January 17, 2019
<br />Page 1
<br />Approximate Start/End Dates: October 2017 — March 2018
<br />Brief Description of Work: Traffic Signal Installation/Modifications at multiple intersections including new traffic signal poles and
<br />vehiculadpedestrian traffic gear, new controller cabinets with new foundations, new service pedestals with new foundations, battery
<br />backup installation, video detection system installation. safety lighting installation, emergency vehicle preemption installation, new ada
<br />compliant curb ramps, new striping and markings, loop detection systems, new underground conduit and pullbox installation. SCE
<br />underground substructures, concretelasphaltimpovements. etc.
<br />City of Orange
<br />Left Turn Phasing Signal Modification I Chapman Avenue & Cannon Street #HSIPL 5073(079) SP-3868
<br />Left Turn Phasing Signal Modification I Batavia Street & Collins Avenue #HSIPL 5073(081) SP•3870
<br />Original Contract Amount: $599,999.00
<br />Final Contract Amount: $608,424.00
<br />Contact: Medel Llanes
<br />Main: 714.744,5535
<br />Email: mllanes@cityoforange.org
<br />Approximate Start/End Dates: April 2018 — October 2018
<br />Brief Description of Work: Traffic Signal InstallationlModifications including new traffic signal poles and vehicular/pedestrian traffic gear,
<br />new controller cabinets with new foundations, new service pedestals with new foundations, battery backup installation, video detection
<br />system installation, safety lighting installation, emergency vehicle preemption installation, new ada compliant curb ramps, new striping
<br />and markings. loop detection systems. CCTV, new underground conduit and pullbox installation. SCE underground substructures,
<br />concretelaspha# improvements, etc.
<br />City of Orange
<br />Tustin Street and Vanowen Avenue Traffic Signal Modification #SP-3927
<br />Original Contract Amount: $355,156,00
<br />Final Contract Amount: $386,200.60
<br />Contact: Medel Llanes
<br />Main: 714.744.5535
<br />Email: mllanes@cityoforange.org
<br />Approximate Start/End Dates. August 2016 — October 2016
<br />Brief Description of Work: Traffic Signal InstallationlModifications including new traffic signal poles and vehiculadpedestrian traffic gear,
<br />new controller cabinets with new foundations, new service pedestals with new foundations, battery backup installation, video detection
<br />system installation, safety lighting installation, emergency vehicle preemption installation, new ada compliant curb ramps, new striping
<br />and markings, loop detection systems. CCTV, new underground conduit and pullbox installation. SCE underground substructures,
<br />concretelasphalt improvements, etc.
<br />City of Santa An
<br />Traffic Signal Modifications on:
<br />17t" Street at English Street I MacArthur Boulevard at Plaza Drive #15.6834
<br />Edinger Avenue at Sullivan Street I Westminster Avenue at Clinton Street #15.6834
<br />Original Contract Amount: $865,319.00
<br />Final Contract Amount. $872.755.00
<br />Contact: Michael Ortiz
<br />Main: 714.647,5624
<br />Email, MOrtiz@santa-ana.org
<br />Approximate Start%End Dates: January 2017 — December 2017
<br />Brief Description of Work: Traffic Signal Installation.%Modifications at various intersections including new traffic signal poles and
<br />vehiculadpedestrian traffic gear, new controller cabinets with new foundations, new service pedestals with new foundations, battery
<br />backup installation video detection system installation safety lighting installation. emergency vehicle preemption installation, new ada
<br />compliant curb ramps, new striping and markings. CCTV loop detection systems, new underground conduit and pullbox installation. SCE
<br />underground substructures. concrete/asphalt improvements, etc.
<br />City of Santa Ana
<br />Safe Routes to School Enhancements for Heninger Elementary #16.6870
<br />Original Contract Amount: $417,341.50