<br />AGREEMENT 1-2354 <br />Exhibit A <br /> <br />Task.5.04 Bristol Street Viaduct <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />prefemd design by the end of month six (6), the CONSULTANT will develop the bridge <br />general plans for Bristol Street Viaduct within Blistol Street Segment, as defined elsewhere <br />in this document. The bridge general plans consist of plan and elevation views, vertical <br />profile, bridge spans and cQlumn locations, blidge typical sections, showing in general the <br />structure cross-sectional geometry, structure type and depth, column type and size, and <br />foundation type. <br />. This task will be completed within months 6-18. <br /> <br />Task 5.05 Costa Mesa Viaduct <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />preferred design by the end of month six (6), the CONSULTANT will develop bridge general <br />plans for Costa Mesa Viaduct within Costa Mesa Segment, as defined elsewhere in this <br />document. The bridge general plans are as described above in the clarification of Schedul& bf <br />Values Task 5.04. <br />. This task will be completed within months 6-18. <br /> <br />Task 5.06 Irvine Business Center/Airport Viaduct <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />preferred design by the end of month six (6), the CONSULTANT will develop the bridge <br />general plans for Irvine Business Center! Airport Viaduct within Irvine Business <br />Center/Airport Viaduct Segment, as defined elsewhere in this document. The bridge general <br />plans are as describ"d above in the clarification of Schedule of Values Task 5.04. <br />0 This task will be completed within months 6-18. <br /> <br />T~sk 5.07 San Diego Creek Viaduct <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />preferred design by the end of month six (6), the CONSULT ANT will develop the bridge <br />general plans for San Diego Creek Viaduct within San Diego Creek Corridor, as defined <br />elsewhere in this' document. The bridge general plans are as described ~bove in the <br />clarification of Schedule of Values Task 5.04. <br />. This task will be completed within months 6-18. <br /> <br />Task 5.08 Irvine SpectrumlTransportation Center Viaduct <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />preferred design by the end of month six (6), the CONSULTANT will develop the bridge <br />general plans for Irvine Spectrum /Transportation Center Viaduct within Irvine <br />Spectrum/Transportation Center Segment, as defined elsewhere in this document. The bridge <br />general plans are as described above in the Clarification of Schedule of Values Task 5.04. <br />. This task will be completed within months 6-18. <br /> <br />Task 5.09 Stations <br />. Subsequent to Schedule of Values Tasks 5.02 and 5.03, and after the Authority selects a <br />preferred design by the end of month six (6), the CONSULTANT will develop the general <br />structural plans for the preferred station type(s) to be used within the six (6) segments, as <br /> <br />24 <br /> <br /> <br />-~--;- <br /> <br />-' <br />~_... <br /> <br />(\'--/\ <br /> <br />