Project 12-6775 <br />Request for Approval of Change Order No. 1 <br />May 20, 2013 <br />Page 2 of 4 <br />SCHEDULEIMPACT <br />The contract time will be extended by 13 days to allow the contractor time to perform <br />the work included in this change order. The revised completion date will be April 1, <br />2013. <br />APPROVED AS TO FUNDS AND <br />ACCOUNTS: <br />Godinez II, Executive Director <br />Works Agency <br />?' C\M 4 Aa ? ? n <br />Francisco Gutierrez, Executive Director <br />Finance & Management Services Agency <br />Attachment: Change Analysis