSING PROPERLY,
<br />PROPERLY STARTED UP AND THE DAMPER POSITIONS MATCH THE DAMPER POSITION FEEDBACK ON THE PRODIGY
<br />BOARD) (FULLY CLOSED DAMPER INDICATES 0% OPEN FEEDBACK AT PRODIGY/FULLY OPEN DAMPER INDICATES
<br />100% OPEN FEEDBACK AT PRODIGY).
<br />• AS PART OF THE RTU COMMISSIONING, LENNOX TECH ESTABLISHES THE FOLLOWING PARAMETERS FOR DEMAND
<br />CONTROLLED VENTILATION:
<br />1. DEMAND CONTROL VENT -DAMPER START OPEN = 1050 PPM
<br />2. DEMAND CONTROL VENT -DAMPER FULL OPEN = 1150 PPM
<br />• LENNOX PROVIDES COMMISSIONING REPORT TO FSG, VERIZON RDC AND EXCEL & INFORM (AS LEED CXP).REPORT
<br />INCLUDES ALL FAN SETTING INFORMATION SO ALL PARTIES ARE INFORMED OF HIGH AND LOW SPEED AIRFLOW /
<br />OUTPUT %.
<br />STEP 3
<br />• TEST & BALANCE OCCURS.
<br />• MERV 13 FILTERS INSTALLED AND DATED PRIOR TO TEST AND BALANCE.
<br />• TEST AND BALANCE CONTRACTOR ADJUSTS SHEAVES, PULLEYS, BELTS, ETC. ON BELT DRIVE FANS WITH VFDS TO
<br />ACHIEVE SCHEDULED SUPPLY AIRFLOW AT HIGH FAN SPEED PER HVAC UNIT SCHEDULE.
<br />• TEST AND BALANCE CONTRACTOR SETS PRODIGY OUTPUT TO ECM DIRECT DRIVE FAN MOTORS, TO ACHIEVE
<br />SCHEDULED SUPPLY AIRFLOW AT BOTH HIGH AND LOW FAN SPEED PER HVAC UNIT SCHEDULE.
<br />• TEST AND BALANCE CONTRACTOR ALSO BALANCES THE EXHAUST FANS.
<br />• THE LENNOX RTU'S HAVE LENNOX FURNISHED, FIELD INSTALLED CO2 SENSORS AND A DEMAND CONTROLLED
<br />VENTILATION SEQUENCE THAT ALLOWS THE OUTSIDE AIR DAMPER TO OPEN TO A HIGH MINIMUM POSITION WHEN
<br />CO2 LEVELS ARE ABOVE A CERTAIN THRESHOLD.
<br />• LOW MINIMUM AND HIGH MINIMUM OUTSIDE AIR FLOWS ARE SET AT THE RTU'S BY THE TEST AND BALANCE
<br />CONTRACTOR BY PROGRAMMING THE DAMPER POSITION SETTINGS IN THE PRODIGY BOARD AND DOCUMENTING
<br />THOSE SETTINGS. DAMPER PERCENTAGES, ALONG WITH OUTSIDE AIRFLOW MEASUREMENTS ARE TO BE
<br />DOCUMENTED IN THE TEST AND BALANCE REPORT. DOCUMENTATION OF THE OUTSIDE AIRFLOW IS PERTINENT FOR
<br />THE COMMISSIONING TESTER.
<br />• LOW MINIMUM OUTSIDE AIRFLOW IS THE LOWEST OUTSIDE AIRFLOW INTRODUCED INTO THE RTU.
<br />• HIGH MINIMUM OUTSIDE AIRFLOW IS THE MAXIMUM POSITION THE OUTSIDE AIR DAMPER MODULATES OPEN TO PER
<br />THE DEMAND CONTROLLED VENTILATION SEQUENCE. THIS IS TO BE SET AT HIGH FAN SPEED OPERATION.
<br />• PRODIGY PARAMETER SETUP -TEST & BALANCE -DAMPER -DEMAND CONTROL VENT -DAMPER MAX OPENING.
<br />• TEST AND BALANCE REPORT IS PROVIDED TO FSG, LENNOX, VERIZON RDC, A/E OF RECORD AND EXCEL.LENNOX IS
<br />PROVIDED WITH ALL AIRFLOWS, SET POINTS AND PARAMETERS FOR EACH UNIT AT EACH STORE.
<br />STEP 4
<br />• SHOPPING CENTER BMS CONTRACTOR INSTALLS ALL REMAINING CONTROL CONTROLS, COMMISSIONS THE BMS.
