Project 09 -1752 <br />Request for Approval of Change Order No. 3 <br />February 16, 2012 <br />Page 2 of 2 <br />3. The precast water vault location was changed because it was in conflict with a <br />proposed SCE transmission and distribution pole. This change caused delays to <br />the project. This compensates the contractor for delay costs incurred during the <br />relocation of the vault, including loss of production, stand -by time, and <br />remobilization <br />AGREED COST = $11,424 <br />4. The contract requires the extension of a 24 -inch corrugated metal pipe to connect to <br />a catch basin on the northwest corner of Bristol Street and Warner Avenue. It was <br />discovered that the existing pipe was extremely corroded and needed to be replaced. <br />Prior to replacing the pipe, potholes needed to be excavated to determine the <br />existing utility locations. The work was done on a time and materials basis. <br />FINAL COST = $5,336 <br />APPROVED AS TO FUNDS AND ACCOUNTS: <br />1 ` <br />Raul odinez II, ExIdutive Director Francisco Gutierrez, Executive Director <br />Public Works Agency Finance and Management Services Agency <br />K:\ construction \projects \09 - 1752 \MEM RFA 02 CCO 3 <br />