| Proposal, and shall include full compensation for doing all work, including furnishing all materials, labor, 
<br />equipment, tools, and incidentals as required and no additional compensation will be allowed therefore. 
<br />Item No. 4 - PCC Curb & Gutter (A-2-8) 
<br />The work under this item consists of grading, compacting subgrade, and constructing PCC Curb & Gutter 
<br />and shall be in accordance with the provisions of Section 301-1, "Subgrade Preparation," and Section 303-5, 
<br />"Concrete Curbs, Walks, Gutters, Cross Gutters, Alley Intersections, Access Ramps, and Driveways" and 
<br />any City Standard Specifications, plans, and/or any City's Special Provisions/Contract Documents provided 
<br />by the City for each Task Order. 
<br />Payment for PCC Curb & Gutter (A-2-8) shall be at the contract unit price bid per Linear Foot as listed 
<br />in the Fee Proposal, and shall include full compensation for doing all work, including furnishing all 
<br />materials, labor, equipment, tools, and incidentals as required and no additional compensation will be 
<br />allowed therefore. 
<br />Item No. 5- Furnish and Install New #6 Pull Box 
<br />The work under this item for Furnish and Install New #6 Pull Box shall be in accordance with the latest 
<br />CA NMTCD, Caltrans and any City Standard Specifications, plans, and/or any City's Special 
<br />Provisions/Contract Documents to be provided for each Task Order Work. The assumed material for 
<br />placement shall be concrete and any removal of an existing pull box shall be included in the price paid to 
<br />furnish and install a new pull box and no additional payment will be allowed therefore. 
<br />Payment for Furnish and Install New #6 Pull Box shall be at the contract unit price paid per Each as 
<br />listed in the Fee Proposal, and shall include full compensation for doing all work, including furnishing all 
<br />materials, labor, equipment, tools, and incidentals as required and no additional compensation will be 
<br />allowed therefore. 
<br />Item No. 6 - Adjust Manhole to Finished Grade 
<br />Payment for Adjust Manhole to Finished Grade shall be at the contract unit price bid per Each as listed 
<br />in the Fee Proposal, and shall include full compensation for doing all work, including furnishing all 
<br />materials, labor, equipment, tools, and incidentals as required and no additional compensation will be 
<br />allowed therefore. 
<br />Item No. 7- Catch Basin (Type `B," W=101) 
<br />The work under this item consists of grading, compacting subgrade, and constructing Catch Basin and shall 
<br />be in accordance with the provisions of Section 301-1, "Subgrade Preparation," and Section 303-1, "Concrete 
<br />Structures" and any City Standard Specifications, plans, and/or any City's Special Provisions/Contract 
<br />Documents provided by the City for each Task Order. 
<br />Payment for Catch Basin (Type `B," W=10') shall be at the contract unit price paid per Each as listed in 
<br />the Fee Proposal, and shall include full compensation for doing all work, including removal or replacement 
<br />of existing catch basins and/or other appurtenances, including fuuishing all materials, labor, equipment, 
<br />tools, and incidentals as required to construct a new catch basin, soil preparation and compaction, and no 
<br />additional compensation will be allowed therefore. 
<br />City of Santa Ana RFP 20-106 