<br />STEP 5
<br />• FSG TO OVERLAY DEVICES AND SENSORS AS REQUIRED FOR 'MONITORNING ONLY'
<br />STEP 6
<br />• LEED COMMISSIONING
<br />• IN ADDITION TO THE PRE-FUNCTIONAL CHECKLISTS FROM THE MEP SUBCONTRACTORS, THE FOLLOWING
<br />DOCUMENTS WILL BE REQUIRED BY THE COMMISSIONING TESTER, VERIZON REPRESENTATIVE, FSG AND LENNOX A
<br />MINIMUM OF 4 DAYS PRIOR TO THE COMMISSIONING:
<br />1. TEST AND BALANCE REPORT (INCLUDING LOW MINIMUM AND HIGH MINIMUM OUTSIDE AIRFLOW SETTINGS AND
<br />PROGRAMMED DAMPER POSITIONS)
<br />2. LENNOX RTU COMMISSIONING REPORT
<br />3. BMS COMMISSIONING REPORT
<br />HVAC START-UP PROCEDURE
<br />2.00 BALANCING SPECIFICATIONS AND RESPONSIBILITIES OF THE TEST AND BALANCE AGENCY
<br />2.01 SCOPE
<br />IN ACCORDANCE WITH PROJECT DRAWINGS AND SPECIFICATIONS, THE TEST AND BALANCE AGENCY SHALL
<br />PROVIDE ALL SUPERVISION OF QUALITY ASSURANCE:
<br />A. THE FINAL RESULT OF TEST AND BALANCE SHALL BE TO PROVIDE UNIFORM AIR TEMPERATURES WITHIN A TWO-
<br />DEGREE FAHRENHEIT CONDITION.
<br />B. ALL INSTRUMENTS USED SHALL BE MAINTAINED IN GOOD WORKING ORDER. IF REQUESTED, A CALIBRATION
<br />TEST SHALL BE CONDUCTED IN THE PRESENCE OF THE ARCHITECT OR VERIZON WIRELESS REPRESENTATIVE.
<br />C. GAUGES AND THERMOMETERS INSTALLED AS PART OF THE PROJECT ARE NOT TO BE USED FOR TEST AND
<br />BALANCE. THE TEST AND BALANCE AGENCY SHALL CALIBRATE ALL SUCH GAUGES AND THERMOMETERS AND
<br />SHALL AFFIX A PERMANENT TAG TO EACH STATING THE CORRECTIONS TO BE APPLIED.
<br />D. IN THE EVENT OF DISPUTE, VERIZON WIRELESS OR ARCHITECT/ENGINEER MAY CHOOSE TO PROVIDE
<br />VERIFICATION OF TEST AND BALANCE REPORTS, AND SUCH VERIFICATION SHALL BE BY THE N.E.B.B.
<br />INVESTIGATING TEAM WITH THE ARCHITECT AND ENGINEERS PRESENT. REPORTS FOUND TO BE INACCURATE
<br />WILL BE DISALLOWED.
<br />2.02 GENERAL
<br />A. THE SYSTEM TESTING, ADJUSTING AND BALANCING IS THE PROCESS OF CHECKING AND ADJUSTING ALL OF THE
<br />BUILDING ENVIRONMENTAL SYSTEMS TO PRODUCE THE DESIGNED OBJECTIVES.
<br />B. THE TEST AND BALANCE AGENCY SHALL NOT INSTRUCT OR DIRECT THE MECHANICAL CONTRACTOR IN ANY OF
<br />THE WORK. ANY PROPOSED CHANGES OR REVISION IN THE WORK SHALL BE SUBMITTED TO THE ARCHITECT IN
<br />WRITING. THE ARCHITECT SHALL, IN CONJUNCTION WITH VERIZON WIRELESS, PROCESS THE PROPOSAL AS
<br />APPROPRIATE.
<br />2.03 AIR SYSTEM PROCEDURES
<br />THE TEST AND BALANCE AGENCY SHALL PERFORM THE FOLLOWING TEST AND BALANCING FUNCTIONS:
<br />A. FAN SPEEDS –TEST AND ADJUST FAN RPM TO ACHIEVE DESIGN CFM REQUIREMENTS.
<br />1. FOR BELT DRIVE FANS WITH A VFD
<br />a. ADJUST BELT AND SHEAVES TO ACHIEVE HIGH SPEED FAN DESIGN AIRFLOW WITH VFD AT 60
<br />HERTZ.VFD IS NOT TO BE USED FOR INITIAL BALANCING.
<br />b. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER AIRFLOW SETTINGS (CFM)TO MATCH BALANCED
<br />AIRFLOW DURING HEATING AND SECOND STAGE COOLING OPERATION
<br />c. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER AIRFLOW SETTINGS (CFM)TO MATCH SCHEDULED
<br />LOW SPEED FAN AIRFLOW DURING FAN ONLY AND FIRST STAGE COOLING OPERATION
<br />2. FOR DIRECT DRIVE FANS WITH ECM MOTORS, ADJUST RTU CONTROLLER OUTPUT PERCENTAGE TO ACHIEVE
<br />DESIGN AIRFLOW
<br />a. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER FAN OUTPUT SETTINGS (PERCENTAGE) TO
<br />PROVIDE SCHEDULED HIGH SPEED FAN AIRFLOW DURING HEATING AND SECOND STAGE COOLING
<br />OPERATION
<br />b. VERIFY AND, IF NECESSARY, ADJUST RTU CONTROLLER FAN OUTPUT SETTINGS (PERCENTAGE) TO
<br />PROVIDE SCHEDULED LOW SPEED FAN AIRFLOW DURING FAN ONLY AND FIRST STAGE COOLING
<br />OPERATION
<br />B. CURRENT AND VOLTAGE –MEASURE AND RECORD MOTOR CURRENT AND VOLTAGE.
<br />C. PITOT TUBE TRAVERSE –PERFORM A PITOT TUBE TRAVERSE OF MAIN SUPPLY AND RETURN DUCTS WITH
<br />OUTSIDE AIR DAMPER CLOSED TO OBTAIN TOTAL CFM AND VERIFY RTU LEAKAGE RATE.
