Laserfiche WebLink
<br />Page 2 of 5 <br />PM/RE and Contract Administrator Costs tasks that required a significant increase in hour allocation to <br />ensure quality of project delivery include the following: <br />1. Issue w/ Project Sequencing (Plans vs Spec vs Actual) – meetings & discussions with designer <br />2. Obtaining Additional Caltrans Rider Permit for City and Coordinating Contractor Procurement of <br />Double Permit <br />3. Establishing Relationship with City of Tustin and Obtaining Tustin Grading Permit <br />4. SCE Service to SA-7 – Coordination efforts of design issue. SCE design and coordination had not <br />been started. CM team took on this role. <br />5. Project Specification not Reflecting Caltrans Spec and Caltrans Desires – i.e. casing requirements <br />and welding requirements <br />6. Significant Number of Submittal Resubmittals (some resubmitted 4 times) <br />7. Contractor Baseline Schedule Review Sbmtl 004 – Contractor submitted 5 times and still had <br />issues. Extensive time reviewing and meeting with Contractor <br />8. Contractor Jack & Bore Shoring Review – no assistance from designer, contractor plan unusually <br />lacking <br />9. Contractor Issues with Procuring Casing Pipe – Contractor identified over 6 different pipe for <br />submission which included additional submissions for welding. <br />10. Write-up of CCO-001 – extensive write-up, completed Background and CCO versus “assisting with <br />CCO” per original scope. <br />11. RFI-034/PCO-012 SA-7 Automation and work of Enterprise Automated (EA) – Unusually time <br />consuming RFI which is developing into a CCO. <br />12. Preparation of budget and coordination of staff for additional scope added by City with Amendment <br />No. 01 <br />13. Issues with the jack & bore ground monitoring. <br />CWA Rate: As identified in meetings with the City and in BergCM’s Letter to the City dated August 9, 2022, <br />a CWA Rate was established for our Inspectors to be in compliance with the City’s CWA. It was not known, <br />by BergCM or the City, at the time of contract execution that the CWA would apply to CM staff. To-date, <br />through Nov 30, 2022, this rate increase represents roughly $20,000 to-date. These are included in the <br />Inspection estimate above. <br />Submittal Reviews – Unplanned Costs: ON-SITE Conducted submittal reviews in March 2022 that was <br />not allocated in original budget. <br />Additional Admin Reviews by ON-SITE Technical To-Date: ($ 4,130.00) <br />Amendment No. 01 – Unplanned Costs: All of the Amendment No. 01 costs are attached herein to this <br />Letter. The additional unplanned costs that were utilized to date include the following: <br />Specialty Inspection by ON-SITE Technical To-Date: ($ 15,370.25) <br />Specialty Inspection by RMA Group To-Date: ($ 960.00) <br />Scheduling Services for Contingency Plans and Shadow Schedule: ($ 6,280.07) <br />Underestimated Working Days in Original Estimate: In our original budget, 360 working days were used <br />for the Construction periods (Phase 1 and Phase 2). This should have been corrected in a negotiation <br />period, as the actual working days is roughly 390 working days. If project special issues and unplanned <br />costs had not occurred, the Contingency could have been used to account for this error. However, our <br />attached spread sheet shows actual hours per month for the duration of the project according to the <br />Contractor’s baseline schedule. This represents a difference of $69,519.75, for actual costs (390 WD) <br />versus proposed/actual (360 WD). <br />