CITY OF SANTA ANA <br />SPECIFICATIONS <br />PROJECT NO.: XX-XXXX <br />PROJECT TITLE <br /> <br />39 <br />The asphalt concrete surfacing and underlying base materials shall be pulverized such <br />that 100 percent of the material will pass a two-inch sieve and a minimum of 90-percent <br />will pass a one and one-half-inch sieve. All materials other than rock and pulverized <br />asphalt concrete shall be broken up such that these materials will pass a one inch sieve. <br />The pulverized material shall be shaped and rolled to the specified cross sections. The <br />Engineer shall check and verify the conformance of the material to the lines, grade, and <br />elevation as shown on the plans, prior to beginning cement treatment. <br />Trimming and disposal of excess material, if required, will be performed on the intimate <br />mixture of pulverized asphalt concrete, base materials and subgrade soil prior to cement <br />treatment. <br />Portland cement shall be Type II Modified, conforming to the requirements of Section <br />201-1.2.1 "Portland Cement,” of the Standard Specifications. Pozzolanic material shall <br />not be substituted for Portland Cement. <br />Water shall conform to the provisions in Section 201-1.2.3, "Water,” of the Standard <br />Specifications. <br />Cement Application <br />Cement shall be uniformly spread by mechanical equipment at a spread rate necessary to <br />meet the cement content specified on the plans for the various areas to be treated. <br />The cement content shall be 5% (five-percent) based on the dry unit weight of the <br />pulverized material. The dry unit weight of the pulverized material shall be determined <br />by California Test 312 (Design and Testing of Classes A and B Cement Treated <br />bases). The Engineer may order an increase or decrease in the specified cement content <br />when conditions warrant such action. For cost estimate purposes, use 130 pounds/cubic <br />feet for the dry unit weight of pulverized material. <br />The quantity of Portland cement added to the pulverized material for cement treatment <br />shall meet the following requirements when evaluated in conformance with the <br />provisions in Section 400-1.4, Statistical Testing, of the Standard Specifications. <br />1. The average of the test results for the cement content from each sampling station <br />shall vary no more than 0.6-percent under not more than 1.0-percent over the <br />specified cement content. <br />2. The moving average of the test results shall be at least the specified cement <br />content. <br />Cement shall not be spread upon the prepared material more than one hour prior to the <br />mixing operation. No traffic other than the mixing equipment shall be allowed to pass <br />over the spread cement until the mixing operation is completed. <br />505 E Central Ave <br />#B11/6/2024