<br />1. IF LEAKAGE RATE IS FOUND TO BE GREATER THAN THE LOW MINIMUM OA SETTING, WORK WITH HEATING
<br />CONTRACTOR TO DETERMINE THE CAUSE OF THE LEAKAGE AND CORRECT
<br />2. DOCUMENT FINAL RTU LEAKAGE RATE
<br />D. OUTSIDE AIR –TEST SYSTEM MINIMUM OUTSIDE AIR FLOW USING A VEGRID OR ROTATING VANE ANOMOMETER
<br />OR OTHER MEASUREMENT DEVICE.TAB CONTRACTOR SETS THE DAMPER OPENING PERCENTAGES IN THE
<br />PRODIGY CONTROLLER AS REQUIRED TO ACHIEVE OUTSIDE AIRFLOW PER THE FOLLOWING:
<br />1. THE LOW MINIMUM OA SETTING MUST BE PERFORMED WITH THE UNIT IN BOTH LOW AND HIGH FAN SPEED
<br />OPERATION
<br />2. PRODIGY PROGRAMMING:
<br />a. SETUP -TEST & BALANCE -DAMPER -MIN DAMPER POSITION BLOWER HIGH
<br />b. SETUP -TEST & BALANCE -DAMPER -MIN DAMPER POSITION BLOWER LOW
<br />3. THE HIGH MINIMUM OA SETTING MUST BE PERFORMED WITH THE UNIT IN HIGH SPEED FAN OPERATION
<br />4. PRODIGY PROGRAMMING:
<br />a. SETUP -TEST & BALANCE -DAMPER -DEMAND CONTROL VENT -DAMPER MAX OPENING
<br />5. TEST AND BALANCE CONTRACTOR TO DOCUMENT THESE DAMPER OPENING PERCENTAGES ALONG WITH
<br />OUTSIDE AIRFLOW MEASUREMENTS IN TEST AND BALANCE REPORT.
<br />6. TEST AND BALANCE REPORT TO BE PROVIDED TO VERIZON RDC MANAGER, FSG AND COMMISSIONING
<br />AGENT AND TESTER.
<br />E. TEST AND BALANCE CONTRACTOR TO CONTACT LENNOX SUPPORT AT 800-367-6285 AND SELECT OPTION 2 FOR
<br />TECH SUPPORT DURING TEST AND BALANCE IN ORDER TO CONFIRM CORRECT PROGRAMMING PARAMETERS IN
<br />THE PRODIGY CONTROLLER.
<br />2.04 VERIFICATION OF TEMPERATURE CONTROL
<br />THE TEST AND BALANCE AGENCY SHALL BE ASSISTED BY THE CONTROL CONTRACTOR IN VERIFYING THE
<br />OPERATION AND CALIBRATION OF ALL TEMPERATURE CONTROL SYSTEMS. THE FOLLOWING TESTS SHALL BE
<br />CONDUCTED:
<br />A. VERIFY THAT ALL CONTROL COMPONENTS ARE INSTALLED IN ACCORDANCE WITH PROJECT REQUIREMENTS
<br />AND ARE FUNCTIONAL, INCLUDING ALL ELECTRICAL INTERLOCKS, DAMPER SEQUENCES, AND FIRE AND SMOKE
<br />DETECTORS.
<br />B. VERIFY THAT ALL CONTROLLING INSTRUMENTS ARE CALIBRATED AND SET FOR DESIGN OPERATING
<br />CONDITIONS.
<br />C. VERIFY THE ACCURACY OF THE FINAL SETTING BY TAKING TEMPERATURE READINGS. THE READINGS SHALL BE
<br />IN A TYPICAL CONDITIONED SPACE FOR EACH SEPARATELY CONTROLLED ZONE.
<br />2.05 TEST AND BALANCE REPORT
<br />
<br />A. MERV-13 FILTERS SHALL BE INSTALLED PRIOR TO TEST AND BALANCE.
<br />B. CONTRACTOR SHALL COMPLY WITH THE REQUIREMENTS LISTED UNDER THE COMMISSIONING IN THE LEED
<br />PROTOTYPE GREEN SPECIFICATIONS.
<br />C. SYSTEM SHALL BE TESTED, ADJUSTED AND BALANCED WITH SUPERVISION BY NEBB CERTIFIED PERSONNEL
<br />D. TEST & BALANCE REPORT TO INCLUDE OUTSIDE AIRFLOW READINGS.
<br />E. EQUIPMENT SHALL BE BALANCED TO AIR FLOWS WITHIN:
<br />1. TERMINAL DEVICES & BRANCH LINES: ±10% OF DESIGNED LOADS
<br />2. MAIN DUCTS & AHU's: +5% OF DESIGNED LOADS
<br />3. OUTDOOR AIR: + 5% OF DESIGNED LOADS
<br />4. EXHAUST AIR: ± 10% OF DESIGNED LOADS
<br />F. AN EMAIL TYPEWRITTEN COPY OF THE TEST AND BALANCE REPORT IS ALLOWABLE AND SHALL BE SUBMITTED
<br />TO THE ARCHITECT.
<br />G. THE REPORT SHALL CONTAIN THE FOLLOWING GENERAL DATA IN A FORMAT SELECTED BY THE TEST AND
<br />BALANCE AGENCY:
<br />1. PROJECT NUMBER.
