CITY OF SANTA ANA <br />SPECIFICATIONS <br />PROJECT NO.: XX-XXXX <br />PROJECT TITLE <br /> <br />119 <br />N. RECORD DRAWINGS <br />1. All record drawings shall be “redlined” with any as-built information including <br />the items in this section. Dimension from two permanent points of reference <br />(road intersections, etc.) locations of the following items: <br />a. Connection to existing water lines. <br />b. Gate valves. <br />c. Routing of sprinkler lines. <br />d. Sprinkler control valves. <br />e. Quick couplers. <br />f. Routing of control wiring. <br />2. Provide and mount a chart of the sprinkler controller including a cover. This shall <br />be a plot plan of areas by controller and show buildings, service drive, walks, <br />walls, sprinkler heads and valves. Number all valves to match operation schedule <br />and drawings. Make a photostatic reduction print of this plan to a size that will fit <br />into controller cover and mount in plastic, hermetically sealed, and securel y fasten <br />to cover. All work shall be satisfactory to Engineer. The chart shall be colored <br />with a different color for each controller station. <br />3. Before the date of the final inspection, the Contractor shall deliver the corrected <br />and completed redlines to the Engineer. Delivery of the redlines will not relieve <br />the Contractor of the responsibility of furnishing required information that may be <br />omitted from the prints. <br />O. TURN OVER ITEMS <br />1. Equipment: Supply and deliver to the Owner the following equipment and <br />information: <br />a. Six (6) coupler valve keys with hose swivel ell. <br />b. Two (2) sets of various special wrenches or tools that may be required for <br />adjustment of sprinkler heads or equipment. <br />2. Maintenance Instruction: Two (2) hard cover binders with 3 rings containing <br />manufacturer's catalog sheets of each and every material and equipment installed <br />under this contract, including guarantee statement. Maintenance information and <br />diagrammatic equipment drawings shall be included when available. <br />P. COMPLETION CLEANING <br />Upon completion of work, the Contractor shall remove excess materials, rubbish, <br />debris, etc., and his construction and installation equipment from the premises. <br />505 E Central Ave <br />#B11/6/2024