CITY OF SANTA ANA <br />APPENDIX I <br />PROJECT NO.: XX-XXXX <br />PROJECT TITLE <br />The pipe and fittings shall be lowered into the trench. Do not throw the pipe or fittings into <br />the trench. <br />If it is determined that bypassing of sewer flow will be required, the bypass pumping <br />system shall have sufficient capacity to pump the peak flow. Sewer bypassing shall <br />conform to Section 6-21 of these Special Provisions. The Contractor shall provide bypass <br />piping for the effluent during the construction of the sewer main between manholes. The <br />inlet of the downstream manhole and the outlet of the upstream manhole shall be plugged. <br />A portable pump shall be installed in the upstream manhole to discharge the effluent from <br />the upstream manhole to the downstream manhole through the bypass piping. Pump and <br />bypass piping shall be of adequate size and capacity to handle the flow without sewage <br />backup occurring to facilities connected to the sewer. <br />For sewers 12-inches in diameter and larger, or where deemed necessary by the City, the <br />following shall apply: <br />All pumps used shall be fully automatic self -priming units. All pumps used must be <br />constructed to allow dry running for long periods of time to accommodate the cyclical <br />nature of effluent flows. The Contractor shall provide the necessary stop/start controls for <br />each pump. The Contractor shall have adequate standby equipment available and ready <br />for immediate operation and use in the event of an emergency or breakdown. One standby <br />pump for each size pump utilized shall be installed at the mainline flow bypassing <br />locations, ready for use in the event of primary pump failure. The Contractor shall <br />continually monitor all pumping equipment. <br />The Contractor shall perform leakage and pressure tests of the bypass pumping discharge <br />piping suing clean water prior to the actual operation. The Water Resources Division shall <br />be given 24 hours notice prior to testing. <br />The Contractor shall be required to flow monitor for a two week period to assist in sizing <br />the pumps necessary for the sewer work and shall be considered included as part of the <br />work. The Contractor shall prepare, with the vendor, a flow monitoring map for key <br />manholes that will provide adequate data for the work subject to review and approval from <br />the Water Resources Division. Flow monitoring shall capture accurate instantaneous <br />depth, velocity and flow data in 15-minute increments or less, or as otherwise approved by <br />the Water Resources Division. The Contractor shall prepare with the vendor a specific, <br />detailed description of the proposed pumping system and submit it and the vendor's <br />references to the City. The Contractor shall submit to the City detailed descriptions <br />outlining all provisions and precautions to be taken by the Contractor regarding handling <br />of existing sewage flows. The submittal must be specific and complete, including such <br />items as schedules, capacities of equipment, materials, and all other incidental protection <br />of the access and bypass pumping locations from damage due to the discharge flows. <br />The submittal shall include but not be limited to the following: <br />1. Sewer plugging method and types of plug. <br />