c) Close Elm Street at Bristol Street on a
<br /> trial basis.
<br />
<br />2)
<br />
<br />Staff be directed to close Elm Street as rapidly as
<br />possible with temporary barricades; that within 90
<br />days a plan be submitted to the Council and residents
<br />with recommendations for permanent closure, and that
<br />the same be placed in the 1977-78 Budget, and
<br />
<br />3)
<br />
<br />Staff and Council continue efforts to find a final
<br />solution to the widening of the bridge across the
<br />Santiago Creek at Bristol Street. CA
<br /> CA
<br />
<br />29.8
<br />29.1
<br />
<br />AGENDA ORDER The request of Irma
<br />BID AWARD - PROJECT 4025 Ortiz, 614 North Bewley,
<br /> to hear Agenda Item #88,
<br /> Award of Bid on Project
<br />4025 - C-5-F Storm Drain, Phases I, II, III and Add-on
<br />Alternate Phase IV prior to its place on the Agenda was granted.
<br />
<br />BID AWARD - PROJECT 4025 On the unanimously
<br />C-5-F STORM DRAIN, PHASES I, carried 5:0 motion of
<br />II, III & ALTERNATE IV - AWARDED Councilman Ward,
<br /> seconded by Councilman
<br />Yamamoto, the contract on Project 4025, C-5-F Storm Drain,
<br />Phases I, II, III, and Add-on Alternate Phase IV, was awarded
<br />to Steve Bubalo Construction Co., Reseda, on basis of lowest
<br />responsible and best bidder, for a total bid of $936,085.
<br />
<br />A subsequent motion, unanimously 5:0 carried, made by Council-
<br />man Bricken, seconded by Councilman Yamamoto, referred the
<br />letter from the Storm Drain Committee to the City Manager for
<br />follow-up to the requests contained in the letter. An amend-
<br />ment to that motion made by Councilman Bricken, seconded by
<br />Councilman Ortiz, directed Staff to schedule the meetings
<br />regarding use of over-allocated money in accordance with
<br />Federal guidelines, with at least one meeting to be held in
<br />Santa Anita. The second meeting will be held there also, if
<br />possible under Federal regulations.
<br />
<br />Prior to Council action, Assistant City Manager Ronald Wolford
<br />stated that the first Phase of the C-5-F storm drain was con-
<br />structed in 1961; that the City expended $95,000 to bring it
<br />over as far as Newhope; in 1966 Phase II cost $215,000; the
<br />third Phase, Santa Anita Park Lateral, easterly at Harbor in
<br />1970 cost $32,000; and that we are presently at the last Phase
<br />of the C-5-F Project; that this will be a 66-inch pipe, and
<br />the project is funded through the Community Development Second
<br />Year Program with a large grant from the Orange County Flood
<br />Control District; that there were nine bidders, and bids were
<br />opened on January 20, 1977; and that the low bid was $936,085.
<br />
<br />Several persons spoke in favor of the installation of the storm
<br />drain:
<br />
<br />Fernando Barona, Storm Drain Committee Representative,
<br /> 705 N. Gunther
<br />Lydia Morales, 601 North Figueroa
<br />Catherine Griffith, 705 North Bewley
<br />Irma Ortiz, 614 North Bewley
<br />
<br />The proponents requested a copy of the contract by February 8,
<br />a monthly status report of the project to be furnished the
<br />last day of each month, an informational meeting with representa-
<br />tives of the Contractor and Department of Public Works, and that
<br />both Housing and Community Development meetings, concerning the
<br />over-allocated money for the construction of the storm drain, be
<br />held in Santa Anita. CA 89
<br /> CA 70 CA 140.20
<br />
<br />CITY COUNCIL MINUTES 55 FEBRUARY 7, 1977
<br />