<br />2. PROJECT TITLE.
<br />3. PROJECT LOCATION.
<br />4. PROJECT ARCHITECT.
<br />5. PROJECT MECHANICAL ENGINEER.
<br />6. TEST AND BALANCE AGENCY.
<br />7. TEST AND BALANCE ENGINEER.
<br />8. OWNER.
<br />9. MECHANICAL SUBCONTRACTORS.
<br />10. DATES TESTS WERE PERFORMED.
<br />11. CERTIFICATION.
<br />H. THE TEST AND BALANCE REPORT SHALL BE RECORDED ON REPORT FORMS CONFORMING TO THE
<br />RECOMMENDED FORMS IN THE N.E.B.B. NATIONAL STANDARDS.
<br />1. PREFACE -A GENERAL DISCUSSION OF THE SYSTEM, ANY ABNORMALITIES AND PROBLEMS ENCOUNTERED
<br />(DEFICIENCIES OUTSTANDING LISTED).
<br />2. INSTRUMENTATION LIST -THE LIST OF INSTRUMENTS INCLUDE TYPE, MODEL, MANUFACTURER, SERIAL
<br />NUMBER AND CALIBRATION DATE.
<br />3. SYSTEM IDENTIFICATION -IN EACH REPORT, THE V.A.V. BOXES, ZONES, SUPPLY, RETURN, DATA SHEETS,
<br />ALONG WITH A DRAWING SHOWING THE ABOVE.
<br />4. AIR HANDLING EQUIPMENT TEST REPORT FORMS -RECORD THE FOLLOWING ON EACH AIR-HANDLING
<br />EQUIPMENT TEST FORM:
<br />a. MANUFACTURER, MODEL NUMBER AND SERIAL NUMBER
<br />b. ALL DESIGN AND MANUFACTURER-RATED DATA.
<br />c. TOTAL ACTUAL CFM BY TRAVERSE IF PRACTICAL, IF NOT PRACTICAL, THE SUM OF THE OUTLETS MAY BE
<br />USED, OR A COMBINATION OF EACH OF THESE PROCEDURES.
<br />d. SUCTION AND DISCHARGE STATIC PRESSURE OF EACH FAN, AS APPLICABLE.
<br />2.06 ACCEPTANCE OF TEST AND BALANCE REPORT
<br />A. AT THE TIME OF ACCEPTANCE OF THE TEST AND BALANCE REPORT, THE TEST AND BALANCE AGENCY SHALL, IF
<br />REQUESTED, RECHECK IN THE PRESENCE OF THE VERIZON WIRELESS REPRESENTATIVE, SPECIFIC AND
<br />RANDOM SELECTIONS OF DATA RECORDED IN THE CERTIFIED TEST AND BALANCE REPORT.
<br />B. POINTS AND AREAS FOR RECHECK SHALL BE SELECTED BY THE VERIZON WIRELESS REPRESENTATIVE.
<br />C. MEASUREMENTS AND TEST PROCEDURES SHALL BE THE SAME AS THE ORIGINAL TEST AND BALANCE.
<br />D. SELECTIONS FOR RECHECK, SPECIFIC PLUS RANDOM, SHALL NOT NORMALLY EXCEED 15% OF THE TOTAL
<br />NUMBER TABULATED IN THE REPORT, EXCEPT WHERE SPECIAL AIR SYSTEMS REQUIRE A COMPLETE RECHECK
<br />FOR SAFETY REASONS.
<br />E. IF RANDOM TESTS DEMONSTRATED A MEASURED FLOW DEVIATION OF 15% OR MORE FROM THAT RECORDED, A
<br />NEW CERTIFIED TEST AND BALANCE REPORT MUST BE SUBMITTED, AND A NEW INSPECTION TEST MADE, ALL AT
<br />NO ADDITIONAL COST TO VERIZON WIRELESS.
<br />1.00 GENERAL SPECIFICATIONS FOR AIR BALANCING AND TESTING
<br />1.01 GENERAL RESPONSIBILITIES
<br />SYSTEM SHALL BE TESTED, ADJUSTED AND BALANCED WITH SUPERVISION BY NEBB CERTIFIED PERSONNEL. THE
<br />T.A.B. REPORT SHALL INCLUDE MINIMUM & MAXIMUM OUTDOOR AIR FLOW READINGS.
<br />A. GENERAL CONTRACTOR WILL BE RESPONSIBLE FOR HIRING THE SERVICES OF AN INDEPENDENT, THIRD-PARTY,
<br />CERTIFIED TEST AND BALANCE AGENCY. UPON COMPLETION OF THIS JOB, TEST AND BALANCE AGENCY WILL BE
<br />REQUIRED TO GENERATE A CERTIFIED AIR BALANCE REPORT.
<br />B. GENERAL CONTRACTOR SHALL BE RESPONSIBLE TO SCHEDULE AND COORDINATE WITH TEST AND BALANCE
<br />CONTRACTOR TO PROVIDE THEM WITH ALL REQUIRED PAPERWORK AND TO BE PREPARED FOR THE TEST AND
<br />BALANCE AT THE SCHEDULED TIME.
