ARTICLE 2 <br />2. STATEMENT OF THE WORK - PROJECT IMPLEMENTATION AGREEMENT <br />DOCUMENTS <br />2.1 This Agreement represents the entire agreement between the City and Program <br />Manager with regard to the renovations at the Project Site, and supersedes all prior negotiations, <br />representations or agreements. This Agreement shall not be superseded by any provisions of the <br />documents for construction and may be amended only by written instrument signed by both the <br />City and Program Manager. <br />2.2 Program Manager shall (i) provide general administration of the Agreement, (ii) <br />interpret the requirements of the Project Documents, (iii) manage and supervise its Consultants and <br />design professionals and the processing of plans and specifications for the Project; (iv) manage as <br />the City's representative the putting out for bid of all components of construction for the Project, <br />including assuring all competitive bidding requirements applicable to the Project pursuant to City <br />Charter Section 421 are complied with; (v) manage and supervise the services provided by its <br />Construction Manager representative, for the purpose of causing the Project to be completed within <br />the Project Budget and in accordance with the Project Documents. <br />2.3 Program Manager agrees to furnish the services set forth herein and agrees to furnish <br />efficient business administration and management, and cause the Project to be completed in the <br />most expeditious and economical manner consistent with the interests of the City. Program <br />Manager represents that it possesses any and all licenses necessary to discharge its obligations <br />under this Agreement. <br />2.4 Upon approval of this Agreement, Program Manager shall cause its Consultants to <br />prepare and/or modify all further necessary drawings, plans and specifications necessary to <br />construct the Project within the Project Budget. It is understood and agreed that as work proceeds <br />on the Project, certain clarifications and modifications may have to be made, including adjustments <br />in plans, circulation, site work and elevations, as well as detailing of materials, colors and finishes. <br />All scope of work as set forth in the Drawings and Specifications shall be subject to mutual <br />approval by the parties. The Designated City Representative is hereby authorized and directed to <br />review and approve all of the Project Documents as set forth below, provided they substantially <br />conform to the scope of the Project as set forth in Exhibit A and Project Documents, as well as later <br />developed drawings, provided further except as authorized in writing by the City, under no <br />circumstances shall the cost of the Project exceed the Project Budget. <br />ARTICLE 3 <br />3. PROGRAM MANAGER'S RESPONSIBILITIES <br />3.1 Program Manager shall be responsible to cause to be delivered to the City in a <br />timely manner all design work necessary for the implementation of the Project, to assure that all <br />construction work is competitively bid in accordance with bid documents approved by the City and <br />3 <br />