<br />Project Name:
<br />Kana Project # 5822 — Irvine Regional Park — Water Main work
<br />Location:
<br />Orange, CA (Jamboree X Santiago Cyn/ TG 800 J -2)
<br />Description:
<br />2 Phases of work: Total: PVC 0900 CL 150 pipe —12" at 1,475LF, 10" at
<br />9,198 LF, 8" at 7,682 LF, 8" FH Lateral 1,682 LF, 6" office at 172 LF,
<br />thrust blocks, bends, 6",8 ",10" and 12" gate valves, 29 fire hydrant
<br />assemblies, and a connection to existing FH, 7ea, 2" Air Vacuum Relief
<br />Valve Assemblies, 10" RPDA, temp connection to water main, water main
<br />abandonments, ; Also includes, mobilization and demobilization, SWPPP,
<br />Traffic Control, Stub Out to Lake, Connect existing Domestic Water,
<br />Abandon Existing Water Lines, Remove and Replace Trench Asphalt
<br />Pavement, SOC Trench Restoration, Potholing of existing Utilities, Arborist
<br />and Tree Protection, Concrete Work, Testing
<br />Total Man - hours:
<br />7,744 total man hours; 6,651 original man-hours budgeted.
<br />Owner:
<br />County of Orange, OCCR / OC Parks
<br />1501 E. St. Santa Ana, CA 92705
<br />Project Manaser: Doug Giltner, Sr, PM, (714•) 425 -8937;
<br />dou . iltner occr.oc og v.eom
<br />Ref: Project No. OCCR12 -007 /Additional Reference: 3`d Part F/T Onsite Inspector = Denis A
<br />Dembik ( "DAD "), QSP, Construction Manager, Harris & Associates 34 Executive Park Suite 150,
<br />Irvine, CA (949) 655 -3900 / C (714) 318 -8706 ddembik@.harri-assoc.com
<br />Contract Amount: $ 2,392,181.90
<br />Start Date: 7/24/12
<br />Date Of Completion: 5/10/13
<br />Kana Pipeline Public Works Resume [Confidential] /Page 14 of 25 as of 1/2015.