<br />C. THE PLANS AND SPECIFICATIONS HAVE INDICATED DEVICES FOR THE PURPOSE OF ADJUSTING THE SYSTEM TO
<br />OBTAIN OPTIMUM OPERATING CONDITIONS. IT WILL BE THE RESPONSIBILITY OF THE MECHANICAL
<br />SUBCONTRACTOR TO INSTALL THESE DEVICES IN A MANNER THAT WILL LEAVE THEM ACCESSIBLE AND READILY
<br />ADJUSTABLE. THE TEST AND BALANCE AGENCY SHALL PROVIDE GUIDANCE IF THERE IS A QUESTIONABLE
<br />ARRANGEMENT OF A CONTROL OR BALANCING DEVICE.
<br />D. THE MECHANICAL CONTRACTOR AND THE SUPPLIERS OF THE HVAC EQUIPMENT SHALL ALL COOPERATE WITH
<br />THE TEST AND BALANCE AGENCY TO PROVIDE ALL NECESSARY DATA ON THE DESIGN AND PROPER
<br />APPLICATION OF THE SYSTEM COMPONENTS. IN ADDITION, THEY SHALL FURNISH ALL LABOR AND MATERIALS
<br />REQUIRED TO ELIMINATE ANY SYSTEM DEFICIENCIES.
<br />1.02 RESPONSIBILITIES OF THE MECHANICAL CONTRACTOR
<br />A. THE MECHANICAL CONTRACTOR SHALL COMPLETE THE INSTALLATION AND OPERATE ALL HVAC SYSTEMS TO
<br />ENSURE THEY ARE WORKING PROPERLY, AND SHALL PERFORM ALL OTHER ITEMS AS DESCRIBED HEREINAFTER
<br />TO ASSIST THE TEST AND BALANCE AGENCY IN PERFORMING THE TESTING AND BALANCING OF THE HVAC
<br />SYSTEMS.
<br />B. AIR DISTRIBUTION SYSTEMS
<br />1. VERIFY INSTALLATION FOR CONFORMITY TO DESIGN.
<br />2. TERMINATE ALL SUPPLY, RETURN, AND EXHAUST DUCTS AND PRESSURE TEST THEM FOR LEAKAGE, AS
<br />REQUIRED BY SPECIFICATION AND OR INDUSTRY STANDARDS.
<br />3. ENSURE THAT ALL SPLITTERS, EXTRACTORS, VOLUME AND FIRE DAMPERS ARE PROPERLY LOCATED AND
<br />FUNCTIONAL. DAMPERS SERVING REQUIREMENTS OF MINIMUM AND MAXIMUM OUTSIDE, RETURN, RELIEF,
<br />AND EXHAUST AIR SHALL PROVIDE TIGHT CLOSURE AND FULL OPENING, WITH A SMOOTH AND FREE
<br />OPERATION.
<br />4. VERIFY THAT ALL SUPPLY, RETURN, EXHAUST, AND TRANSFER GRILLES, REGISTERS, DIFFUSERS AND HIGH
<br />PRESSURE TERMINAL UNITS ARE INSTALLED AND OPERATIONAL.
<br />5. ENSURE THAT AIR HANDLING SYSTEMS, UNITS AND ASSOCIATED SECTIONS, ACCESS DOORS, ETC., ARE
<br />BLANKED AND/OR SEALED TO ELIMINATE EXCESSIVE BYPASS OR LEAKAGE OF AIR.
<br />6. ENSURE THAT ALL FANS (SUPPLY, RETURN, RELIEF AND EXHAUST) ARE OPERATING AND FREE OF
<br />VIBRATION. MEASUREMENT OF CURRENT AND VOLTAGE SHALL BE MADE TO VERIFY THAT THE MOTORS DO
<br />NOT EXCEED NAME PLATE RATING.
<br />7. MAKE ANY NECESSARY CHANGES TO THE SHEAVES, BELTS AND DAMPERS, AS REQUIRED BY THE TEST AND
<br />BALANCE AGENCY, AT NO ADDITIONAL COST TO THE OWNER.
<br />8. INSTALL CLEAN FILTERS PRIOR TO TESTING.
<br />1.03 PRETEST AND BALANCE CHECK LIST TO BE PROVIDED TO THE INSTALLING CONTRACTOR
<br />SYSTEM START UP
<br />A. CHECK FUNCTIONS AND COMPONENTS LISTED IN 1.02.
<br />DUCT SYSTEMS AND AIR DISTRIBUTIONS:
<br />A. VERIFY THAT END CAPS, FLEXIBLE DUCTS, ACCESS PANELS, AND ALL PIECES OF AIR DISTRIBUTION ARE
<br />INSTALLED PER SPECIFICATIONS OR INDUSTRY STANDARDS.
<br />1.04 NOTIFICATION FOR TESTING AND BALANCING WORK TO BEGIN
<br />A. THE MECHANICAL CONTRACTOR SHALL NOTIFY THE TEST AND BALANCE AGENCY IN WRITING WITH A COPY TO
<br />VERIZON WIRELESS AND THE ARCHITECT WHEN ALL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS
<br />ARE COMPLETE AND READY FOR TESTING AND BALANCING. THE MECHANICAL CONTRACTOR SHALL ATTEST
<br />THAT HE HAS COMPLETED ALL ITEMS.
<br />B. THIS INSPECTION SHALL ESTABLISH THAT THE SYSTEMS MEET THE BASIC REQUIREMENTS FOR TESTING AND
<br />BALANCING. SHOULD THE INSPECTION REVEAL THE NOTIFICATION TO HAVE BEEN PREMATURE, ALL COSTS FOR
<br />THE INSPECTION AND WORK PREVIOUSLY ACCOMPLISHED BY THE TEST AND BALANCE AGENCY SHALL BE PAID
<br />FOR BY THE MECHANICAL CONTRACTOR. FURTHERMORE, SUCH ITEMS THAT ARE NOT READY FOR TESTING
<br />AND BALANCING SHALL BE COMPLETED AND PLACED IN OPERATIONAL READINESS BEFORE TESTING AND
<br />BALANCING SERVICES SHALL AGAIN BE REQUESTED.
<br />AIR BALANCING AND TESTING
<br />15A.4 TEMPERATURE CONTROLS
<br />GENERAL REQUIREMENTS
<br />SHOPPING CENTER BMS CONTRACTOR, AS PART OF THIS SCOPE OF WORK, SHALL PROVIDE A SYSTEM OF
<br />TEMPERATURE CONTROLS INCLUDING THERMOSTATS, CONTROL PANELS, TIME SWITCHES, OVERRIDE TIMERS,
<br />DAMPER MOTORS AND RELAYS REQUIRED TO PROVIDE THE DESIRED SEQUENCE OF OPERATION. PROVIDE
<br />INTEGRATED WIRING DIAGRAMS SHOWING INTERCONNECTIONS BETWEEN FIELD-INSTALLED EQUIPMENT AND
<br />PACKAGE WIRING FURNISHED WITH THE HVAC EQUIPMENT.
<br />PER MALL STANDARDS, EACH RTU SHALL BE MONITORED AND CONTROLLED BY SHOPPING CENTER'S BMS.A
<br />MINIMUM OF ONE CONTROLLER TO BE INSTALLED IN EACH HVAC UNIT. EACH CONTROLLER TO HAVE AS A MINIMUM,
<br />THE FOLLOWING POINTS:
<br />• FAN DISCHARGE TEMP
<br />• MIXED AIR TEMP
<br />• SPACE TEMP
<br />• FLOW STATUS SWITCH
<br />• COOLING CIRCUIT
<br />• HEATING CIRCUIT
<br />• FAN START/STOP
<br />• ECONOMIZER MODULATION
<br />• OUTDOOR AIR TEMP
<br />DIVISION 15 CONTRACTOR TO PROVIDE TEMPORARY HONEYWELL OR EQUAL ELECTRONIC NON-PROGRAMMABLE
<br />TYPE THERMOSTAT, MANUAL CHANGEOVER, SWITCHING SUB-BASE, MULTI-STAGE AS REQUIRED TO MATCH UNIT
<br />COOLING/HEATING STAGING. LOW-VOLTAGE TYPE NON-PROGRAMMABLE HEATING AND COOLING THERMOSTATS
<br />SHALL BE HONEYWELL SERIES T FOCUSPRO 5000 OR EQUAL WITH INTEGRAL SUB-BASE. INSTALL THERMOSTATS AT
<br />48" AFF TO MEET ADA REQUIREMENTS UNLESS OTHERWISE NOTED ON THE PLANS.
<br />EQUIPMENT SUPPLIER SHALL PROVIDE SUPERVISION AND ON-JOB CHECKOUT SERVICE AS REQUIRED TO ENSURE
<br />THAT INSTALLATION MEETS REQUIREMENTS OF THE SPECIFICATION.
<br />AFTER COMPLETION OF INSTALLATION, SHOPPING CENTER BMS CONTRACTOR SHALL CALIBRATE & ADJUST ALL
<br />THERMOSTATS, CONTROL VALVES, MOTORS & OTHER EQUIPMENT PROVIDED AS PART OF THE TEMPERATURE
<br />CONTROL SYSTEM. HE SHALL THEN PLACE IN COMPLETE OPERATING CONDITION SUBJECT TO THE APPROVAL OF
<br />THE ENGINEER.
<br />TEMPERATURE CONTROLS SHALL BE CALIBRATED TO +/- 2-DEG F.
<br />TEMPERATURE CONTROLS SHALL ALLOW AN OCCUPANT ADJUSTMENT RANGE OF +/- 2-DEG F.
<br />TEMPERATURE CONTROLS SHALL BE LABELED WITH ASSOCIATED HVAC UNIT AND INSTALLED PER MANUFACTURER'S
<br />SPECIFICATIONS INCLUDING LOCATING THE UNITS ON SURFACES THAT ARE NOT EXPECTED TO EXPERIENCE
<br />RAPIDLY CHANGING TEMPERATURES.
<br />EQUIPMENT
<br />ALL AUTOMATIC CONTROL VALVES AND DAMPERS SHALL BE FURNISHED AND INSTALLED BY THE MECHANICAL
<br />CONTRACTOR.
<br />MANUFACTURERS AND MODEL NUMBERS ARE LISTED FOR REFERENCE AS TO QUALITY AND FEATURES REQUIRED
<br />FOR THE CONTROL DEVICES. PROVIDE CONTROL DEVICES AS REQUIRE BY SHOPPING CENTER BMS.
<br />15A. 5 SEQUENCE OF OPERATION
<br />HVAC UNITS (EXCLUDING COMPUTER ROOM UNIT)
<br />SHALL SWITCH TO OCCUPIED MODE ONE HOUR BEFORE DOOR OPEN TIME AND SHALL SWITCH TO UNOCCUPIED MODE
<br />ONE HOUR AFTER DOOR CLOSE TIME.
<br />INTERIOR RELATIVE HUMIDITY IS LIMITED BY DESIGN TO LESS THAN 50% RELATIVE HUMIDITY TO COMPLY WITH
<br />VERIZON WIRELESS OPR.
<br />SETPOINTS
<br />OCCUPIED SETPOINTS SHALL BE:
<br />72ºF -COOLING
<br />68ºF –HEATING
<br />LOCALLY CHANGING THE HEATING/COOLING SETPOINT SHALL ENABLE A 120 MINUTES SETPOINT (± 2*F ADJUSTMENT)
<br />OVERRIDE.
<br />UNOCCUPIED SETPOINTS SHALL BE:
<br />80ºF –COOLING
<br />60ºF -HEATING
<br />ECONOMIZATION –IF EQUIPMENT IS SO EQUIPPED
<br />ECONOMIZER CONTROL SHALL COMPARE OUTDOOR AIR ENTHALPY TO RETURN AIRE ENTHALPY AND SELECT THE
<br />LOWER ENTHALPY (RETURN OR OUTDOOR AIR) FOR COOLING.
<br />IF OUTDOOR AIR IS SELECTED FOR COOLING, THE OUTDOOR AIR DAMPER SHALL BE PROPORTIONED OPEN TO
<br />MAINTAIN BETWEEN 50 DEG. F. AND 56 DEG. F. SUPPLY AIR DISCHARGE TEMPERATURE.
<br />DEMAND VENTILATION –IF EQUIPMENT IS SO EQUIPPED
<br />PER ASHRAE 90.1, DURING UNOCCUPIED HOURS THE OUTDOOR AIR DAMPERS SHALL BE SET TO CLOSED. DURING
<br />OCCUPIED HOURS, THE OUTDOOR AIR DAMPER SHALL OPEN TO THE LOW MINIMUM POSITION AS PROGRAMMED INTO
<br />THE RTU PRODIGY CONTROLLER. PRODIGY PROGRAMMING SHALL BE ESTABLISHED BY THE TEST & BALANCE
<br />CONTRACTOR TO ACHIEVE THE LOW MINIMUM OUTSIDE AIRFLOW INDICATED IN THE HVAC UNIT SCHEDULE DURING
<br />BOTH LOW SPEED AND HIGH SPEED FAN OPERATION. IF INDOOR CO2 LEVELS RISE ABOVE 1050 PPM (BASED ON AN
<br />OUTDOOR BASELINE CO2 LEVEL OF 400 PPM AND 650 PPM DIFFERENTIAL -ADJUSTABLE) THE OUTDOOR AIR DAMPER
<br />SHALL MODULATE TOWARD THE HIGH MINIMUM POSITION AS PROGRAMMED INTO THE RTU PRODIGY CONTROLLER.
<br />OUTDOOR AIR DAMPER SHALL BE AT HIGH MINIMUM POSITION AT CO2 LEVELS OF 1150 PPM. PRODIGY
<br />PROGRAMMING SHALL BE ESTABLISHED BY THE TEST AND BALANCE CONTRACTOR TO ACHIEVE THE HIGH MINIMUM
<br />OUTSIDE AIRFLOW INDICATED IN THE HVAC UNIT SCHEDULE DURING HIGH FAN SPEED OPERATION.
<br />EMS CO2 LEVEL ALARM
<br />THE EMS SHALL ALARM IF INDOOR CO2 LEVEL EXCEEDS 1400 PPM (ADJUSTABLE) FOR A PERIOD OF 120 MINUTES
<br />(ADJUSTABLE). ALARM SHALL CLEAR WHEN THE INDOOR CO2 LEVEL DROPS BELOW 1300 PPM (ADJUSTABLE) FOR 5
<br />MINUTES (ADJUSTABLE).
<br />INDOOR BLOWER
<br />OCCUPIED –THE BLOWER SHALL OPERATE CONTINUOUSLY
<br />UNOCCUPIED -THE BLOWER SHALL OPERATE ON DEMAND, HEATING/COOLING
<br />RUNTIMES
<br />ACCUMULATED RUNTIMES FOR THE COMPRESSOR AND INDOOR BLOWER SHALL BE PROVIDED.
<br />OUTDOOR AIR LOCKOUT
<br />WHEN TWO OR MORE UNITS SERVE A COMMON AREA (SALES FLOOR ZONE) THE OPERATING MODE
<br />(HEATING/COOLING) SHALL BE SET BY THE OUTDOOR AIR TEMPERATURE. WHEN THE OUTSIDE AIR TEMPERATURE IS
<br />GREATER THAN 50°F (ADJ) THE OPERATING MODE SHALL BE COOLING. WHEN THE OUTSIDE AIR TEMPERATURE IS
<br />LESS THAN 50°F (ADJ) THE OPERATING MODE SHALL BE HEATING.
<br />PROVIDE FREEZESTAT IN THE SUPPLY AIR DUCT TO SHUT DOWN THE SUPPLY FAN AND CLOSE THE OUTDOOR AIR
<br />DAMPER IF TEMPERATURE IN THE SUPPLY DUCT DROPS BELOW 40-DEGREES FAHRENHEIT.
<br />RESTROOM AND JANITOR CLOSET EXHAUST FAN
<br />RESTROOM / JANITOR CLOSET EXHAUST FAN (EF-1) SHALL BE INTERLOCKED TO TIMECLOCK TO ALLOW FOR
<br />CONTINUOUS OPERATION DURING OCCUPIED HOURS AND SHALL SHUT DOWN DURING UNOCCUPIED HOURS.
<br />TELCO SPLIT AC UNIT (CRU-1 / ACCU-1)
<br />SYSTEM SHALL BE AVAILABLE FOR OPERATION 24/7. UPON A RISE IN SPACE TEMPERATURE SETPOINT OF 78
<br />DEGREES F (ADJUSTABLE), CRU-1 / ACCU-1 SHALL ENERGIZE AND CYCLE COMPRESSOR AS REQUIRED TO MAINTAIN
<br />SPACE TEMPERATURE.
<br />UPON A DROP IN SPACE TEMPERATURE BELOW SETPOINT, CRU-1 / ACCU-1 SHALL DE-ENERGIZE
<br />HEAT PUMP AC UNIT (FCU-1 / HP-1)
<br />REFERENCE THE HEAT PUMP UNIT CONTROL MATRIX FOR SEQUENCE OF OPERATIONS.
<br />HVAC TEMPERATURE CONTROLS
<br />Mechanical and Electrical Engineers
<br />Lilker Associates
<br />1001 Avenue of the Americas
<br />New York, NY 10018
<br />tel 212.695.1000
<br />fax 212.695.1299
<br />www.lilker.com
<br />Kenneth A. Gruskin AIA
<br />No. Date Description
<br />Consultant:
<br />Checked By:
<br />Drawn By:
<br />Job Address:
<br />Drawing Title:
<br />Revision Issue:
<br />Professional Seal:
<br />Drawing Number:
<br />2022 Gruskin Architecture + Design, P.C.c
<br />This document and the ideas and designs incorporated
<br />herein, as an instrument of professional service, is the
<br />property of GRUSKIN ARCHITECTURE + DESIGN, P.C.,
<br />and is not to be used in whole or in part for any other
<br />project without the written authorization of GRUSKIN
<br />ARCHITECTURE + DESIGN, P.C.
<br />North
<br />Arrow:
<br />Job Name and Number:
<br />Date Issued For
<br />All Rights Reserved
<br />Client:
<br />Landlord:
<br />Permit:
<br />Bid:
<br />Construction:
<br />0006261
<br />AR91629
<br />5421
<br />9613
<br />39209
<br />10635
<br />2537
<br />11016
<br />5734
<br />ARC 2596
<br />4674
<br />2666
<br />AI 09999
<br />2796
<br />0401 011223
<br />2572
<br />17680
<br />RA-015432-B
<br />025528-1 NY
<br />TX
<br />VA
<br />VT
<br />MA
<br />MT
<br />RI
<br />PA
<br />NY
<br />NJ
<br />NH
<br />MD
<br />LA
<br />ME
<br />KS
<br />FL
<br />DE
<br />CT
<br />AZ
<br />AL
<br />C-1967WY
<br />RA011075GA
<br />AR10400066IN
<br />C-29898CA
<br />NM 004168
<br />ARC-400347CO
<br />HI AR 11489
<br />PR 19965
<br />OR 4899
<br />SC 6834
<br />NC 9961
<br />13761OH
<br />05713IA
<br />WV 3727
<br />IL 001-019152
<br />UT 5881358-0301
<br />ID AR-984459
<br />1301052379MI
<br />ARC100723DC
<br />WI 9900-005MN44326
<br />A-3547NE
<br />3811AR
<br />5967KY 101374TN
<br />MS 3860
<br />1666ND
<br />A-2005029740MO
<br />a4895OK
<br />NV 5521
<br />WA 10344
<br />13167AK
<br />SD 11532
<br />C:
<br />\
<br />R
<br />e
<br />v
<br />i
<br />t
<br />
<br />L
<br />o
<br />c
<br />a
<br />l
<br />
<br />F
<br />i
<br />l
<br />e
<br />s
<br />\
<br />2
<br />4
<br />0
<br />0
<br />1
<br />3
<br />0
<br />8
<br />_
<br />V
<br />E
<br />R
<br />I
<br />Z
<br />O
<br />N
<br />_
<br />S
<br />a
<br />n
<br />t
<br />a
<br />
<br />A
<br />n
<br />a
<br />_
<br />C
<br />A
<br />_
<br />ME
<br />C
<br />H
<br />A
<br />N
<br />I
<br />C
<br />A
<br />L
<br />_
<br />v
<br />2
<br />3
<br />_
<br />r
<br />t
<br />r
<br />o
<br />v
<br />a
<br />t
<br />o
<br />T
<br />7
<br />V
<br />P
<br />K
<br />.
<br />r
<br />v
<br />t
<br />2023-0069
<br />Proposed
<br />Store Design
<br />for: VERIZON
<br />Metro Pointe
<br />3500 South Bristol Street
<br />Suite 100
<br />Santa Ana, CA 92704
<br />3/15/2024
<br />3/15/2024
<br />HVAC SPECIFICATIONS
<br />M.0.1
<br />BS
<br />RT
<br />34 OF 81
<br />3500 S Bristol St Unit# 100 -
<br />101119098, 20182666 &
<br />401390437/11/2024
|